AC415_EN_Col52_FV_Part_A4 (第4页)

第 129 页 / 共 181 页

AC415 Lesson: Planning Scope and Prerequisites

Pleasenotethatonlythosecostcenters,costelements,activitytypesandstatistical

keyfiguresthatareorganizedintogroupsandstoredintheplanningprofilecan

be taken into account during planning.

For unitcosting, youneedtodefineandassignacostingvariant(CO-PC).The

costingvariantwillbetheinterfacetothebillofmaterials,materialmasterdataand

routing(theso-calledquantitystructure)whichyouneedforplanningonthislevel.

Figure 44: Overall Planning

Overallplanningisthemostbasicformoforderplanning. Here,youcreateaplan

byestimatingthelikelycostswhichwillbeincurredforanorder. Inadditionto

thedetailed,costelement-basedplanningvaluesusedincostcenteraccounting,

youcanalsosavegeneraloverallplanningvaluesforeachfiscalyearseparately

from cost elements. Youmaintain thesevaluesparallel tothevaluesfromcost

element planning and unit costing.

Youcanplaneitheroverallvaluesorvaluesfor individualyears. Forplanning,

youneedtodefineaplanningprofilefirstandstoreitintheordertype.

Youcancall uptheprimarycostplanning, unit costing, revenueplanning, and

activity input planningfunctions straight from theoverall planning screen. As

wellastheOverallValuescolumn,thesystemalsodisplaystheplannedtotal,the

unit costing values, and the cost element plan. The total planned value is the

sumofallthecostplanningformsused(overall,costandrevenueelement,unit

costing, and activity input planning).

121

Q2/2005 © 2005 SAP AG. All rights reserved.

第 130 页 / 共 181 页

Unit5: PlanningandBudgeting AC415

Figure 45: Versions: Settings forIntegrated Planning

Youcanplanyourinternalordersinmultipleversions.

Whenyoucreateacontrollingarea,theSAPsystemautomaticallycreatesversion

000, whichisvalidforfivefiscalyears. Youcanalsoplanalternativeversions.

Note that the SAP system always uses version 000 when referencing actual

postings.

Alternativeversionsallowonlyplandatastorageforinternalorders,orthestorage

of parallel valuations if you useTransfer Prices.

Therearetwoindicatorsusedforintegratedplanningintheversion:

• Integrated planning

– This indicator governswhether planning data is passed on to Profit

CenterAccountingandtheSpecialPurposeLedger. Italsoensuresthat

eachplanningchangeisdocumentedwithaplanlineitem.

• Integratedplanningwithcostcenters/businessprocesses

– To ensure that internal order planning is included in Cost Center

Accounting and Activity-Based Accounting, this indicator must be

active in the plan version.

Touseintegratedplanningforindividualorders,youalsoneedtosettherelevant

indicator in theordermaster. You can createa default setting for thisin the

order type.

122

©2005SAPAG.Allrightsreserved. Q2/2005

第 131 页 / 共 181 页

AC415 Lesson: Planning Scope and Prerequisites

Figure 46: Effects of Plan-Integrated Orders on planning

Withinintegratedplanningforinternalorders,youcanintegratecostelement

andactivityinputplanningforaninternalorderintocostcenterorbusinessprocess

planning. All the planned business allocations on the internal order are then

automaticallyupdatedonthesender/receivercostcenteroronthesender/receiver

business process.

Youcanonlyuseintegratedplanningforinternalorderswhentheinternalorder

alreadyexistsatthetimeofcostcenterplanning. Inthecaseoflongtermorders,

you can use integrated planning.

• If you are planning activity inputs for an integrated planning order, the

plannedactivityisupdatedtothecostcenterprovidingtheactivity.

• During planned settlement of the order, the order costs are debited from

the receiver.

• Overheadcalculationsonplan-integratedordersdebittheinternalorderand

credit a cost center.

• Ifyouareusingassessmentanddistribution,theplannedcostsofasender

costcenterareallocatedbasedonpre-definedassessmentanddistribution

keys.

• Periodicrepostingsofplan-integratedorderstocostcentersaresupported.

123

Q2/2005 © 2005 SAP AG. All rights reserved.

第 132 页 / 共 181 页

Unit5: PlanningandBudgeting AC415

Figure 47: Copy Actual to Plan or Plan to Plan

Youcancopybothactualvaluesandplannedvaluesfrominternalordersintoa

plan version.

The actual business transactions are assigned to the corresponding, manually

planned business transactions.

124

©2005SAPAG.Allrightsreserved. Q2/2005

第 133 页 / 共 181 页

AC415 Lesson: Planning Scope and Prerequisites

Exercise 8: Planning

Exercise Objectives

After completingthisexercise, youwillbeableto:

• Planordersusingtheoverallplanningfunctionandusetheoptionsavailable

fordetailedplanningwithcostelementsorunitcosting.

