AC505 Lesson: Costing Run in Product Cost Planning
Task 2:
CreateacostingrunwiththenameGR##usingcurrentdateasthecostingrundate.
1. EnterthedescriptionGroup##mid-yearcostestimate. Usecostingvariant
PPC1andcostingversion01. Executethecostingrunforcontrollingarea
1000 and company code 1000.
a) Menu→Accounting→Controlling→ProductCostControlling→
ProductCostPlanning→MaterialCosting→CostingRun→Edit
Costing Run (CK40N)
ChoosethefunctionCostingRun→Create.
Enter the following data:
Costing run: GR##
Description: Group##mid-yearcostestimate
Costing run date: Current date
Costing variant: PPC1
Costing version: 01
Controlling area: 1000
Company code: 1000
Choose Continue (Enter)
2. The cost estimate is to bemarked and released today. Make the relevant
date settings.
a) Make the following settings:
Costing date from: Current date
Costing date to: Maximum date
Acceptthedefaultquantitystructuredateandvaluationdate.
3. Save the costing run.
a) SavetherunbychoosingCostingRun→Save.
Note: You are now at the editing stage of the costing
run. Thesystemdisplaystheoverviewof theprocessing
activities to be taken.
Continued on next page
231
2009 © 2009 SAP AG. All rights reserved.
第 250 页 / 共 537 页
Unit6: CostingRun AC505
Task 3:
1. Display theprocessactivitiesforthecosting run andassign yourflexible
selectionlistSelect##formaterialselection. Intheprocessingoptions,turn
offtheindicatorforbackgroundprocessingandsaveyourentries.
a) For flow step Selection, click on the icon within the Parameter
column. Thesystem displaysthe Change Parametersscreen for
the Selection step.
Enter the Selection List Select##.
Deselect the Background processing indicator in the Processing
options area. Save your entries and go back to the Edit Costing
Run screen.
2. Executetheselectionstep. Thepre-selectionofmaterialsshoulddisplaytwo
materialswith thestatusSE (Selectedwithout Errors). Checkthecosting
result in the list of costing levels.
a) YoucannowseetheExecutesymbolintheExecutecolumnforthe
Selectionstep. Clickonthissymboltoproceedwiththisstep.
ExpandtheCostingResults. Selectthecostinglevel1lineandthen
chooseMaterialsOverview. YouwillseethetwomaterialsR-F1##
andR-F2##wereselectedwithouterrorsincostinglevel1.
Task 4:
1. Maintaintheparametersforthenextcostingrunstep,thestructureexplosion.
Turn off theBackground processing indicator, so that the activity can be
executed online.
a) Click on theParameter column for the Structureexplosion step.
Thesystemdisplaysthe ChangeParameters screen forthisstep.
Turn offtheindicatorforbackground processingandsaveyour
entries. GobacktotheEditCostingRunscreen.
2. Nowthatyouhavemaintainedtheparameters,youcanexecutethestructure
explosion step.
a) You can now see theExecute symbol in the Execute column for
theStructureexplosionstep. Clickonthissymboltoproceedwith
this step.
Continued on next page
232
©2009SAPAG.Allrightsreserved. 2009
第 251 页 / 共 537 页
AC505 Lesson: Costing Run in Product Cost Planning
3. Howmanycostinglevelswereselected? Whatisthereasonforthis?
a) Call the Costing Results. You see that three costing levels have
been selected.
Sincenosettingsfortransfercontrolhavebeenmade,thestructure
explosion readstheBOM fortheselectedmaterials. Thesystem
displaysthelevelforfinishedproducts,assemblies, andmaterial
components.
4. Whichnewmaterialsappearinthematerialoverviewofthecostingrun?
a) WithintheCostingResults,selectthethreecostinglevelsandselect
the Materials Overview. In addition to R-F2## and R-F1##, the
following materials are listed:
R-B2##,R-B3##,R-B4##,R-T0##,R-T4##,R-T5##.
(additional components may belisted).
ThesubassemblyR-B1##isnotlistedbecauseduringtheprevious
exercise, astandardcostestimatewasreleasedforR-B1##inthe
current period. Thiscanbe verified byaccessingthelogforthe
structure explosion.
5. ViewtheselectionstatusSEfromthematerialsoverviewlist,bychanging
to the list layout 1SAP01.
a) Remain in the materials overview and choose layout 1SAP01
CalculationResults. Youseethatallthematerialshavethestatus
SE (selected without errors).
Task 5:
Proceed with the costing step.
1. Go into the parameter maintenance for the costing step and turn off the
Backgroundprocessingindicator. Makesurethatthelogissetforcosting
levels.
a) Click on the Parameter column in the Costing step. The system
displaystheChangeParametersscreenforthisstep. Deselectthe
BackgroundprocessingindicatorandselecttheindicatorLogper
costing level
2. After saving thesettings, executecosting.
a) SavethesettingandgobacktotheEditCostingRunscreen. You
can now see the Execute symbol in the Execute column for the
Costingstep. Clickonthissymboltoproceedwiththisstep.
Continued on next page
233
2009 © 2009 SAP AG. All rights reserved.
第 252 页 / 共 537 页
Unit6: CostingRun AC505
3. Fromthematerialsoverview,makesurethatallthematerialsthathavebeen
costed have ayellow or green trafficlight.
a) Call thematerialsoverviewagain intheCosting Resultssection.
Youwillseethatallmaterialshaveeitherayelloworgreentraffic
light.
Task 6:
Younowwanttoanalyzethecostingresultsusingspecialreports.
