第 41 页 / 共 543 页
AC405 Lesson: Cost Centers
InCustomizing,youcandefinelockindicatorsforeachcostcentercategory,or
specify that the managing of quantities on cost centers is allowed. When you
assignacostcenter toaparticularcategory(youdothiswhencreatingthecost
center),thecorrespondinglockindicatorsandallowedvaluesforthiscategoryare
proposed as default valuesfor thiscost center.
Figure13: ExerciseTasks: StructuringtheExampleEnterprise
29
2009 © 2009 SAP AG. All rights reserved.
第 42 页 / 共 543 页
Unit2: MasterData AC405
30
©2009SAPAG.Allrightsreserved. 2009
第 43 页 / 共 543 页
AC405 Lesson: Cost Centers
Exercise 2: Cost Centers
Exercise Objectives
After completingthisexercise, youwillbeableto:
• Display the standard hierarchy.
• Createcostcentersfortheconsultingdepartment.
Business Example
Theorganizationalstructureofyourconsultingdepartmentisalreadymappedin
thestandardhierarchyofthecontrollingarea. Younowneedtoassignthesixcost
centersthatyouhavereservedfortheconsultingdepartmenttothecorresponding
hierarchy nodes.
31
2009 © 2009 SAP AG. All rights reserved.
第 44 页 / 共 543 页
Unit2: MasterData AC405
Task 1:
Figure14: Standardhierarchyofthe consultingdepartment
1. Displaythestandardhierarchyofyourcompanyandcheckthatthenodes
correspond to those in the above graphic.
Task 2:
Createcostcentersfortheconsultingdepartment. Thecostcentersshouldbevalid
fromthefirstdayofthecurrentfiscalyearuntilthedefaultvalidtodate. Assign
allthecostcenterstotheGermansubsidiary(Companycode1000).
1. Create the cost centers Telephone, Organization, IT Services and FI/CO
Consulting directly in the standard hierarchy. Use the above graphic as
a guide. When you create the master data for each cost center, use the
following information:
Continued on next page
32
©2009SAPAG.Allrightsreserved. 2009
第 45 页 / 共 543 页
AC405 Lesson: Cost Centers
Figure 15: Dataforcreatingthecostcentermasterdata
2. To keep data input to a minimum, create the cost center “Motor Pool”
by copying the cost center “IT Services” anduse the cost center “FI/CO
Consulting”tocreatethecostcenter“LOConsulting”. Eventhoughyou
candothisdirectlyinthestandardhierarchy,tryusingthemenuentriesin
the application menu.
Remembertochangethenameofthecostcenterandthepersonresponsible
each time.
Figure 16: Dataforcreatingthecostcentermasterdata
Continued on next page
33
2009 © 2009 SAP AG. All rights reserved.
第 46 页 / 共 543 页
Unit2: MasterData AC405
3. Displayoneofthecostcenters. Whichcurrencydoesthecostcenteruse?
Wheredoesthisentryincostcentermasterdataoriginatefrom?
4. Displaythecontrolindicatorforthecostcenteryouhavecalledup. Where
doesthisinformationcomefrom? Canthisinformationbechangedinthe
master data?
5. Becauseallyourcostcentersarelocatedincontrollingarea1000anduse
the object currency EUR, you don’t want to seethisinformation onthe
overview screen in the standard hierarchy.
34
©2009SAPAG.Allrightsreserved. 2009
第 47 页 / 共 543 页
AC405 Lesson: Cost Centers
Solution 2: Cost Centers
Task 1:
Figure 17: Standard hierarchyoftheconsultingdepartment
1. Displaythestandardhierarchyofyourcompanyandcheckthatthenodes
correspond to those in the above graphic.
Answer: Cost Center Accounting: Master Data → Standard Hierarchy
→ Display
The organizational structure of the consulting department appears under
nodeH-AC405. Expand the individual nodesunder your group SERV##
and then expand B##.
Task 2:
Createcostcentersfortheconsultingdepartment. Thecostcentersshouldbevalid
fromthefirstdayofthecurrentfiscalyearuntilthedefaultvalidtodate. Assign
allthecostcenterstotheGermansubsidiary(Companycode1000).
1. Create the cost centers Telephone, Organization, IT Services and FI/CO
Consulting directly in the standard hierarchy. Use the above graphic as
a guide. When you create the master data for each cost center, use the
following information:
Continued on next page
35
2009 © 2009 SAP AG. All rights reserved.
第 48 页 / 共 543 页
Unit2: MasterData AC405
Figure18: Dataforcreating thecost centermasterdata
a) Cost Center Accounting: Master Data → Standard Hierarchy →
Change
b) PlaceyourcursoronthehierarchyareaB10##towhichthecostcenter
istobeassignedandchooseEdit→CreateCostCenter
FieldNameorDataClass Values
Cost Center 101##
Valid from 01.01. Currentfiscalyear
To 31.12.9999
Description Telephone
Owner Smith
Cost center category 9
Choose"Organization"toenterthedataontheorganizationalunits.
FieldNameorDataClass Values
Company Code 1000
Business Area IS##
Profit Center 1402
Save your data!
Repeattheproceduretocreatetherestofthecostcenters.
Bear in mind that they may be assigned to different areas of the
hierarchy.