Business Example

Basedonyourdiscussionswiththecostcentermanagers,youknowthattheIDES

Group usestheoverallplanningfunctionsto producepreliminary plansfor the

future. Foreachfiscalyear,unitcostingisusedtoproducemoredetailedplanning

atcostelementoractivitylevel,inparticularforshort-termorders.

Totestthisfunction,youwillbeusingcostelementplanningtocreateacurrent

fiscal year plan for your PC repair/maintenance order. Since this isa standing

order, youcreateanoverallplanforthefollowingtwofiscalyears. Youusethe

unitcostingfunctiontocreateaplanfor yourmarketingbrochureorder forthe

currentfiscalyear. Sincethisisashort-termindividualorder,nootherplanningis

required.

Task 1:

CreateaplanforyourPCrepair/maintenanceorder usingtheoverallplanning

andcostelementplanningfunctions. Usetheoverallplanningtoplanthenext

two fiscal years.

Use overallplanning tocreate adetailedplanfor thecurrent fiscal year at cost

element level.

1. Usingtheoverallplanningfunction,planEUR50,000forallfiscalyears,

EUR 16,000 for thenext fiscal year, and EUR 17,500 for thefollowing

fiscal year. Check and save your order plan.

Caution: Notethatwhenyouaccessunitcostingorcost element

planningviatheoverallplanningfunctionandselect“Save”onthe

unitcostingorcostelementplanningscreens,thedataisonlysaved

temporarily. YoumustselectSaveattheoverallplanninglevelin

ordertosavetheplansforyourorderproperly.

2. For the current fiscal year and plan version 0, use the overall planning

screen to plan EUR 10,000 for direct labor costs (cost element420000),

EUR 3,600 for spare parts (cost element 404000), EUR 400 for office

supplies (cost element 476000), and EUR 1,000 for IT materials (cost

element 476100).

Continued on next page

125

Q2/2005 © 2005 SAP AG. All rights reserved.

第 134 页 / 共 181 页

Unit5: PlanningandBudgeting AC415

Save your cost element planning information.

Task 2:

Usetheunitcostingfunctiontoproduceaplanforyourmarketingbrochures

for the current fiscal year.

Usetheoverallplanningscreentobranchtounitcosting.

1. Useunitcostingtoplantheanticipatedcostsforthepublicationofyourcell

phone marketing brochures.

UsetheVariableitem categoryfor yourentries.

Youneedtoorder60hoursofprinting,atacostofEUR50perhour.

Plan 2 daysof photographic services at EUR 1,000 per day. Plan both

itemsusingthecostelement417000(PurchasedServices).

Defineasubtotalrow(categoryS)forTotalPurchasedServices.

You alsoneed packagingmaterialsfor your brochures. Plan5000 pieces

of packaging at EUR 1 each. These costs should be planned using the

packaging materials cost element405000.

Createatotalsrow(categoryS)fortheTotalUnitCostingPlan.

Save the order plan.

2. Call up the Orders: Actual/Plan/Variance report for your marketing

brochures for the whole fiscal year.

126

©2005SAPAG.Allrightsreserved. Q2/2005

第 135 页 / 共 181 页

AC415 Lesson: Planning Scope and Prerequisites

Solution 8: Planning

Task 1:

CreateaplanforyourPCrepair/maintenanceorder usingtheoverallplanning

andcostelementplanningfunctions. Usetheoverallplanningtoplanthenext

two fiscal years.

Use overallplanning tocreate adetailedplanfor thecurrent fiscal year at cost

element level.

1. Usingtheoverallplanningfunction,planEUR50,000forallfiscalyears,

EUR 16,000 for thenext fiscal year, and EUR 17,500 for thefollowing

fiscal year. Check and save your order plan.

Caution: Notethatwhenyouaccessunitcostingorcost element

planningviatheoverallplanningfunctionandselect“Save”onthe

unitcostingorcostelementplanningscreens,thedataisonlysaved

temporarily. YoumustselectSaveattheoverallplanninglevelin

ordertosavetheplansforyourorderproperly.

a) SAP EasyAccess→Internal Orders→ Planning →Overall Values

→ Change Enter your PC repair/maintenance order number in the

Order field.

Press Enter.

Enter 50000 in the Overall field.

Enter16000inthefieldforthenextfiscalyear.

Enter17500inthefieldforthenextfiscalyear+1.

ChooseENTERtoviewtheupdatedPlannedtotalcolumn.

Choose Check.

If no errors are found, save your plan.