1. In the analysis parameters, select display variant SAP&11. Using the
parameters, select your costing run GR## with the relevant costing date
and save it.
a) ClickontheParametercolumnfortheAnalysisstep. Selectvariant
SAP&11 Results of Costing Run and choose Enter. The system
displaystheChangeParametersscreenforthisstep.
Enter the following data:
Costing run: GR##
Costing date: Current date
SaveyoursettingsandgobacktotheEditCostingRunscreen.
2. Executetheanalysisandselectalayoutthatcomparesthecostingresultwith
the standard price for every material, in order to see the impact that will
occuriftheseresultsarereleasedasthenewstandardcost.
a) YoucannowseetheExecutesymbolintheExecutecolumnforthe
Analysisstep. Clickonthissymboltoproceedwiththisstep.
Fromthereport,choosetheSelectLayoutsymbolandselectlayout
1SAP03StandardPricevsCostEst/Revaluation. Copythesetting
andcontinuepasttheinformationmessage.
3. Fromthereport,displaytheMulitlevelBOMreport.
a) SelectR-F2##,thenselecttheiconDetailedReport: MultilevelBOM.
Continued on next page
234
©2009SAPAG.Allrightsreserved. 2009
第 253 页 / 共 537 页
AC505 Lesson: Costing Run in Product Cost Planning
Task 7:
1. Markthecostingresults. First,checkwhethermarkinghasbeenallowedin
the current period for your costing variant.
a) Go back to the Edit Costing Run screen and click on the
AuthorizationcolumnfortheMarkingstep. Clickoncompanycode
1000. You see that marking (and release) is allowed for costing
variant PPC1.
Youassignedthiscostingvariantintheparametersforthecosting
run.
Go back tothe Edit Costing Run screen.
2. TurnofftheBackgroundprocessingandtestrunindicatorsintheparameter
settings. Execute the update run.
a) ClickontheParametercolumnfortheMarkingstep. Deselectthe
BackgroundprocessingindicatorandtheTestRunindicatorand
saveyourentries. GobacktotheEditCostingRunscreen.
YoucannowseetheExecutesymbolintheExecutecolumnforthe
Markingstep. Clickonthissymboltoproceedwiththisstep.
Go back tothe Edit Costing Run screen.
3. Fromthematerialsoverview,checkthecostingresultforagivenmaterialby
double-clicking on the material number.
a) Gotothematerialsoverviewinthecostingresults. Double-clickon
anymaterialnumber. Youcananalyzethecostingresultindetail
(multilevelBOM, cost views, itemization).
Go back to the materials overview.
4. Gotothematerialmaster(Costingview2)forthesematerials. Placeyour
cursoronthematerialnumber,clickontherightmousebuttonandgotothe
material master. Make sure that the Future standard cost estimate price
field has been updated.
a) Remaininthematerialsoverview. Placeyourcursoronamaterial.
PresstherightmousebuttonandchooseExtras→Materialmaster.
ScrollalongthetabsuntilyoureachCosting2.
InCosting2,youcanseetheresultofyourmarkingintheFuture
planned price field.
Continued on next page
235
2009 © 2009 SAP AG. All rights reserved.
第 254 页 / 共 537 页
Unit6: CostingRun AC505
Task 8:
1. Finally,releasethecostingresults. Makesurethatreleasewillbecarriedout
onlineandthenexecutetherelease. Donotexecuteatestrun.
a) IntheEditCostingRunscreen,clickontheParametercolumnfor
theReleasestep. DeselecttheBackgroundprocessingandTestrun
indicators. Save your settings and go back to the Edit Costing
Run screen.
YoucannowseetheExecutesymbolintheExecutecolumnforthe
Releasestep. Clickonthissymboltoproceedwiththisstep.
RemaininPriceUpdate: ReleaseStandardPrice.
2. From the Price Update: Release Standard Price list, make sure that all
materials have the status FR (Released without Errors). Navigate to the
materialmasterdirectlyfromthePriceUpdate: ReleaseStandardPricelist
byselectingthematerial. ChecktheresultsofthereleaseintheAccounting
1 and Costing 2 views.
a) The Price Update: Release Standard Price list is immediately
displayed after the release of cost estimates is executed. From
the Price Update: Release Standard Price list, the costing status
is displayed. You will see that all the materials have the status
FR (released without errors).
Remaininthesamelistandclickonanyofthematerialnumbers.
Thiswilltakeyouimmediatelytothematerialmaster. Scrollalong
thetabsuntilyoureachAccounting1andCosting2.
InCosting2, youcanseetheresultofyourreleaseintheCurrent
plannedpricefield. Youcanalsoseethenewstandardpriceinthe
Accounting1tab. AnymaterialsinexistingstocksubjecttoSprice
control arerevaluated with thisprice.
Continued on next page
236
©2009SAPAG.Allrightsreserved. 2009
第 255 页 / 共 537 页
AC505 Lesson: Costing Run in Product Cost Planning
3. FromthePriceUpdate: ReleaseStandardPricelist,displaythefinancial
accounting document for the revaluation of inventory. Which materials
caused the inventorybalanceto berevalued?
a) Scroll to the right of the Price Update: Release Standard Price
list. Selectthedocumentnumberforthepricechange. Theprice
change document lists the old and new price for each material
included in the costing run.
TodisplaytherevaluationdocumentselectAccountingDocuments,
fromthelistofaccountingdocumentsselecttheentryAccounting
document. To display the material number in the accounting
documentchoosethelayout4SAP(chooseSelectdifferentdisplay
varianticon). Aninventoryrevaluationoccurredforamaterialif
there was stock in the warehouse at the time the new standard
price was released.