Continued on next page
36
©2009SAPAG.Allrightsreserved. 2009
| FieldNameorDataClass | Values |
|---|---|
| Cost Center | 101## |
| Valid from | 01.01. Currentfiscalyear |
| To | 31.12.9999 |
| Description | Telephone |
| Owner | Smith |
| Cost center category | 9 |
| FieldNameorDataClass | Values |
|---|---|
| Company Code | 1000 |
| Business Area | IS## |
| Profit Center | 1402 |
第 49 页 / 共 543 页
AC405 Lesson: Cost Centers
2. To keep data input to a minimum, create the cost center “Motor Pool”
by copying the cost center “IT Services” anduse the cost center “FI/CO
Consulting”tocreatethecostcenter“LOConsulting”. Eventhoughyou
candothisdirectlyinthestandardhierarchy,tryusingthemenuentriesin
the application menu.
Remembertochangethenameofthecostcenterandthepersonresponsible
each time.
Figure 19: Dataforcreatingthecostcentermasterdata
a) CostCenterAccounting: MasterData→CostCenter→Individual
Processing → Create
b)
FieldNameorDataClass Values
Cost Center 203##
Valid from 01.01. Currentfiscalyear
To 31.12.9999
Template 202##
Controlling Area 1000
Onthebasicdatascreen,changethenameofthecostcenterandthatof
the manager (person responsible)
FieldNameorDataClass Values
Description Motor pool
Employee responsible Rose
Save your data!
Proceedasforcostcenter302##. Usecostcenter301##asatemplate.
Continued on next page
37
2009 © 2009 SAP AG. All rights reserved.
| FieldNameorDataClass | Values |
|---|---|
| Cost Center | 203## |
| Valid from | 01.01. Currentfiscalyear |
| To | 31.12.9999 |
| Template | 202## |
| Controlling Area | 1000 |
| FieldNameorDataClass | Values |
|---|---|
| Description | Motor pool |
| Employee responsible | Rose |
第 50 页 / 共 543 页
Unit2: MasterData AC405
3. Displayoneofthecostcenters. Whichcurrencydoesthecostcenteruse?
Wheredoesthisentryincostcentermasterdataoriginatefrom?
Answer: Cost Center Accounting: Master Data → Cost Center →
Individual Processing → Display
Enter acost center you created. In thiscase, the object currency istaken
fromthecompanycode. Thelocalcurrencyincompanycode1000isEUR.
4. Displaythecontrolindicatorforthecostcenteryouhavecalledup. Where
doesthisinformationcomefrom? Canthisinformationbechangedinthe
master data?
Answer: ClicktheControltabpage. Controlindicatorsaredefaultvalues
thataretaken from thecostcenter categoryandwhichcanbechanged in
the master data.
5. Becauseallyourcostcentersarelocatedincontrollingarea1000anduse
the object currency EUR, you don’t want to seethisinformation onthe
overview screen in the standard hierarchy.
Answer: CostCenterAccounting: MasterData→StandardHierarchy→
Change → Column Configuration icon
Deselecttheindicatorforthecompanycodeandtheobjectcurrency.
38
©2009SAPAG.Allrightsreserved. 2009
第 51 页 / 共 543 页
AC405 Lesson: Cost Centers
Lesson Summary
You should now be able to:
• Describehowtobeststructurethestandardhierarchy
• Create cost centers
• Understandthemeaningofthecostcentercategory.
39
2009 © 2009 SAP AG. All rights reserved.
第 52 页 / 共 543 页
Unit2: MasterData AC405
Lesson: Cost elements
Lesson Overview
You will familiarize yourself with the relationship between general ledgers in
FinancialAccountingandinManagementAccounting.
Youwilllearnhowtocreatecostelementsmanuallyandautomatically.
Lesson Objectives
After completingthislesson, you will beable to:
• DistinguishbetweenG/Laccountsandcostelements
• CreatecostelementsinManagement Accounting, and explainalternative
methods for creating them
Business Example
You receive a message from Financial Accounting informing you that the
companycodesaresetup. Youcannowstartcreatingcorrespondingcostelements
in Management Accounting.
The Chart of Accounts
Figure 20: The Chart of Accounts
Thechartofaccountscontainsallthegeneralledger(G/L)accountsbelongingto
Financial Accounting.
40
©2009SAPAG.Allrightsreserved. 2009
第 53 页 / 共 543 页
AC405 Lesson: Cost elements
Fromthecostcontrollingviewpoint,acircularsystemexistsbecausetheexpense
andrevenueaccountsinFinancialAccountingcorrespondtoprimarycostand
revenueelementsinManagementAccounting,andbecausepostingsinFinancial
Accountingarepassedoninreal-timetoCostandRevenueElementAccounting.
Inaddition,itisonlyinManagementAccountingthatyoucancreatesecondary
cost elements. These are used to record internal value flows like activity
allocations, assessments and settlements.
The Cost Element
Figure 21: The Cost Element
DuetotheintegratednatureofthemySAPERPsystemyouneedtocreateexpense
accountsinFinancialAccountingwithcorrespondingprimarycostselementsin
Controlling. ThisensuresthatexpensesinFinancialAccountingandprimarycosts
inManagementAccountingcanbereconciled. Youmustcreatetheprimarycost
elementsin Financial Accounting asG/L accountsbeforeyoucan createthem
in Management Accounting.
To be able to post to a primary cost element, you require an object in
ManagementAccounting(suchasacostcenter)toidentifytheoriginofthecosts.
Examplesofprimarycostelementsarematerialcostsandsalarycosts.
SecondarycostselementsareusedexclusivelyinManagement Accountingto
identifyinternalcostflowssuchasassessmentsorsettlements. Theydonothave
correspondinggeneralledgeraccountsinFinancialAccountingandaredefinedin
Management Accounting only.
41
2009 © 2009 SAP AG. All rights reserved.
第 54 页 / 共 543 页
Unit2: MasterData AC405
Whenyouanalyzerevenuesincostcontrolling,themySAPERPsystemrecords
themasrevenueelements. Revenueelementsareprimarycostelements.