2. For the current fiscal year and plan version 0, use the overall planning

screen to plan EUR 10,000 for direct labor costs (cost element420000),

EUR 3,600 for spare parts (cost element 404000), EUR 400 for office

supplies (cost element 476000), and EUR 1,000 for IT materials (cost

element 476100).

Continued on next page

127

Q2/2005 © 2005 SAP AG. All rights reserved.

第 136 页 / 共 181 页

Unit5: PlanningandBudgeting AC415

Save your cost element planning information.

a) SAP EasyAccess→Internal Orders→Planning →Overall Values

→ Change

PlaceyourcursorinthePlanfieldforthecurrentfiscalyear.

ChooseExtras→DetailedPlanning→PrimaryCosts

In the Total plan costs column, enter:

-10000forcostelement420000,Directlaborcosts.

Usethe“Position…”pushbuttontonavigatemorequickly.

- 3600for costelement 404000, Spareparts.

- 400forcostelement476000, Officesupplies.

- 1000forcost element476100, IT materials.

ChooseSavetotemporarilysaveyourcostelementplan.

Save your overall plan

Task 2:

Usetheunitcostingfunctiontoproduceaplanforyourmarketingbrochures

for the current fiscal year.

Usetheoverallplanningscreentobranchtounitcosting.

1. Useunitcostingtoplantheanticipatedcostsforthepublicationofyourcell

phone marketing brochures.

UsetheVariableitem categoryfor yourentries.

Youneedtoorder60hoursofprinting,atacostofEUR50perhour.

Plan 2 daysof photographic services at EUR 1,000 per day. Plan both

itemsusingthecostelement417000(PurchasedServices).

Defineasubtotalrow(categoryS)forTotalPurchasedServices.

You alsoneed packagingmaterialsfor your brochures. Plan5000 pieces

of packaging at EUR 1 each. These costs should be planned using the

packaging materials cost element405000.

Createatotalsrow(categoryS)fortheTotalUnitCostingPlan.

Save the order plan.

a) EnterthenumberofyourmarketingbrochureorderintheOrderfield.

Press Enter.

Makesurethecursorisinthefieldforthecurrentfiscalyear.

Continued on next page

128

©2005SAPAG.Allrightsreserved. Q2/2005

第 137 页 / 共 181 页

AC415 Lesson: Planning Scope and Prerequisites

Choose Extras → Unit Costing.

Confirmthepop-upcontainingthecostingvariantPC02.

For item 1, enter:

- V in the Category column.

- 60 in the Quantity column.

- H in the Unit of measure field.

-PrintingServicesintheDescriptioncolumn.

- 50 in the Price - total field.

- 417000 in the Cost element field.

For item 2, enter:

- V in the Category column.

- 2 in the Quantity column.

- D(days) in the Unit of measurefield.

-PhotographicServicesintheDescriptioncolumn.

- 1000 in the Price - total field.

- 417000 in the Cost element field.

For item 3, enter:

- S in the Category column.

- Place the cursor in the Formula field. Either double-click on the

lineorselectInsert TotalsItem. Theformula=(1:3)shouldappear

in the Formula column.

-TotalPurchasedServicesintheDescriptionfield.

For item 4, enter:

- V in the Category column.

- 5000 in the Quantity column.

-PC(pieces)inthe Unitof measurecolumn.

- Packaging in the Description field.

- 1 in the Price - total field.

- 405000 in the Cost element column.

For item 5, enter:

- S in the Category column.

Continued on next page

129

Q2/2005 © 2005 SAP AG. All rights reserved.

第 138 页 / 共 181 页

Unit5: PlanningandBudgeting AC415

- Place cursor in the Formulafield. SelectInsert TotalsItem. The

formula=(1:5)shouldappearintheFormulacolumn.

-TotalUnitCostingPlanintheDescriptionfield.

-ChooseENTERtoviewtheresultsintheValue–Totalcolumn.

SelectSavetotemporarilysaveyourunitcostingplan.

ChooseSave tosavethechangestotheorderplan.

2. Call up the Orders: Actual/Plan/Variance report for your marketing

brochures for the whole fiscal year.

a) SAPEasyAccessmenu→InternalOrders→InformationSystem→

ReportsforInternalOrders→Plan/ActualComparisons→Orders:

Actual/Plan/Variance

Enter1000in theControllingareafield.

EnterthecurrentfiscalyearintheFiscalyearfield.

Enter 1 in the From period field.

Enter 12 in the To period field.

Enter 0 in the Plan version field.

Enterthenumberofyourmarketingbrochureorderinthe“Orvalue(s)”

field.

Choose Execute.