4. In the Edit Costing Run screen, go to the overview of the costing run in
theScheduleManager todisplaytheactivitiesthatwereperformed inthe
costing run.
a) ReturntotheEditCostingRunscreen,andchooseGoto→Schedule
Manager. Alistoftheactivitiesyouperformedisdisplayed.
237
2009 © 2009 SAP AG. All rights reserved.
第 256 页 / 共 537 页
Unit6: CostingRun AC505
Lesson Summary
You should now be able to:
• Create a costing run
• Createaselectionlistusingflexiblematerialselectionforacostingrun
• Execute a costing run
• Analyze the result of a costing run
• Usethecostingrunefficientlythrougheffectiveerrorhandling
238
©2009SAPAG.Allrightsreserved. 2009
第 257 页 / 共 537 页
AC505 Unit Summary
Unit Summary
You should now be able to:
• Create a costing run
• Createaselectionlistusingflexiblematerialselectionforacostingrun
• Execute a costing run
• Analyze the result of a costing run
• Usethecostingrunefficientlythrougheffectiveerrorhandling
239
2009 © 2009 SAP AG. All rights reserved.
第 258 页 / 共 537 页
UnitSummary AC505
240
©2009SAPAG.Allrightsreserved. 2009
第 259 页 / 共 537 页
AC505 Test Your Knowledge
Test Your Knowledge
1. Theadministrativedatainacostingrunshouldneverbedeleted.
Determinewhetherthisstatementistrueorfalse.
□ True
□ False
2. Whichparametersarerequiredtocreateacostingrun?
3. Whichactivitiesareinvolvedinflexiblematerialselection?
4. Whatistheuseofbackgroundprocessinginacostingrun?
5. List the three reports available for analyzing the results of a processing
activity.
6. Youshouldprintthelogateachstageofalargecostingrun.
Determinewhetherthisstatementistrueorfalse.
□ True
□ False
241
2009 © 2009 SAP AG. All rights reserved.
第 260 页 / 共 537 页
TestYourKnowledge AC505
Answers
1. Theadministrativedatainacostingrunshouldneverbedeleted.
Answer: False
Afteracostingrunanditsprocessingactivitiesarecompletedsuccessfully,
itcanbedeleted. Theadministrativedatainthecostingrunisalsodeleted.
2. Whichparametersarerequiredtocreateacostingrun?
Answer: Yourequirethefollowingparameterstocreateacostingrun:
• Company code
• Costing variant
• Costing dates
3. Whichactivitiesareinvolvedinflexiblematerialselection?
Answer: You will need to perform the following activities to perform
flexible material selection:
• Providenameandshorttext of SelectionList
• Enter selection parametersfor materials
• Execute material selection
• Manuallyaddordeletematerialsincludedintheselectionlist
• Usetheselectionlistwithmaterialselectionforacostingrun
4. Whatistheuseofbackgroundprocessinginacostingrun?
Answer: The Background processing option enables you to specify if
processing should take place online or in the background. When you
chooseExecute, thesystemeitherstartstheactivity or schedulesitin the
background, as applicable.
5. List the three reports available for analyzing the results of a processing
activity.
Answer: To analyzethe results of a processing activity, you can use the
following three reports:
• Costing Levels
• Material List
• Analysis
242
©2009SAPAG.Allrightsreserved. 2009
第 261 页 / 共 537 页
AC505 Test Your Knowledge
6. Youshouldprintthelogateachstageofalargecostingrun.
Answer: False
Youcanprintthelogateachstageofacostingrun. Inalargecostingrun,
printingateachstageincreasestheprocessingtimeandusesaconsiderable
amountofthesystem'sresources(spools). Itisagoodideatosavethelog
and analyze it later.
243
2009 © 2009 SAP AG. All rights reserved.
第 262 页 / 共 537 页
Unit6: CostingRun AC505
244
©2009SAPAG.Allrightsreserved. 2009
第 263 页 / 共 537 页
第 264 页 / 共 537 页
第 265 页 / 共 537 页
Unit 7
Other Costing Functions
Unit Overview
Thisunitexplainsthepurposeoftransfercontrolandhowtomakethenecessary
customizingsettings. Itdescribestheuseandbenefitofgroupcostingandexplains
howtouseadditivecoststoenhanceamaterialcostestimate.
Unit Objectives
After completing thisunit, you will beableto:
• Describe the purpose of transfer control
• Define possibletransfer control strategies
• Identify theuse andbenefit of group costing
• Describetheuseofadditivecoststoenhanceamaterialcostestimate
Unit Contents
Lesson: Transfer Control.......................................................246
Exercise 11: Transfer Control.............................................253
Lesson: Group Costing.........................................................259
245
2009 © 2009 SAP AG. All rights reserved.
第 266 页 / 共 537 页
Unit7: OtherCostingFunctions AC505
Lesson: Transfer Control
Lesson Overview
This lesson explains the purpose of transfer control. It also describes how to
customize transfer control.
Lesson Objectives
After completingthislesson, you will beable to:
• Describe the purpose of transfer control
• Define possible transfer control strategies
Business Example
Duringthefiscalyear,whencreatinganewcostestimateforafinishedgood,you
wanttovaluethesub-assembliesusingthereleasedstandardcostestimatevalue.
Youdonotwantthesystemtocalculateanewcostforanysubordinatematerial
that already has a released cost estimate.
Youwillusetransfercontroltoaccomplishthisrequirement.
Purpose of Transfer Control
Figure 103: Transfer Control – Purpose
InCustomizingfortransfercontrol,youcanspecifywhatcostestimatesareused.