Whenyoucreateacostelement,youmustassignacostelementcategory. This
assignmentdeterminesthetransactionsforwhichyoucanusethecostelement.
Forexample,category01(generalprimarycostelements)isusedforthestandard
primarypostingsfromFinancialAccountingorMaterialsManagement.
Figure 22: Automatic Creation of Cost Elements
You can create cost elements automatically. You provide thedefault settings
throughwhichthecostelementorthecostelementrangethatyouwanttocreateis
givenandenterthecostelementtypesforthecostelements.
Primarycostsareonlycreatedwhentherespectivegeneralledgerexistsinthe
operational chart. The SAP system takes the cost element name from theG/L
accountmasterdatainFinancialAccounting. However,youcanchangethename
in Management Accounting.
AsofRelease4.6, whenprocessingtheoperationalchartdirectoryinFinancial
AccountingCustomizing, youcancustomizewhethercreatingageneral ledger
automaticallygeneratesacostelement. If youusethisfunction, youmusttake
intoaccounttheaccountnumberwithintheframeworkofthepre-settingsforthe
automatic creation of cost elements.
Secondarycostelementsaregeneratedforallcostelementsyouhavedefined.
Thedescriptionistakenfromthecostelementcategory.
Onceyouhave enteredyour default settings, a background sessionstartsthat
generates the cost elements.
42
©2009SAPAG.Allrightsreserved. 2009
第 55 页 / 共 543 页
AC405 Lesson: Cost elements
Figure 23: Business scenario
The overview above displays the enterprise organization from your exercise
activities. Heretheportrayalofthemethodusedforcreditingcostcentersseems
tobetooearly. However,itisusefultoprovideapreviewatthisstage. Tomake
anassessmentortoallocateactivitydirectly,youneedsecondarycostelements.
Asyoucanseeabove,someofthecostcentersintheexercisescenariowilluse
assessmenttomakecredits,orwillallocateactivitydirectly.
Thisoverviewshowsyouwhy(!) youcreatewhichsecondarycostelementsin
the exercise.
Youcantakethisoverheadslidefromthefolderanduseitasahelpfuloverview
thoughout the course.
43
2009 © 2009 SAP AG. All rights reserved.
第 56 页 / 共 543 页
Unit2: MasterData AC405
44
©2009SAPAG.Allrightsreserved. 2009
第 57 页 / 共 543 页
AC405 Lesson: Cost elements
Exercise 3: Cost elements
Exercise Objectives
After completingthisexercise, youwillbeableto:
• CreatesecondarycostelementsinManagementAccounting.
Business Example
Attheendoftheperiod,youwouldliketoassesscostsfromthe“Organization”,
“IT Services”, and “Motor Pool” cost centers to the Consulting cost centers.
Furthermore, the Consulting cost centers use the direct activity allocation
functionsto allocatetheir consultingservicestointernal orders. Theseinternal
ordershavebeensetuptoact ascostobjectsfor theindividualcompaniesthat
usedtheservices. Tousetheassessmentanddirectactivityallocationfunctions,
youneedtodefinesecondarycostelements. Inaddition, youwanttodistribute
productioncostcenterstotherepaircostsaccordingtotheirorigin. Thisshouldbe
carriedoutlaterbymeansoftheindirectactivityallocation.
Task 1:
Createyoursecondarycostelements. Theyshouldbevalidfromthefirstdayof
thecurrentfiscalyearthroughthedefaultValidtodate.
1. Createtheassessmentcostelements. Usethefollowinginformation:
Cost Name Desc. Costel-
element ement
cate-
gory
6300## Assessmentorg. OrganizationalGroup## 42
6310## AssessmentITService ITServicesGroup## 42
##
6311## AssessMotorPool## MotorPoolGroup## 42
2. Create the cost elements you need to allocate consulting activities. Use
the following information:
Continued on next page
45
2009 © 2009 SAP AG. All rights reserved.
| Cost element | Name | Desc. | Costel- ement cate- gory |
|---|---|---|---|
| 6300## | Assessmentorg. | OrganizationalGroup## | 42 |
| 6310## | AssessmentITService ## | ITServicesGroup## | 42 |
| 6311## | AssessMotorPool## | MotorPoolGroup## | 42 |
第 58 页 / 共 543 页
Unit2: MasterData AC405
CostEl- Name Desc. Costel-
ement ement
cate-
gory
6261## Juniorconsulting## Juniorconsultinggroup## 43
6262## SeniorConsultant## SeniorConsultantGroup## 43
6393## IAA repair (internal RepairCostsGroup## 43
activity allocation
repair)
Task 2:
Carry out the following task:
1. Usingtheonlinehelp,defineprimaryandsecondarycostelements. Whatare
theprerequisitesforcreatingprimarycostelementsorrevenueelements?
46
©2009SAPAG.Allrightsreserved. 2009
| CostEl- ement | Name | Desc. | Costel- ement cate- gory |
|---|---|---|---|
| 6261## | Juniorconsulting## | Juniorconsultinggroup## | 43 |
| 6262## | SeniorConsultant## | SeniorConsultantGroup## | 43 |
| 6393## | IAA repair (internal activity allocation repair) | RepairCostsGroup## | 43 |
第 59 页 / 共 543 页
AC405 Lesson: Cost elements
Solution 3: Cost elements
Task 1:
Createyoursecondarycostelements. Theyshouldbevalidfromthefirstdayof
thecurrentfiscalyearthroughthedefaultValidtodate.