130

©2005SAPAG.Allrightsreserved. Q2/2005

第 139 页 / 共 181 页

AC415 Lesson: Planning Scope and Prerequisites

Lesson Summary

You should now be able to:

• Describe different planning methods

• Explain the plan profile

• Performoverallanddetailedplanningontheinternalorder

• List the options for automatic planning

• Distinguishbetweenorderswithandorderswithoutintegratedplanning

131

Q2/2005 © 2005 SAP AG. All rights reserved.

第 140 页 / 共 181 页

Unit5: PlanningandBudgeting AC415

Lesson: Budgeting and Availability Control Concept

Lesson Overview

You learntocreateabudget for an internal order and familiarizeyourself with

thebudgetprofile. Yousetupanavailabilitycontrolandobservetheeffectson

the orders. You see how to transfer a budget and how the budgeting works in

different currencies.

Lesson Objectives

After completingthislesson, you will beable to:

• Set up the profiles for the budgeting

• Enter budgets on overhead cost orders

• Set up the availability control

• Understandtheresultsofthebudgetingandavailabilitycontrol

• Transfer thebudgetsintothe following year

Business Example

You should also review the system options for the budgeting and availability

controlandmakearecommendationforitsusewithinIDES.

Figure 48: Budget Management

132

©2005SAPAG.Allrightsreserved. Q2/2005

第 141 页 / 共 181 页

AC415 Lesson: Budgeting and Availability Control Concept

Thesystemrecognizesthefollowingbudgettypes:

• Theoriginalbudgetisthebudgetthatwasoriginallyallocated.

• Budget updatesforordersincludesupplementsand returnsandareused

whenunforeseeneventsandadditionalrequirementsforceacorrectiontothe

original budget

• Thecurrentbudgetincludestheoriginalbudgetandallbudgetupdates.

In addition to the budget update functions, you can also make changes to the

originalbudget. Youcanfreezetheoriginalbudgetusingstatusmanagement. To

do this, you must create a user status which prohibits the Budgeting business

transactionbutwhichallowsbudgetsupplementsandreturns.

Whenyoucreateorupdateyourbudget,thesystemdocumentsthetransactionina

lineitem. Youcanthendisplaythebudgetlineitems. Youcanalsoentertextfor

budgetlineitemsthatprovidesadditionalinformationforbudgeting.

In order tocreatea budget for an order, you must definea budget profile and

assignittotheordertype. Thebudgetprofiledefinestheparametersforbudgeting.

InCustomizing,youmustdefineanumberrangeforyourbudgetdocuments. To

do so, use number range 04.

Whenyousavethebudget,thesystemchecksthatthesumoftheannualvalues

matches the overall value for the order.

Figure 49: Profile for Budgeting

133

Q2/2005 © 2005 SAP AG. All rights reserved.

第 142 页 / 共 181 页

Unit5: PlanningandBudgeting AC415

Inordertocreateabudgetforanorder,youmustdefineabudgetprofileandassign

ittotheordertype. Thebudgetprofiledefinestheparametersforbudgeting. In

Customizing, youmust defineanumber range for your budget documents. To

do so, use number range 04.

Intheprofile,youcanspecifywhethertheavailabilitycontrolcannotbeactivated,

is activated manually via a function in the component menu, or is activated

automatically during budgeting. You cancheck funds availability usingeither

the annual or overall budgeted value.

Figure 50: Availability Control

Certainbusinesstransactionsresultinactualcostsandcommitmentsbeingposted

totheorder. Commitmentsrepresentobligationswhichwillleadtoactualcosts

throughsubsequentbusinessevents. Apurchaseorder, forexample,mayresult

in a commitment in Management Accounting which is then reduced by the

subsequent goods and invoice receipts.

Actual costs and commitments are funds allotted to an order and they can be

checkedagainstthebudgetusingtheavailabilitycontrol.

InCustomizing,youdefinehowavailabilitycontrolwilloperateforyourorder

types:

• Is availability control active?

• Forwhichtransactionswillavailabilitycontrolapply?

• What are the tolerance limits?

• Whatactionwillbeinitiatedwhentolerancelimitsareexceeded?

• Shouldcertaintypesofcostsbeexemptedfromavailabilitycontrol?

134

©2005SAPAG.Allrightsreserved. Q2/2005

第 143 页 / 共 181 页

AC415 Lesson: Budgeting and Availability Control Concept

Figure 51: Budgeting and Availability Control Concept

Youusethetolerancestodefinehowthesystemshouldrespondtoagivendegree

ofbudgetoverrun. Inourexample,ifthebudgetisexceededby5%(105%),the

system generatesa warning and a message is sent automatically to the person

responsible for thebudget. If thebudget is exceededby 15% (115%), an error

messageisdisplayed. Thedocumentthatcausedthebudgettobeexceededcan

nolongerbeposted. Thetolerancelevelsfor budgetsaredefinedinthebudget

profileaccordingtobusinesstransactiongroups. Differenttolerancelevelscanbe

set for different business transaction types.