246
©2009SAPAG.Allrightsreserved. 2009
第 267 页 / 共 537 页
AC505 Lesson: Transfer Control
You can define a strategy in the transfer control for transferring the following
cost estimates:
• Future,current,previousstandardcostestimates(costingtype01).
• Costestimateswithperiod-basedtransfer control(costestimateswith the
samekey-thatis,withthesamecostingvariant,version,and,ifapplicable,
period).
Youcan define such astrategyfor thefollowing:
• Transfer of cost estimatesin thesameplant.
• Transfer of cross-plant cost estimates.
Application of Transfer Control
• MaterialCost EstimatewithQuantityStructure
– Newproductwith90%existingassembliesandrawmaterials
• MaterialCostEstimateWithoutQuantityStructure
– Valuation of material item
• Costing Run
– Selection
– BOM explosion
• Cross-Company Costing
– Cross-plant
– Cross-company-code
• Reference Variant
Figure104: Application: MaterialCostEstimatewithQtyStructure
247
2009 © 2009 SAP AG. All rights reserved.
第 268 页 / 共 537 页
Unit7: OtherCostingFunctions AC505
Whenyoucosta newproduct, you canavoid having tocosttheentire product
structure again by automatically transferring existing, such as released, cost
estimatesfor assemblies and raw materials.
InCustomizingfortransfercontrol,youcanspecifywhatcostestimatesareused.
Thekeyfortransfercontrolisassignedtothecostingvariant.
Requirement: Youmustusethesamecostcomponentstructure.
Figure105: Application: MaterialCostEst. WithoutQtyStructure
Inmaterialcostingwithoutaquantitystructure,oneofthetransferstrategiesinthe
costingvariantspecifiesthefollowingsequenceformaterialitems:
• The system first searches for a material cost estimatein accordance with
transfer control.
• Itthenproceedsaccordingtothematerialvaluationstrategy.
This applies to the following:
• Manual entry of a material item.
• When making entries using Cut, Copy and Paste This does not apply to
multi-levelunitcostingwhenyouaretransferringusingdrag-and-drop. In
suchcases,youcanonlytransferthecostestimateastheoriginalorasacopy.
248
©2009SAPAG.Allrightsreserved. 2009
第 269 页 / 共 537 页
AC505 Lesson: Transfer Control
Figure 106: Application: Costing Run
Exampleofapplication: Youwanttoensurethat allthematerialsinyour plant
haveastandardcostestimate. Tothisend,youdefineatransfercontrolIDwhose
sole strategy is to find a current standard cost estimate. After selection (and
structure explosion), you receive all the materials that do not have a current
standard cost estimate.
IntheGeneralDatasectionofthecostingrun,thetransfercontrolIDisproposed
from the costing variant.
Selection: When selecting, the system also checks if a material cost estimate
alreadyexistsforthematerialinaccordancewithtransfercontrol. Ifoneexists,
thematerialisnotincludedintheselection. Intheaboveexample,PumpP-100is
not selected.
Exception: IfyouselectAlwaysrecalculate,thecheckstepwithtransfercontrol
does not apply.
Structureexplosion: The BOMs areexplodedfor theselectedmaterials. The
systemthenchecksifmaterialcostestimatesaccordingtotransfercontrolexistfor
thecomponents. Ifcostestimatesexist,thecomponentsarenotincludedandare
notfurtherexploded. Intheaboveexample,thisappliestoShaft100-300.
Therefore,intheaboveexampleamaterialcostestimateiscreatedforSh. metal
NEW and Pump NEW only.
249
2009 © 2009 SAP AG. All rights reserved.
第 270 页 / 共 537 页
Unit7: OtherCostingFunctions AC505
Figure 107: Application: Cross-Plant Costing
Exampleofapplication: Thereareoftendifferencesbetweentheproductionplant
andthesalesplant. Thecostestimateinthesalesplantshouldexactlymatchthe
material cost estimate in the production plant.
Inthisexample,Shaft100-300isproducedinplantY.Differentcostingvariants
are used in the plants.
If,inaccordancewithtransfercontrol,acostestimateisfoundintheotherplant,
its cost component split istransferred directly.
Requirement: Youmustusethesamecostcomponentstructure.
Thenextunitcovershowcross-plantcostingiscontrolled.
250
©2009SAPAG.Allrightsreserved. 2009
第 271 页 / 共 537 页
AC505 Lesson: Transfer Control
Figure 108: Application: Cross-Company Costing
When you cost across company codes, an important factor is whether
cross-companycostinghasbeenallowedinCustomizing.
Notallowed: AlthoughShaft100-300hasacostestimateintheCanadianplantY,
thematerialShaft100-300wasvaluatedintheUSplantXinaccordancewiththe
materialvaluationstrategy. Thetransfercontrolisnottakenintoaccount.
Allowed: See cross-company costing. Here, the cost component split data is
intended to be retained beyond the company code for internal cost accounting
reasons.
251
2009 © 2009 SAP AG. All rights reserved.
第 272 页 / 共 537 页
Unit7: OtherCostingFunctions AC505
Figure 109: Application: Reference Variant
Example of application: Suppose you want to create a modified standard cost
estimatebasedonexactlythesamequantitystructureasthestandardcostestimate.
Thepurposeistoindicatehowtheloweractualpricesinthecostcenterareaofthe
previousmonthwerereflectedintheproductspectrum.
Thereferencevariantallowsyoutocreatenewmaterialcostestimatesorcosting
runsfromexistingmaterialcostestimateswithitemizations,inorderto:
• Preventrepetitionofthequantitystructuredeterminationandexplosionsteps.