1. Createtheassessmentcostelements. Usethefollowinginformation:
Cost Name Desc. Costel-
element ement
cate-
gory
6300## Assessmentorg. OrganizationalGroup## 42
6310## AssessmentITService ITServicesGroup## 42
##
6311## AssessMotorPool## MotorPoolGroup## 42
a) CostCenterAccounting: MasterData→CostElement→Individual
Processing → Create Secondary
b)
FieldNameorDataClass Values
Cost Element 6300##
Valid from 01.01. Currentfiscalyear
To 31.12.9999
Name Assessment org.
Desc. OrganizationalGroup##
Costelementcategory 42
Save your data!
Repeatthisproceduretocreatetheothercostelements.
2. Create the cost elements you need to allocate consulting activities. Use
the following information:
Continued on next page
47
2009 © 2009 SAP AG. All rights reserved.
| Cost element | Name | Desc. | Costel- ement cate- gory |
|---|---|---|---|
| 6300## | Assessmentorg. | OrganizationalGroup## | 42 |
| 6310## | AssessmentITService ## | ITServicesGroup## | 42 |
| 6311## | AssessMotorPool## | MotorPoolGroup## | 42 |
| FieldNameorDataClass | Values |
|---|---|
| Cost Element | 6300## |
| Valid from | 01.01. Currentfiscalyear |
| To | 31.12.9999 |
| Name | Assessment org. |
| Desc. | OrganizationalGroup## |
| Costelementcategory | 42 |
第 60 页 / 共 543 页
Unit2: MasterData AC405
CostEl- Name Desc. Costel-
ement ement
cate-
gory
6261## Juniorconsulting## Juniorconsultinggroup## 43
6262## SeniorConsultant## SeniorConsultantGroup## 43
6393## IAA repair (internal RepairCostsGroup## 43
activity allocation
repair)
a)
FieldNameorDataClass Values
Cost Element 6261##
Valid from 01.01. Currentfiscalyear
To 31.12.9999
Name Junior consulting ##
Desc. Juniorconsultinggroup##
Costelementcategory 43
Save your data!
Proceedasforcostelement6262##and6393##(reference6261##).
Task 2:
Carry out the following task:
1. Usingtheonlinehelp,defineprimaryandsecondarycostelements. Whatare
theprerequisitesforcreatingprimarycostelementsorrevenueelements?
Answer: Acostelementclassifiesanorganization'svaluatedconsumption
ofproductionfactorswithinacontrollingarea. Acostelementcorresponds
to acost-relevant itemin thechart of accounts.
Adistinctionismadebetweenprimarycostelements,whicharisethrough
theuseofexternallyprocuredgoods, andsecondarycostelements, which
representvaluesflowswithinManagementAccounting.
Primary cost elements must be defined as G/L accounts before they can
be created within a controlling area.
48
©2009SAPAG.Allrightsreserved. 2009
| CostEl- ement | Name | Desc. | Costel- ement cate- gory |
|---|---|---|---|
| 6261## | Juniorconsulting## | Juniorconsultinggroup## | 43 |
| 6262## | SeniorConsultant## | SeniorConsultantGroup## | 43 |
| 6393## | IAA repair (internal activity allocation repair) | RepairCostsGroup## | 43 |
| FieldNameorDataClass | Values |
|---|---|
| Cost Element | 6261## |
| Valid from | 01.01. Currentfiscalyear |
| To | 31.12.9999 |
| Name | Junior consulting ## |
| Desc. | Juniorconsultinggroup## |
| Costelementcategory | 43 |
第 61 页 / 共 543 页
AC405 Lesson: Cost elements
Lesson Summary
You should now be able to:
• DistinguishbetweenG/Laccountsandcostelements
• Createcost elementsinManagement Accounting, andexplainalternative
methods for creating them
49
2009 © 2009 SAP AG. All rights reserved.
第 62 页 / 共 543 页
Unit2: MasterData AC405
Lesson: Activity Types
Lesson Overview
Youwillfamiliarizeyourself withthemaster dataoftheactivitytypeandlearn
howtocreateapricefortheactivitytobeperformed.
Lesson Objectives
After completingthislesson, you will beable to:
• Create activity types.
• Planmanualpricesfortheactivitytypesondifferentcostcenters
Business Example
Theconsultantsthatworkforyourcompanyneedtobeabletosettletheservices
thattheyprovidetocustomersdirectlytoacostobject(internalorder). Youwant
toallocatetheservicesofjuniorandseniorconsultantsseparately.
The Activity Types
Figure 24: The Activity Types
The activity type classifies the activities that are to be performed within a
company by one or several cost centers.
50
©2009SAPAG.Allrightsreserved. 2009
第 63 页 / 共 543 页
AC405 Lesson: Activity Types
Ifacostcenterprovidesactivitiesforothercostcenters,orders,processes,andso
on,thenthismeansthattheresourcesofthiscostcenterarebeingused. Thecosts
of theseresourcesneed tobeallocatedtothereceiversof theactivity. Activity
typesserveastracingfactors for thiscost allocation.
In an internal activity allocation, the quantity of the activity, such as the
numberofconsultinghours,isenteredintothemySAPERPsystem(manuallyor
automatically). Thesystemcalculatestheassociatedcostbasedontheactivity
priceandgeneratesadebittothereceiverandacredittothesenderforboththe
quantityandcosts. Theinternalactivityallocationiscarriedoutusingsecondary
costelements,whicharestoredasdefaulttypesintheactivitytypemasterdata.
Youcanrestricttheuseof the activity typetocertaintypesof cost centersby
enteringtheallowedcostcentercategoriesintheactivitytypemasterrecord. You
can enter up to eight allowed cost center categories, or leave the assignments
"unrestricted" by entering an asterisk (*).