IfyouselecttheactionWarning andMail, you must specifyabudget manager

inCustomizing. Ifnobudgetmanagerisentered, thesystemgeneratesanerror

message. Abudget managermaybeestablishedfor eachordertypeand object

class. Ifmorethanonebudgetmanagerisdefinedforanordertypeandclass,a

mailwill besenttoeachindividual. Forexample, intheaboveillustration, the

userPeter Millerwillreceiveamail for anydeviationsthatoccur inordertype

0100, object class OCOST.

135

Q2/2005 © 2005 SAP AG. All rights reserved.

第 144 页 / 共 181 页

Unit5: PlanningandBudgeting AC415

Figure 52: Budget Carryforward

Youcantransferunusedfundstothenextfiscalyearusingthebudgetcarryforward

function. TheSAPsystemwillcarryforwardthedifferencebetweenthebudget

and the actual amounts for theyear specified.

YoucannotcarryforwardbudgetsfororderswhichhavesystemstatusComplete

or which are flagged for deletion, nor can you carry forward negative budget

amounts.

You can execute the carry forward run more than once for a fiscal year. Each

executionoftheprogramcarriesforwardbudgetnotpreviouslyprocessed. You

canalsoreturnfundstothe“old”fiscalyear,uptotheamountofbudgetactually

carried forward.

Toexecutethecarryforwardprogram,enterthefiscalyearofthebudgetyouwant

to carryforwardand aselectionvariant whichspecifieswhichordersare to be

included. YoumustmaintaintheselectionvariantinCustomizing.

Commitments are not considered in the calculation of the unused funds. You

should, therefore, carryforwardyourcommitmentsbeforecarryingforwardthe

budget.

136

©2005SAPAG.Allrightsreserved. Q2/2005

第 145 页 / 共 181 页

AC415 Lesson: Budgeting and Availability Control Concept

Figure53: BudgetingandAvailabilityControlinDifferentCurrencies

Multinationalbusinesslocationsmayrequireyoutoperformbudgetingindifferent

currencies. FromRelease4.0,youcanchoosedifferentcurrenciestoenteryour

budget. Allbudgetitemsareconvertedandsavedautomaticallyinthecontrolling

area currency and the object currency.

If you choose budgeting in the controlling area currency, all budget items are

entered in the controlling area currency.

Ifyouchoosebudgetingintheobjectcurrency, youcanenterthebudgetinthis

currency for each object. The object currency is stored in the master record

of the object.

Whenbudgetinginafreely-definablecurrency,youcanchooseforeachbudgeting

transaction, inwhich currency it should beentered.

Youshouldspecifyinthebudgetprofileoftheordertypeortheprojectprofile,in

whichcurrencythebudgetitemsfortheorderortheprojectcanbeentered.

InR/3Enterpriseupwards,theavailabilitycontrolfunctionisnolongerexecuted

in the controlling area currency but in the object currency. This eliminates

exchange rate fluctuations.

137

Q2/2005 © 2005 SAP AG. All rights reserved.

第 146 页 / 共 181 页

Unit5: PlanningandBudgeting AC415

138

©2005SAPAG.Allrightsreserved. Q2/2005

第 147 页 / 共 181 页

AC415 Lesson: Budgeting and Availability Control Concept

Exercise 9: Budgeting and Availability

Control Concept

Exercise Objectives

After completingthisexercise, youwillbeableto:

• Budget an overhead order

• Establish availability control

• Test the availability control function

Business Example

Youmustcreateabudgetforyourmarketingbrochureorder. Theamountshould

bemonitoredusingtheavailabilitycontrolfunctions,thatis,everydebitmadeon

the order should first betestedagainst the budget.

Mostoftheavailabilitycontrolconfigurationhasalreadybeencompletedforyour

orderthroughthebudgetprofileassignedtoyourordertype. However,because

youareresponsibleforthebudget,youneedtoenterthisinthesystemsothatthe

system can inform you of any irregularities.

Onceyouhavefinishedmakingthenecessaryavailability control settings, test

them by posting items to the general ledger account that exceed the tolerance

limits.

Task 1:

Fulfil the following task:

1. InyourexistingMA##ordertype, createaneworderfor collecting the

costsofthecellphonemarketingcampaign. Theshorttextforthisorderis

“Cell Phone## Marketing Campaign”.

Assigntheordertocompanycode1000, businessarea9900, and profit

center 1402.

Release the order.

Task 2:

Fulfil the following task:

1. AllocatethemarketingcampaignabudgetofEUR10,000forthecurrent

fiscal year.