• Carryoutalternativeornewvaluationsbasedonexactlythesamequantity
structure.
The followingis entered in the referencevariant:
• Whichmaterialcostestimatesshouldbesearchedfor(transfercontrol).
• Which costing itemsshould be revaluated.
ThereferencevariantisassignedtothecostingvariantinCustomizing.
Amaterialcostestimategeneratedbyareferencevariantisalwaysindicatedasa
material cost estimate with quantity structure.
252
©2009SAPAG.Allrightsreserved. 2009
第 273 页 / 共 537 页
AC505 Lesson: Transfer Control
Exercise 11: Transfer Control
Exercise Objectives
After completingthisexercise, youwillbeableto:
• Use transfer control
• Define wheretransfer control canbeentered
• Define the possible transfer strategies
Business Example
Whenyoucostfinishedgoods,youwanttopreventsubordinateassembliesfrom
beingrecosted, providedareleasedcostestimatealreadyexists. You,therefore,
usethetransfercontrolfunction. Sincealltheassembliesofyourfinishedproduct
areproducedinthesameplant,youusetheplant-specifictransferstrategy.
Task 1:
InthePriceUpdateunit,youcreatedacostestimateforpumpR-F1##. Thepump
consistsofseveralassemblies,includingtheassemblyforthecasing(R-B1##).
Having already updated the result of the standard cost estimate for assembly
R-B1##bymarkingandreleasing, youcannowaccessthisresultbycreatinga
newcostestimateforpumpR-F1##. Youhavemarkedandreleasedtheresults
oftheotherassembliesofthepumpinthecostingrunexercise, soyoucanalso
access these results.
1. GointothematerialmasterofyourcomponentR-B1##(Costingview2)and
makesure thattheresult of thecurrent posting periodwasupdated inthe
Current planned price field.
2. Createacostestimatefor product R-F1##. Useatransfer control ID that
enablesyoutoutilizetheexistingcostestimatesforyourcomponents. Select
costingvariantPPC1, plant1000, costinglotsize100pieces, andcosting
version2. Thecostestimateshouldbevalidfromthefirstdayofthenext
period. ThecostestimateshouldbevaliduntilDecember31,2010. Accept
thedefaultquantitystructuredateandvaluationdate.
3. What isthe error statusof your cost estimate?
4. The costing result of your subordinate components is shown in the
itemization. Wherecanyoucheckthatthematerialswerenotrecosted?
5. Save the result.
Continued on next page
253
2009 © 2009 SAP AG. All rights reserved.
第 274 页 / 共 537 页
Unit7: OtherCostingFunctions AC505
Task 2:
Intheaboveexercise,youenteredthetransfercontrolIDdirectlyintherequest
screen of the cost estimate.
1. Howcanyouenteritcentrally? Recordtherelevantmenuoption.
2. Whatdoyouhavetotakeintoaccountwhentransfercontrolissetcentrally?
3. What are the prerequisites for transfer control to access existing cost
estimates?
254
©2009SAPAG.Allrightsreserved. 2009
第 275 页 / 共 537 页
AC505 Lesson: Transfer Control
Solution 11: Transfer Control
Task 1:
InthePriceUpdateunit,youcreatedacostestimateforpumpR-F1##. Thepump
consistsofseveralassemblies,includingtheassemblyforthecasing(R-B1##).
Having already updated the result of the standard cost estimate for assembly
R-B1##bymarkingandreleasing, youcannowaccessthisresultbycreatinga
newcostestimateforpumpR-F1##. Youhavemarkedandreleasedtheresults
oftheotherassembliesofthepumpinthecostingrunexercise, soyoucanalso
access these results.
1. GointothematerialmasterofyourcomponentR-B1##(Costingview2)and
makesure thattheresult of thecurrent posting periodwasupdated inthe
Current planned price field.
a) Menu→Logistics→MaterialsManagement→MaterialMaster→
Material→Display→DisplayCurrent(MM03)
EntermaterialR-B1##andchooseSelectview(s).
SelectCosting2andchooseContinue(Enter).
Enterplant1000andchooseContinue(Enter).
In theCurrentplannedpricefield, you can seetheresult of your
markingandreleasefromthecurrentpostingperiod.
2. Createacostestimatefor product R-F1##. Useatransfer control ID that
enablesyoutoutilizetheexistingcostestimatesforyourcomponents. Select
costingvariantPPC1, plant1000, costinglotsize100pieces, andcosting
Continued on next page
255
2009 © 2009 SAP AG. All rights reserved.
第 276 页 / 共 537 页
Unit7: OtherCostingFunctions AC505
version2. Thecostestimateshouldbevalidfromthefirstdayofthenext
period. ThecostestimateshouldbevaliduntilDecember31,2010. Accept
thedefaultquantitystructuredateandvaluationdate.
a) Menu→Accounting→Controlling→ProductCostControlling→
Product Cost Planning→MaterialCosting→Cost Estimatewith
Quantity Structure→ Create(CK11N)
Enter the following:
Material: R-F1##
Plant: 1000
Costing variant:PPC1
Costing version: 2
Costing lot size: 100
Transfer control: PC02
GototheDatestab. SelectDefaultValuesicon.
Change the default dates asfollows:
Costingdatefrom: Acceptdefaultoffirstdayofnextmonth.
Costing dateto: December 31, 2010
Acceptthedefaultquantitystructuredateandvaluationdate.
ChooseEnter. Thesystemexecutesthecostestimateautomatically.
3. Whatis the error statusof your cost estimate?
a) Go to theCosting datatab. The statusshould be Costed without
errors.