The activity type category is used to determine whether and how an activity
type is recorded and allocated. For example, you can allow some activities to
beallocateddirectly, butspecifyforothersthattheyareeither notallocated, or
allocated indirectly only.
Relationship Between Cost Center/Activity Type
Figure 25: Cost center/activity type
51
2009 © 2009 SAP AG. All rights reserved.
第 64 页 / 共 543 页
Unit2: MasterData AC405
To enable internal activity allocation, you need to specify which cost centers
providewhichactivitytypesatwhatprice. YoudothisinthemySAPERPsystem
byplanningtheactivityoutput/pricesforacostcenter. Toenablethis, theSAP
system provides a wide range of options.
Fordirectactivityallocation,youenterthequantityoftheactivitytobeallocated
manually. Inorderforacostallocationandanactivityallocationtobeperformed,
the mySAP ERP system hasto valuate the allocated activity amount usingthe
sender'spriceforthisactivitytype. Foradirectactivityallocation,theplanprice
forthecombination“costcenter/activitytype”isusedforthiscalculation.
You can enter the planned price either manually, or have it calculated by the
systemautomaticallywithinplanning. Tomanuallysettheprice, theplanprice
indicator (PPI)mustbe(manually)setto3. You canusethisprocedureifyour
pricecalculationisnotcomplex,forexamplewherethepricesrequiredforyour
rates are determined withinyour organization and do not depend on internally
producedactivities,orwheretheratedependsonthepricesofexternalsuppliers
and not on the costs of the cost center. Automatic calculation of plan prices
is covered in course AC412.
52
©2009SAPAG.Allrightsreserved. 2009
第 65 页 / 共 543 页
AC405 Lesson: Activity Types
Exercise 4: Activity Types
Exercise Objectives
After completingthisexercise, youwillbeableto:
• Create activity types.
• Plan prices for activity types.
Business Example
The consultants in the new consulting department allocate their consulting
activitiestointernalordersusingdirectactivityallocation. Theseinternalorders
actascostobjectsforservicesthathavebeenprovidedforacompany. Youmust
create master data for the various types of activities. Because these activities
(consultingservices)alsohavetobeevaluated,youhavetoplanpricesforeach
activitytypeatcostcenterlevel. Whentheconsultantsenterhowmanyhoursthey
haveworkedforacompany,thenumberofhoursismultipliedbythepriceand
thisamountiscreditedtothecostcenteranddebitedfromthecostobject. When
youdefineprices,youshouldbasethemonthestandardmarketconsultingrate.
Inaddition,therepaircostsincurredontherepaircostcentershouldbeassigned
totheproductioncost centers on aprorated basisby meansof indirect activity
allocation. Theallocationshouldbeperformedusinganotheractivitytype.
Task 1:
Youwouldliketoanalyzetheconsultingactivitiesofjuniorandseniorconsultants
separately. Consequently, youneedto createtwoactivitytypesfor consulting.
The activitytypesarevalid fromthestart of thecurrent fiscal year. Accept
the proposed end date. Define another activity type for the allocation of the
repair costs.
1. CreatetheactivitytypeJ##(JuniorConsultant##). Thisactivitytypeis
measuredinhoursandisonlyusedbycategory8costcenters(Consulting).
For allocation, choosetheactivity typecategory1, which supportsdirect
activity allocation. The allocation cost element is6261##. Set the price
manually.
Continued on next page
53
2009 © 2009 SAP AG. All rights reserved.
第 66 页 / 共 543 页
Unit2: MasterData AC405
2. CreateactivitytypeS##(SeniorConsultant##). UseactivitytypeJ##as
areference. Changetheshorttext, thedescription,andtheallocationcost
element (6262##). Keep the remainingdata.
3. CreatetheactivitytypeREP##(repair##). Theactivitytypeismeasuredin
hoursandcanbeusedbyallcostcenters. Forallocation,choosetheactivity
typecategory3,forindirectactivityallocation. Theallocationcostelement
is 6393##. Set the price manually.
Task 2:
Both“FI/COConsulting”and“LOConsulting”costcentersusejuniorandsenior
consultants. Define prices for the activity types. The repair service is carried
out by the repair cost center.
1. Enterthepricesintheplanningmenu. ChoosetheplannerprofileSAPEASY.
2. Useplanning layout1-261(activitytypeplanning)to planthepricesfor
activitytypeJ##ontheConsultingcostcenters(costcentergroupB30##).
Planthepricesforallperiodsofthecurrentfiscalyearinversion0.
Use form-based entry.
3. AnhourlyjuniorconsultantrateofEUR200hasbeendeterminedforboth
costcenters(301##FI/COConsultingand302##LOConsulting).
4. PlanseniorconsultingpricesS##ontheconsultingcostcenters(costcenter
groupB30##). Plan thepricesfor all periods of thecurrent fiscal year
in version 0.
Use form-based entry.
5. AnhourlyrateofEUR300forsenior consultinghasbeendeterminedfor
costcenter301##(FI/COConsulting). SeniorconsultantsinLO(costcenter
302##),however,chargeanhourlyrateofEUR280.
6. Useplanninglayout1-261(priceplanning,simplelayout)toplantheprices
foractivitytypeREP##ontheRepaircostcenters(costcenter113##). Plan
thepricesforallperiodsofthecurrentfiscalyearinversion0.
Use form-based entry.
7. AnhourlyrateofEUR20hasbeenagreedforcostcenter113##(Repairs).
54
©2009SAPAG.Allrightsreserved. 2009
第 67 页 / 共 543 页
AC405 Lesson: Activity Types
Solution 4: Activity Types
Task 1:
Youwouldliketoanalyzetheconsultingactivitiesofjuniorandseniorconsultants
separately. Consequently, youneedto createtwoactivitytypesfor consulting.