Save your budget

Continued on next page

139

Q2/2005 © 2005 SAP AG. All rights reserved.

第 148 页 / 共 181 页

Unit5: PlanningandBudgeting AC415

Task 3:

InCustomizing, review the availabilitycontrol fortheorder type(MA##) of

yourmarketingcampaignorderandcompletetheconfiguration.

1. Whatbudget profileisassignedtoyourordertype?

___________________________________________

2. Whattolerancelimitshavebeensetforthisbudgetprofileincontrolling

area 1000?

___________________________________________________

___________________________________________________

___________________________________________________

___________________________________________________

3. EnteryourselfasthebudgetmanagerforordertypeMA##incontrolling

area 1000 and object class OCOST.

Use your user ID (AC415-##)

Task 4:

Post the costs for your marketing campaign to check the availability control

functions.

1. TestthetolerancelimitsbydebitingyourorderwithG/Laccountpostings

sothatallthewarningscenariosthathavebeensetupinthesystemarecalled

uponeaftertheother. (Warning,warningbymail,mail,anderrormessage)

TherelevantmailislocatedintheSAPEasyAccessmenuunderOffice→

Workplace.

140

©2005SAPAG.Allrightsreserved. Q2/2005

第 149 页 / 共 181 页

AC415 Lesson: Budgeting and Availability Control Concept

Solution 9: Budgeting and Availability

Control Concept

Task 1:

Fulfil the following task:

1. InyourexistingMA##ordertype, createaneworderfor collecting the

costsofthecellphonemarketingcampaign. Theshorttextforthisorderis

“Cell Phone## Marketing Campaign”.

Assigntheordertocompanycode1000, businessarea9900, and profit

center 1402.

Release the order.

a) SAPEasyAccess→MasterData→OrderManager→MasterData

→ Create

EnterMA## in theOrder type field.

Choose Master data.

Enter“CellPhoneMarketingGroupCampaign##”intheShorttext

field.

Enter1000 in the Company code field.

Enter9900 in the Business area field.

Enter1402 in the Profit center field.

Release the order.

Save your order.

Make a note of the order number!

Task 2:

Fulfil the following task:

1. AllocatethemarketingcampaignabudgetofEUR10,000forthecurrent

fiscal year.

Continued on next page

141

Q2/2005 © 2005 SAP AG. All rights reserved.

第 150 页 / 共 181 页

Unit5: PlanningandBudgeting AC415

Save your budget

a) SAPEasyAccess→InternalOrders→Budgeting→OriginalBudget

→ Change

EntertheordernumberforyourmarketingcampaignintheOrder

field.

Press Enter.

Enter10000intheOriginalBudgetcolumnforyourorderforOverall

and the Current Fiscal Year.

Select Save.

Task 3:

InCustomizing, review the availabilitycontrol fortheorder type(MA##) of

yourmarketingcampaignorderandcompletetheconfiguration.

1. Whatbudget profileisassignedtoyourordertype?

___________________________________________

a) IMG→Controlling→InternalOrders→BudgetingandAvailability

Control → Maintain Budget Profile

ChooseMaintainbudgetprofilesinordertypes.

Scroll down to your order typeMA##.

The budget profile assigned to your order type MA## should be

000001.

Once you have checked the entries, go back to the SAP Reference

IMG screen.

2. Whattolerancelimitshavebeensetforthisbudgetprofileincontrolling

area 1000?

___________________________________________________

___________________________________________________

___________________________________________________

Continued on next page

142

©2005SAPAG.Allrightsreserved. Q2/2005

第 151 页 / 共 181 页

AC415 Lesson: Budgeting and Availability Control Concept

___________________________________________________

a) IMG→Controlling→InternalOrders→BudgetingandAvailability

Control→DefineToleranceLimitsforAvailabilityControl

Forcontrollingarea1000,budgetprofile000001,awarningmessage

willbedisplayedif thebusinesstransactionsperformedforanorder

useupmorethan95%ofthebudget. Awarningmessagewillbesent

bymailtothebudgetmanagerifthebusinesstransactionsperformed

foranorderexceed105%ofthebudget. Ifthebudgetisexceededby

115%,thebusinesstransactionwillbelockedandanerrormessagewill

bedisplayedexplainingwhythetransactioncannotbeexecuted.

Afteryourreview,returntotheSAPReferenceIMGscreen.

3. EnteryourselfasthebudgetmanagerforordertypeMA##incontrolling

area 1000 and object class OCOST.

Use your user ID (AC415-##)

a) IMG→Controlling→InternalOrders→BudgetingandAvailability

Control → Maintain Budget Manager

Choose Edit → New Entries.

Enter1000intheCOAr(controllingarea)field.