4. The costing result of your subordinate components is shown in the
itemization. Wherecanyoucheckthatthematerialswerenotrecosted?
a) Choose Goto → Material Overview. Only the material R-F1##
is displayed. Since the subordinate assemblies and material
componentswerenotrecosted,theyarenotlisted.
5. Save the result.
a) Go backto theoverviewof thecostestimateand savetheresult
with all options selected.
Continued on next page
256
©2009SAPAG.Allrightsreserved. 2009
第 277 页 / 共 537 页
AC505 Lesson: Transfer Control
Task 2:
Intheaboveexercise,youenteredthetransfercontrolIDdirectlyintherequest
screen of the cost estimate.
1. Howcanyouenteritcentrally? Recordtherelevantmenuoption.
a) Transfercontrolcanbeenteredcentrallyinthecostingvariant.
MenuTools→Customizing→IMG→ExecuteProject(SPRO)
Select SAP Reference IMG
SAPCustomizingImplementationGuide→Controlling→Product
CostControlling→ProductCostPlanning→MaterialCostEstimate
withQuantityStructure→DefineCostingVariants
2. Whatdoyouhavetotakeintoaccountwhentransfercontrolissetcentrally?
a) Whenyousettransfercontrolcentrally,youcandecidewhetheror
notitcanbechangedintheapplication. Youmakethesettingin
CustomizingforthecostingvariantintheQuantityStructuretab.
3. What are the prerequisites for transfer control to access existing cost
estimates?
a) Whenyouusetransfercontrol, thecostestimatesmustbebased
onthesamecostcomponentstructure. Thismeansthatthesame
costcomponentstructuremustbeassignedtoeachcostingvariant
of the company code or plant.
257
2009 © 2009 SAP AG. All rights reserved.
第 278 页 / 共 537 页
Unit7: OtherCostingFunctions AC505
Lesson Summary
You should now be able to:
• Describe the purpose of transfer control
• Define possible transfer control strategies
258
©2009SAPAG.Allrightsreserved. 2009
第 279 页 / 共 537 页
AC505 Lesson: Group Costing
Lesson: Group Costing
Lesson Overview
Thislessonexplainstheuseandbenefitofgroupcosting. Italsoexplainshowto
useadditivecoststoenhancematerialcost estimates.
Lesson Objectives
After completingthislesson, youwillbeable to:
• Identify theuse andbenefit of group costing
• Describetheuseofadditivecoststoenhanceamaterialcostestimate
Business Example
Someofyour subassembliesaresupplied by other company codeswithinyour
controllingarea. Youwouldliketousegroupcostingtodeterminethecontribution
of each company code to the products cost.
Cost Component Split by Partner
Figure 110: Cost Component Split by Partner
ThereportshowsanexampleofagroupcostestimateforProductP-102.
Groupcostingdisplaystheproportionofproductcoststhatareincurredoverseas.
Thisenablesyoutoanticipatetheeffectofexchangeratechangesonproductcosts.
It shows the contribution of each plant to product costs. This can help decide
where to produce products and whether or not to shift production from one
location to another.
259
2009 © 2009 SAP AG. All rights reserved.
第 280 页 / 共 537 页
Unit7: OtherCostingFunctions AC505
It shows the contribution of each profit center and business unit to product
costs. This showshow internal suppliers addvalue toyour product and which
organizationalunithasthemostpotentialtoreducecosts.
Based on thestructureof your company, you can interactively change the sort
order of the partners.
Figure 111: Cost Component Split by Partner
Groupcostinggeneratesparallelcostcomponentsplitsforeachmaterialwiththe
valueaddedbyeachpartnerintheproductionprocess. Thesystemautomatically
determinesthepartnerthatsuppliedtheresource,suchascompany,plant,profit
center, businessarea, whenit coststhat resource.
A separate cost component split is generated for each partner. In the above
example,thecostcomponentforeachplantinvolvedinthemanufactureofR-1000
is displayed in a different color.
Ifyoudonotneedsuchahighlevelofdetail, thevalueaddedbyotherpartners
canbedisplayedasasubtotalunderthevalueaddedbythedirectpartner.
Group costing can be used only if all the companies are assigned to the same
controlling area.
Youdefinewhetherornotyouwanttocalculateandstorecostcomponentsplits
by partners in Customizing. To do this, you can define a partner version and
assignthistothecostingtype. Thepartnerversionspecifiesthelevelofdetailin
whichyouwanttomaintainpartnerinformation,suchascompanycode,business
area, plant, and profit center.
260
©2009SAPAG.Allrightsreserved. 2009
第 281 页 / 共 537 页
AC505 Lesson: Group Costing
Additive Costs
Figure 112: Additive Costs
Uses of additive costing:
• Adding known costs to the material cost estimate with quantity structure
thatarenot containedinthequantitystructure. Intheaboveexample, the
costs are transport or insurance costs.
• When valuating material components, you can include manual costs for
eachmaterialpriceoruseonlymanualcosts(ascontrolledbythevaluation
variant).
• Transferringcostestimatesfromnon-SAPERP.
Anadditivecostestimateisinsertedinacostestimatewithquantitystructure. You
useunitcostingfunctionstocreatetheadditivecostestimate.
The costing variant determines if the additive cost estimate is included in an
automaticcostestimate. Thecostingtype, valuationvariant,andversionofthe
automaticcostestimateshouldcorrespondwiththoseofthemanualcostestimate.
Thequantitystructuredateof theautomaticcost estimateshouldbewithinthe
validity range of the manual cost estimate.
Costelementsarerequiredtohandleadditivecosts(suchasapplyingoverhead).