The activitytypesarevalid fromthestart of thecurrent fiscal year. Accept
the proposed end date. Define another activity type for the allocation of the
repair costs.
1. CreatetheactivitytypeJ##(JuniorConsultant##). Thisactivitytypeis
measuredinhoursandisonlyusedbycategory8costcenters(Consulting).
For allocation, choosetheactivity typecategory1, which supportsdirect
activity allocation. The allocation cost element is6261##. Set the price
manually.
a) CostCenterAccounting: MasterData→ActivityType→Individual
Processing → Create
b)
FieldNameorDataClass Values
Activity Type J##
Valid from 01.01. Currentfiscalyear
To 31.12.9999
Name Juniorconsulting##
Activity Unit HR
Cost center categories 8
Activity typecategory 1
Allocationcostelement 6261##
Price Indicator 3
Save your data!
2. CreateactivitytypeS##(SeniorConsultant##). UseactivitytypeJ##as
areference. Changetheshorttext, thedescription, andtheallocationcost
element (6262##). Keep the remainingdata.
Answer: Saveyourdata. CreatetheactivitytypeS##accordingly-using
reference J##.
Changethenameandtheallocationcostelement. Keeptheremainingdata.
Save your data!
Continued on next page
55
2009 © 2009 SAP AG. All rights reserved.
| FieldNameorDataClass | Values |
|---|---|
| Activity Type | J## |
| Valid from | 01.01. Currentfiscalyear |
| To | 31.12.9999 |
| Name | Juniorconsulting## |
| Activity Unit | HR |
| Cost center categories | 8 |
| Activity typecategory | 1 |
| Allocationcostelement | 6261## |
| Price Indicator | 3 |
第 68 页 / 共 543 页
Unit2: MasterData AC405
3. CreatetheactivitytypeREP##(repair##). Theactivitytypeismeasuredin
hoursandcanbeusedbyallcostcenters. Forallocation,choosetheactivity
typecategory3,forindirectactivityallocation. Theallocationcostelement
is 6393##. Set the price manually.
a) CostCenterAccounting: MasterData→ActivityType→Individual
Processing → Create
b)
FieldNameorDataClass Values
Activity Type REP##
Valid from 01.01. Currentfiscalyear
To 31.12.9999
Name Repair ##
Activity Unit HR
Cost center categories *
Activity typecategory 3
Allocationcostelement 6393##
Price Indicator 3
Save your data!
Task 2:
Both“FI/COConsulting”and“LOConsulting”costcentersusejuniorandsenior
consultants. Define prices for the activity types. The repair service is carried
out by the repair cost center.
1. Enterthepricesintheplanningmenu. ChoosetheplannerprofileSAPEASY.
a) CostCenterAccounting: Planning→SetPlanningProfile
b)
FieldNameorDataClass Values
Planner profile SAPEASY
Confirm profile icon.
2. Useplanning layout1-261(activitytypeplanning)to planthepricesfor
activitytypeJ##ontheConsultingcostcenters(costcentergroupB30##).
Planthepricesforallperiodsofthecurrentfiscalyearinversion0.
Continued on next page
56
©2009SAPAG.Allrightsreserved. 2009
| FieldNameorDataClass | Values |
|---|---|
| Activity Type | REP## |
| Valid from | 01.01. Currentfiscalyear |
| To | 31.12.9999 |
| Name | Repair ## |
| Activity Unit | HR |
| Cost center categories | * |
| Activity typecategory | 3 |
| Allocationcostelement | 6393## |
| Price Indicator | 3 |
| FieldNameorDataClass | Values |
|---|---|
| Planner profile | SAPEASY |
第 69 页 / 共 543 页
AC405 Lesson: Activity Types
Use form-based entry.
a) Cost Center Accounting: Planning → Activity Output/Prices →
Change
b)
FieldNameorDataClass Values
Version: 0
Period From 1
Period To 12
Fiscal Year current
Cost center - group B30##
Activity Type J##
Input Form-based
Goto → Overview Screen
3. AnhourlyjuniorconsultantrateofEUR200hasbeendeterminedforboth
costcenters(301##FI/COConsultingand302##LOConsulting).
a) On the overview screen
FieldNameorDataClass Values
Total price 200
Goto→NextCombination(costcenter302##)
FieldNameorDataClass Values
Total price 200
Save your data!
4. PlanseniorconsultingpricesS##ontheconsultingcostcenters(costcenter
group B30##). Planthe prices forall periods of thecurrent fiscal year
in version 0.
Continued on next page
57
2009 © 2009 SAP AG. All rights reserved.
| FieldNameorDataClass | Values |
|---|---|
| Version: | 0 |
| Period From | 1 |
| Period To | 12 |
| Fiscal Year | current |
| Cost center - group | B30## |
| Activity Type | J## |
| Input | Form-based |
| FieldNameorDataClass | Values |
|---|---|
| Total price | 200 |
| FieldNameorDataClass | Values |
|---|---|
| Total price | 200 |
第 70 页 / 共 543 页
Unit2: MasterData AC405
Use form-based entry.
a) Cost Center Accounting: Planning → Activity Output/Prices →
Change
FieldNameorDataClass Values
Version: 0
Period From 1
Period To 12
Fiscal Year current
Cost center - group B30##
Activity Type S##
Input Form-based
5. AnhourlyrateofEUR300forsenior consultinghasbeendeterminedfor
costcenter301##(FI/COConsulting). SeniorconsultantsinLO(costcenter
302##),however,chargeanhourlyrateofEUR280.
a) On the overview screen
FieldNameorDataClass Values
Total price 300
Goto→NextCombination(cost center302##)
FieldNameorDataClass Values
Total price 280
Save your data!