EnterMA## in theOrder type field.

Enter OCOST in the ObjCl field.

Enteryour userIDin theUsernamefield.

Select Save.

Task 4:

Post the costs for your marketing campaign to check the availability control

functions.

1. TestthetolerancelimitsbydebitingyourorderwithG/Laccountpostings

sothatallthewarningscenariosthathavebeensetupinthesystemarecalled

uponeaftertheother. (Warning,warningbymail,mail,anderrormessage)

Continued on next page

143

Q2/2005 © 2005 SAP AG. All rights reserved.

第 152 页 / 共 181 页

Unit5: PlanningandBudgeting AC415

TherelevantmailislocatedintheSAPEasyAccessmenuunderOffice→

Workplace.

a) SAP Easy Accessmenu →Accounting →Financial Accounting→

GeneralLedger→Posting→EnterG/LAccountDocument

EnterthecurrentdateintheDocumentdatefield.

Enter420000 in the Account field.

Choose Debit in the D/C field.

EnterEUR9501intheAmountdoc. curr. field.

EnterthenumberofyourmarketingcampaignorderintheOrder

field.

Enter113100 in the Account field.

Choose Credit in the D/C field.

Enter* inthe Amount doc. curr. field.

Press Enter.

Select Save.

Hint: Notethebudgetwarningmessage.

PressEntertoconfirmthewarningmessage. Notethatthetransaction

isonlypostedonceyouhaveconfirmedtheerrormessage.

StayintheEnterG/LAccountDocumentscreenforthenextexercise.

Repeatthe procedure again, but this timepostan additional EUR

1,000 toyour orderusingany cost element.

Hint: Notethenewbudgetwarningmessage.

PressEntertoclearthebudgetwarningmessage.

SAPEasyAccessmenu→Office→Workplace→Inbox

Double-clickontheunreadmessagesinyourinbox.

Double-clickonthee-mailmessageaboutyourorder.

Now try posting another EUR 1,000 to your order using any cost

element.

Ifyouravailabilitycontrolsettingsarecorrect,anerrormessagewillbe

displayedexplainingthatallpostingstothisobjectarelocked.

144

©2005SAPAG.Allrightsreserved. Q2/2005

第 153 页 / 共 181 页

AC415 Lesson: Budgeting and Availability Control Concept

Exercise 10: Optional Exercises

Exercise Objectives

After completingthisexercise, youwillbeableto:

• Create a planned settlement.

• Read the documentation on statistical planning key figures and

plan-integrated orders

Business Example

Try tosettleyourPCrepair/maintenanceandmarketing brochureorderstosee

the difference between orders that are plan-integrated and those that are not

plan-integrated. Before you can settle your PC repair/maintenance order, you

must first set up a rule for planned settlement that allocates the costs to the

Administration and Financials cost centers.

Find more information on planning statistical key figures and the benefits of

planning using plan-integrated orders.

Task 1:

CarryoutaplannedsettlementforthecostsofyourPCrepair/maintenanceand

marketing brochure orders.

1. EnteraperiodicplannedsettlementruleforyourPCrepair/maintenance

order. Settle50% of the coststo the Administration and Financialscost

center(2100), 25% toHuman Resources(2200), and25%toPurchasing

(2300).

Save your order.

2. CarryoutaplannedsettlementforyourPCrepair/maintenanceorderfor

the current periodand plan version 0.

Run the settlement in test mode.

Ifnoerrorsoccur, runitagaininproductionmode.

3. CheckthebalanceofyourPCrepair/maintenanceorder. Intheinformation

system,calluptheplanningoverviewinthecurrentperiodandplanversion

0.

4. Perform a planned settlement for your marketing brochure order for the

currentperiodandplanversion0. Runthesettlementintestmode. Whatis

the result and why do you get this result?

_________________________________________________

Continued on next page

145

Q2/2005 © 2005 SAP AG. All rights reserved.

第 154 页 / 共 181 页

Unit5: PlanningandBudgeting AC415

Task 2:

Usetheonlinehelptoreviewtheplanningdocumentation.

1. Readthedocumentationonstatistical keyfigures.

2. Readthedocumentationonplan-integratedorders.

146

©2005SAPAG.Allrightsreserved. Q2/2005

第 155 页 / 共 181 页

AC415 Lesson: Budgeting and Availability Control Concept

Solution 10: Optional Exercises

Task 1:

CarryoutaplannedsettlementforthecostsofyourPCrepair/maintenanceand

marketing brochure orders.

1. EnteraperiodicplannedsettlementruleforyourPCrepair/maintenance

order. Settle50% of the coststo the Administration and Financialscost

center(2100), 25% toHuman Resources(2200), and25%toPurchasing

(2300).