One cost element is assigned for each cost component (in the settings for the
costcomponentstructure). Youcanalsodistinguishbetweencostelementsusing
origin groups.
261
2009 © 2009 SAP AG. All rights reserved.
第 282 页 / 共 537 页
Unit7: OtherCostingFunctions AC505
Figure 113: Updating Additive Costs
Thecostscalculatedinanadditivecostestimateareaddedtothecostscalculated
inanautomaticcostestimatethenexttimecostingisperformed.
The costing variant determines if an additive cost estimate is included in an
automatic cost estimate.
The costingtype, valuation variant, andversionof the automatic cost estimate
shouldmatchthoseoftheadditivecostestimate. Thequantitystructuredateof
the automaticcost estimateshould be within the validity range of the additive
cost estimate.
When valuing material components, you can include additive costs for each
materialpriceoruseonlyadditivecosts,ascontrolledbythevaluationvariant.
Cost elements are required to handle additive costs, for example, to apply
overhead. Onecost element is assigned toeach cost component. You can also
distinguishbetweencostelementsusingorigingroups.
262
©2009SAPAG.Allrightsreserved. 2009
第 283 页 / 共 537 页
AC505 Lesson: Group Costing
Lesson Summary
You should now be able to:
• Identify theuse andbenefit of group costing
• Describetheuseofadditivecoststoenhanceamaterialcostestimate
263
2009 © 2009 SAP AG. All rights reserved.
第 284 页 / 共 537 页
UnitSummary AC505
Unit Summary
You should now be able to:
• Describe the purpose of transfer control
• Define possible transfer control strategies
• Identify theuse andbenefit of group costing
• Describetheuseofadditivecoststoenhanceamaterialcostestimate
264
©2009SAPAG.Allrightsreserved. 2009
第 285 页 / 共 537 页
AC505 Test Your Knowledge
Test Your Knowledge
1. What are the prerequisites for transfer control to access existing cost
estimates?
2. The use of the transfer control key is determined by the
.
Fillintheblankstocompletethesentence.
3. Costelementsarerequiredtohandleadditivecosts.
Determinewhetherthisstatementistrueorfalse.
□ True
□ False
4. Whatdoesthereportusingacostcomponentsplitbypartnershow?
265
2009 © 2009 SAP AG. All rights reserved.
第 286 页 / 共 537 页
TestYourKnowledge AC505
Answers
1. What are the prerequisites for transfer control to access existing cost
estimates?
Answer: Whenyouusetransfercontrol,thecostestimatesshouldbebased
onthesamecostcomponentstructure. Thesamecostcomponentstructure
shouldbeassignedtoeachcostingvariantofthecompanycodeorplant.
2. Theuseofthetransfercontrolkeyisdeterminedbythecostingvariant.
Answer: costing variant
3. Costelementsarerequiredtohandleadditivecosts.
Answer: True
Costelementsarerequiredtohandleadditivecosts.
4. Whatdoesthereportusingacostcomponentsplitbypartnershow?
Answer: The report shows:
• Theproportionofproductcostsincurredoverseas.
• Thecontributionofeachplanttoproductcosts.
• Thecontributionofeachprofitcenterandbusinessunittoproductcosts.
266
©2009SAPAG.Allrightsreserved. 2009
第 287 页 / 共 537 页
第 288 页 / 共 537 页
第 289 页 / 共 537 页
Unit 8
Further Valuation Methods
Unit Overview
Thisunitexplainshowtoexecuteamixedcostestimateandmaketherequired
settings. It describes the types, purpose, and control of special procurement.
Theunitalsodifferentiatesbetweensubcontractingandexternalprocessingand
explains how to use them in Product Cost Planning. Theunit explainshow to
accessthePurchasingdataforrawmaterialcostingandmaketherequiredsettings.
Italsodescribesthevariousscrapcategoriesandtheirinfluenceonthecostsfor
materialsandproductionactivities. Itexplainshowtoexecuteacostestimatefor
a configured material.
Unit Objectives
After completing thisunit, you will beableto:
• Create procurement alternatives
• Maintain Mixing Ratios
• Execute a mixed cost estimate
• Interpret the resultsof mixed cost estimate
• Describethepurposeandrelevanttypesofspecialprocurement
• Define Phantom Assembly
• Explainthedifferencebetweensub-contractingandexternalprocessing
• Implement control on sub-contracting
• Describe the master data for external processing and valuating external
processing
• AccessthePurchasingdataforrawmaterialcosting
• Use cost components to distinguish between different elements of the
procurement costs for purchasing
• Distinguishbetweenthedifferentscrapcategoriesandhowtheyaffectthe
cost of the materials andproductionactivities
• Maintain the scrap rate for an assembly
• Executeacostestimatethatincludesassemblyscrap
• Compare the results of two cost estimates
• Describe variant configuration
267
2009 © 2009 SAP AG. All rights reserved.
第 290 页 / 共 537 页
Unit8: FurtherValuationMethods AC505
• Executeacostestimatefor aconfiguredmaterial
Unit Contents
Lesson: Mixed Costing.........................................................269
Exercise 12: Mixed Costing...............................................275
Lesson: Special Procurement.................................................282
Lesson: Subcontracting and External Processing..........................286
Exercise 13: Subcontracting..............................................291
Lesson: Raw Material Costing ................................................301
Exercise 14: Raw Material Costing ......................................307
Lesson: Scrap...................................................................313
Exercise 15: Scrap Categories and their Effect ........................323
Lesson: Variant Configuration.................................................329
268
©2009SAPAG.Allrightsreserved. 2009
第 291 页 / 共 537 页
AC505 Lesson: Mixed Costing
Lesson: Mixed Costing
Lesson Overview
Thislessonexplainshowtocreateprocurementalternatives. Itexplainshowto
maintainmixingratiosandexecuteamixedcostestimate. Italsoexplainshowto
interpret the results of a mixed cost estimate.