6. Useplanninglayout1-261(priceplanning,simplelayout)toplantheprices
foractivitytypeREP##ontheRepaircostcenters(costcenter113##). Plan
thepricesforallperiodsofthecurrentfiscalyearinversion0.
Continued on next page
58
©2009SAPAG.Allrightsreserved. 2009
| FieldNameorDataClass | Values |
|---|---|
| Version: | 0 |
| Period From | 1 |
| Period To | 12 |
| Fiscal Year | current |
| Cost center - group | B30## |
| Activity Type | S## |
| Input | Form-based |
| FieldNameorDataClass | Values |
|---|---|
| Total price | 300 |
| FieldNameorDataClass | Values |
|---|---|
| Total price | 280 |
第 71 页 / 共 543 页
AC405 Lesson: Activity Types
Use form-based entry.
a) Cost Center Accounting: Planning → Activity Output/Prices →
Change
b)
FieldNameorDataClass Values
Version: 0
Period From 1
Period To 12
Fiscal Year current
Cost Center 113##
Activity Type REP##
Input Form-based
Goto → Overview Screen
7. AnhourlyrateofEUR20hasbeenagreedforcostcenter113##(Repairs).
a) On the overview screen
FieldNameorDataClass Values
Total price 20
Save your data!
59
2009 © 2009 SAP AG. All rights reserved.
| FieldNameorDataClass | Values |
|---|---|
| Version: | 0 |
| Period From | 1 |
| Period To | 12 |
| Fiscal Year | current |
| Cost Center | 113## |
| Activity Type | REP## |
| Input | Form-based |
| FieldNameorDataClass | Values |
|---|---|
| Total price | 20 |
第 72 页 / 共 543 页
Unit2: MasterData AC405
Lesson Summary
You should now be able to:
• Create activity types.
• Planmanualpricesfortheactivitytypesondifferentcostcenters
60
©2009SAPAG.Allrightsreserved. 2009
第 73 页 / 共 543 页
AC405 Lesson: Statistical key figures
Lesson: Statistical key figures
Lesson Overview
You will familiarize your self with statistical key figures in Management
Accounting.
Lesson Objectives
After completingthislesson, youwillbeable to:
• Create statistical key figures
Business Example
You want to use statistical key figures as the tracing factor for repostings and
allocations at period end.
Statistical key figures
Figure 26: Statistical key figures
Statistical key figures are figures relating to cost centers, profit centers, and
overhead cost orders (for example, the number of employees, the length of
long-distance calls). Statistical key figures may also be a value representing
theservicesprovidedbyoneparticularcost center, for example, thenumberof
employeesintheTransportationcostcenterwhocarryoutrepairs. Thesetypesof
keyfiguresareknownasactivity-dependentstatisticalkeyfigures.
Youcanpostbothplannedandactualstatisticalkeyfigures.
Youcanusestatisticalkeyfiguresbothasabasisforperiodictransactions,suchas
assessment or distribution, andforkeyfigureanalysis.
61
2009 © 2009 SAP AG. All rights reserved.
第 74 页 / 共 543 页
Unit2: MasterData AC405
Statisticalkeyfiguresaredefinedeitherasafixedvalueoratotalsvalue.
Thefixedvalue(forexample,employees)iscarriedoverfromtheperiodinwhich
it isenteredtoall subsequent periodsof thesamefiscalyear. Youonlyneedto
enteranewpostingifthisfixedvaluechanges. Thefiscalyeartotalisanaverage
of the period totals.
Thetotalsvalueisonlypostedintheperiodinwhichitisentered(forexample,
forlong-distancecalls). Thefiscalyeartotalisthesumofalltheperiodvalues.
62
©2009SAPAG.Allrightsreserved. 2009
第 75 页 / 共 543 页
AC405 Lesson: Statistical key figures
Exercise 5: Statistical key figures
Exercise Objectives
After completingthisexercise, youwillbeableto:
• Create statistical key figures
Business Example
At the end of the period, the cost centers “Telephone”, “Organization”, “IT
Services”,and“MotorPool”allocatetheircoststothecostcentersthatincurred
thecosts. Statisticalkeyfigurescanbeusedasabasisforallocatingthecosts.
The productioncost centersaredistributed totherepair costs at period end by
meansofanindirectactivityallocation. Thesecostsareallocatedonthebasisof
theproducedunitsofthecostcenters. Thisoutputisalsorepresentedbymeansof
a statistical key figure.
Task:
Create statistical key figures that are to be used as a basis for the periodic
allocations of the cost centers.
1. The“Telephone”costcenterusesthenumberoftelephoneunitsonthecost
centerasanallocationbasis,the“ITServices”costcenterusesthenumber
of PCs in use, and the “Motor Pool” cost center allocates costs based on
mileage. The production cost centers use the number of their produced
units. Decidewhichof theseallocationbasesaretotalsvaluesandwhich
are fixed values.
Numberoftelephoneunits:
Number of PCs:
Mileage:
Numberof producedunits
2. Canyouchangefixedvaluesduringthefiscalyear?
3. DefinethestatisticalkeyfigureTELE##forthenumberoftelephoneunits.
The unit of measure is pieces.
Continued on next page
63
2009 © 2009 SAP AG. All rights reserved.
| Numberoftelephoneunits: | |
|---|---|
| Number of PCs: | |
| Mileage: | |
| Numberof producedunits |
第 76 页 / 共 543 页
Unit2: MasterData AC405
4. DefinethestatisticalkeyfigurePC## forthenumberofPCsinuseonthe
cost centers. The unit of measure ispieces.
5. DefinethestatisticalkeyfigureMI##formileage. Theunitofmeasureis
miles (MI).
6. Define the statistical key figure Prod## for the number of the produced
units. The unit of measure ispieces PC.
64
©2009SAPAG.Allrightsreserved. 2009
第 77 页 / 共 543 页
AC405 Lesson: Statistical key figures
Solution 5: Statistical key figures
Task:
Create statistical key figures that are to be used as a basis for the periodic
allocations of the cost centers.
1. The“Telephone”costcenterusesthenumberoftelephoneunitsonthecost
centerasanallocationbasis,the“ITServices”costcenterusesthenumber
of PCs in use, and the “Motor Pool” cost center allocates costs based on
mileage. The production cost centers use the number of their produced
units. Decidewhichof theseallocationbasesaretotalsvaluesandwhich
are fixed values.
Numberoftelephoneunits: Totals value
Number of PCs: Fixed value
Mileage: Totals value
Numberof producedunits Totals value
a) Youenter and post totalsvalues onlyin the relevant posting period.
Startingfromtheentryperiod,fixedvaluesareupdatedfortheentire
fiscal year.
2. Canyouchangefixedvaluesduringthefiscalyear?
Answer: Youcanchangefixedvaluesduringafiscalyear,byenteringthe
newvalueinthecorrespondingperiod. From thistimeonwards, thedata
is updated to the following periods.
Asthenamesuggests, fixedvaluesare statisticalkeyfigures, theposting
valueofwhichisalwaysconstant. However,valuessuchasthesestillneedto
becapableofbeingadjustedtochangeswithintheenterprise. Suchchanges
couldincludeadditionalemployeesorsmallerofficespaceforacostcenter.
Continued on next page
65
2009 © 2009 SAP AG. All rights reserved.
| Numberoftelephoneunits: | Totals value |
|---|---|
| Number of PCs: | Fixed value |
| Mileage: | Totals value |
| Numberof producedunits | Totals value |
第 78 页 / 共 543 页
Unit2: MasterData AC405
3. DefinethestatisticalkeyfigureTELE##forthenumberoftelephoneunits.
The unit of measure is pieces.
a) CostCenterAccounting: MasterData→StatististicalKeyFigures→
Individual Processing → Create
FieldNameorDataClass Values
Statist. Key Figure TELE##
Bezeichnung Telephone units
Statist.key figure unit Pc
Key figure category Totals values
Save your data!
4. DefinethestatisticalkeyfigurePC## forthenumberofPCsinuseonthe
cost centers. The unit of measure ispieces.
a)
FieldNameorDataClass Values
Statist. Key Figure PC##
Bezeichnung PCs
Statist.key figure unit Pc
Key figure category Fixed values
Save your data!
5. DefinethestatisticalkeyfigureMI##formileage. Theunitofmeasureis
miles (MI).
a)
FieldNameorDataClass Values
Statist. Key Figure MI##
Bezeichnung Miles traveled
Statist.key figure unit ml
Key figure category Totals values
Save your data!
Continued on next page
66
©2009SAPAG.Allrightsreserved. 2009
| FieldNameorDataClass | Values |
|---|---|
| Statist. Key Figure | TELE## |
| Bezeichnung | Telephone units |
| Statist.key figure unit | Pc |
| Key figure category | Totals values |
| FieldNameorDataClass | Values |
|---|---|
| Statist. Key Figure | PC## |
| Bezeichnung | PCs |
| Statist.key figure unit | Pc |
| Key figure category | Fixed values |
| FieldNameorDataClass | Values |
|---|---|
| Statist. Key Figure | MI## |
| Bezeichnung | Miles traveled |
| Statist.key figure unit | ml |
| Key figure category | Totals values |
第 79 页 / 共 543 页
AC405 Lesson: Statistical key figures
6. Define the statistical key figure Prod## for the number of the produced
units. The unit of measure is piecesPC.
a)
FieldNameorDataClass Values
Statist. Key Figure Prod##
Bezeichnung Produced unit
Statist. keyfigure unit PC
Key figure category Totals values
Save your data!
67
2009 © 2009 SAP AG. All rights reserved.
| FieldNameorDataClass | Values |
|---|---|
| Statist. Key Figure | Prod## |
| Bezeichnung | Produced unit |
| Statist. keyfigure unit | PC |
| Key figure category | Totals values |
第 80 页 / 共 543 页
Unit2: MasterData AC405
Lesson Summary
You should now be able to:
• Create statistical key figures
68
©2009SAPAG.Allrightsreserved. 2009
第 81 页 / 共 543 页
AC405 Lesson: Global Functions For Master Data
Lesson: Global Functions For Master Data
Lesson Overview
Youwillfamiliarizeyourselfwiththetimedependencyofmasterdataandlearn
howyoucancombinemasterdataingroupsandprocesstheseinthecollective
processing
Lesson Objectives
After completingthislesson, youwillbeable to:
• Updatemaster data in collective processing
• Explain thetime dependenciesof master data
• Createmasterdatagroupsandexplainhowtheyarecreated
Business Example
Althoughmasterdataremainsrelativelyconstantforlongperiodsoftime,some
maintenancewillberequiredastheenterprisegrowsandchanges. Youfamiliarize
yourselfwiththevarietyoftoolsthatexistforthispurpose.
Creating Time-Based Master Data
Figure 27: Creating Time-Based Master Data
You can store master data fields for cost centers, cost elements, and activity
typesastime-based. Ifyouchangeoneofthesefieldsforaparticulartimeframe,
the system creates a new master record containing the new master record for
this period. This means that several database records are maintained for each
69
2009 © 2009 SAP AG. All rights reserved.