Lesson Objectives
After completingthislesson, youwillbeable to:
• Create procurement alternatives
• Maintain Mixing Ratios
• Execute a mixed cost estimate
• Interpret the resultsof mixed cost estimate
Business Example
Your company usually manufactures assemblies for the pump in-house, but
for certain semi-finished products, thein-house manufacturing capacity isnot
sufficienttomeetthedemand. Consequently, youneedtoprocureapercentage
of these products from external vendors. Until now, costing was based on the
assumptionof100%in-houseproduction. Managementnowrequiresthatcosting
reflect the current practice of meeting part of the demand through external
procurement. You need to understand mixed costing using a material for an
example.
269
2009 © 2009 SAP AG. All rights reserved.
第 292 页 / 共 537 页
Unit8: FurtherValuationMethods AC505
Process Flow
Figure 114: Mixed Costing: Process Flow
Quantitystructuretype: Youusethequantitystructuretypetomanagemixing
ratios. Foreachquantitystructuretype, youcanspecifyifmixingratioscanbe
maintained:
• Per fiscal year
• Per period
• Without reference to a period
Assignment to costing version: To create a mixed cost estimate, you need to
assignthequantitystructuretypesinthecostingversion. Thisensuresthatvarious
quantity structures or mixing ratios can also be costed using various costing
versions.
270
©2009SAPAG.Allrightsreserved. 2009
第 293 页 / 共 537 页
AC505 Lesson: Mixed Costing
Procurement Alternatives
Figure 115: Procurement Alternatives
A material can be manufactured using various processes and procured from
various supply sources.
The priceof a material isaffectedby the supply source or production process.
Consequently, any valuation and/or costing of the material should take these
factors into account.
To do this, you need to create one or more procurement alternatives for each
process category.
Example1: Therearetworegularvendors,AandB,formaterialX,whichisan
importantmaterialthatyouprocureonlyexternally. Youcreatetwoprocurement
alternativesfortheprocesscategoryPurchaseorderforvendorsAandBandenter
thenormalpurchasequantityasthecostinglotsize.
Example2: YouproducemostofmaterialYusingtwoproductionversions,01and
02. TherestofthematerialisprovidedbyplantZ.Youcreatetwoprocurement
alternativesfortheprocesscategoryProduction,forproductionversion01,which
hasthelotsizenandproductionversion02, whichhasthelotsizem. Youalso
create another procurement alternative for process category Stock transfer in
respectofplantZwiththeremainingstocktransferquantityasthecostinglotsize.
Note: IfyouuseproductcostcollectorsformaterialsinCostObjectControlling,
verifyifyouuseproductionversionsorBOMsandroutingswhenyoucreatethe
procurementalternatives. Formoreinformation,refertotheSAPLibraryunder
Cost Object Controlling.
271
2009 © 2009 SAP AG. All rights reserved.
第 294 页 / 共 537 页
Unit8: FurtherValuationMethods AC505
Figure 116: Processing Procurement Alternatives
Theleft-handsidegroupsprocurementalternativesunderprocesscategoriesand
enables quick navigation.
On the right side, you can maintain data for the procurement alternative to be
selected or created.
Dependingontheprocesscategory,youcanmakevariousentriesinthedatafor
the procurement alternative.
Mixed Cost Estimate
Figure 117: Mixing Ratios
272
©2009SAPAG.Allrightsreserved. 2009
第 295 页 / 共 537 页
AC505 Lesson: Mixed Costing
Procurementalternativesareweightedbyequivalencenumbers.
You maintain the equivalence numbers in % or in numerical form for each
procurement alternative.
If you turned on the 100% check indicator in the quantity structure type, the
equivalence numbers should total 100.
Intheaboveexample, mixingratiosareenteredintwoquantitystructuretypes
for the same material.
• QuantitystructuretypeAenablesmixingratiostobemaintainedonafiscal
year basisandisassignedto costingversion01.
• QuantitystructuretypeBdoesnotdependontimeandisassignedtocosting
version 02.
Figure 118: Mixed Cost Estimate
When a material cost estimate is executed, the system first determines the
procurement alternatives from the quantity structure type and then costs
them individually, generating a cost component split and itemization for each
alternative. Thecostinglotsizeistakenfromtheprocurementalternative.
Thesystemcreatesamixedcostestimateforthematerialusingthemixingratios.
273
2009 © 2009 SAP AG. All rights reserved.
第 296 页 / 共 537 页
Unit8: FurtherValuationMethods AC505
Figure 119: Mixed Cost Estimate Results
The costed multi-level BOM displays one row of data for each procurement
alternative. Thequantitiesaredisplayedasaproportionofthecostedmixingratio.
You can branch from here to detail reports.
Display cost estimate: This indicator in the cost estimatespecifiesthat it is a
mixedcostestimateorthatacostedprocurementalternativeisdisplayed.
Theexplanationfacilitiesprovidequickaccesstotherelevantdataofthemixed
cost estimate.
InformationSystem: Intheobjectlist,multi-levelBOM,anditemizationreports,
youcanincludethemixedcostingorprocurementalternativecharacteristicsin
the personal display variants.
If you directly call a detail report for the material cost estimate by choosing
Extras, youcanaccessaspecificprocurementalternative.
Recommendation: To analyze individual cost estimates for procurement
alternatives,navigatethroughobjectlistsorthecostedmulti-levelBOM.