Continued on next page

147

Q2/2005 © 2005 SAP AG. All rights reserved.

第 156 页 / 共 181 页

Unit5: PlanningandBudgeting AC415

Save your order.

a) SAPEasyAccessmenu→InternalOrders→MasterData→Special

Functions → Order → Change

EnteryourPCrepair/maintenanceordernumberintheOrderfield.

Choose Settlement rule.

Choose Plan settlement.

Double-click on version 0.

In the first row, enter:

- CTR in the Cat field.

- 2100 in the Settlement receiver field.

- 50 in the % field.

- PER in the Settlement type field.

In the second row, enter:

- CTR in the Cat field.

- 2200 in the Settlement receiver field.

- 25 in the % field.

- PER in the Settlement type field.

In the third row, enter:

- CTR in the Cat field.

- 2300 in the Settlement receiver field.

- 25 in the % field.

- PER in the Settlement type field.

Choose Check.

ChooseContinuetocleartheinformationmessage.

If no errors were found, choose Save.

2. CarryoutaplannedsettlementforyourPCrepair/maintenanceorderfor

the current periodand plan version 0.

Run the settlement in test mode.

Continued on next page

148

©2005SAPAG.Allrightsreserved. Q2/2005

第 157 页 / 共 181 页

AC415 Lesson: Budgeting and Availability Control Concept

Ifnoerrorsoccur, runitagaininproductionmode.

a) SAPEasyAccessmenu→InternalOrders→Planning→Allocations

→Settlement→ Individual Processing

EnteryourPCrepair/maintenanceordernumberintheOrderfield.

Enter 0 in the Version field.

Enter period 1 in the Periodfield.

Enter period 12 in the To field.

EnterthecurrentfiscalyearintheFiscalyearfield.

Check the Test run box.

Choose Execute.

If thereareno errors, go backto the Planned Settlement: Internal

orders screen.

Deactivate the Test Run box.

Choose Execute.

3. CheckthebalanceofyourPCrepair/maintenanceorder. Intheinformation

system,calluptheplanningoverviewinthecurrentperiodandplanversion

0.

a) SAPEasyAccessmenu→InternalOrders→InformationSystem→

ReportsforInternalOrders→PlanningReports→Order: Planning

Overview

EnteryourPCrepair/maintenanceordernumberintheOrderfield.

EnterthecurrentfiscalyearintheFiscalyearfield.

Enterthecurrent periodin thePeriodfield.

Enter the current period in the To field.

Enter 0 in the Version field.

Choose Execute.

The balance should be zero.

4. Perform a planned settlement for your marketing brochure order for the

currentperiodandplanversion0. Runthesettlementintestmode. Whatis

the result and why do you get this result?

Continued on next page

149

Q2/2005 © 2005 SAP AG. All rights reserved.

第 158 页 / 共 181 页

Unit5: PlanningandBudgeting AC415

_________________________________________________

a) SAPEasyAccessmenu→InternalOrders→Planning→Allocations

→ Settlement→ Individual Processing

EnterthenumberofyourmarketingbrochureorderintheOrderfield.

Enter 0 in the Version field.

EnterthecurrentperiodinthePeriod field.

Enter the current period inthe To field.

EnterthecurrentfiscalyearintheFiscalyearfield.

Check the Test run box.

Choose Execute.

The plan settlement cannot be processed. The order is not

plan-integrated. Therefore the planned costs cannot be credited to

the selected cost centers.

Task 2:

Usetheonlinehelptoreviewtheplanningdocumentation.

1. Readthedocumentationonstatistical keyfigures.

a) SAPEasyAccessmenu→Help→SAPLibrary→SAPERPCentral

Component→Financials→Controlling(CO)→InternalOrders→

Planning→ManualPlanning→PlanningStatisticalKeyFigures

2. Readthedocumentationonplan-integratedorders.

a) SAPEasyAccessmenu→Help→SAPLibrary→SAPERPCentral

Component→Financials→Controlling(CO)→InternalOrders→

Planning→IntegratedPlanningforInternalOrders

150

©2005SAPAG.Allrightsreserved. Q2/2005

第 159 页 / 共 181 页

AC415 Lesson: Budgeting and Availability Control Concept

Lesson Summary

You should now be able to:

• Set up the profiles for the budgeting

• Enter budgets on overhead cost orders

• Set up the availability control

• Understandtheresultsofthebudgetingandavailabilitycontrol

• Transfer the budgetsinto the following year

151

Q2/2005 © 2005 SAP AG. All rights reserved.

第 160 页 / 共 181 页

UnitSummary AC415

Unit Summary

You should now be able to:

• Describe different planning methods

• Explain the plan profile

• Performoverallanddetailedplanningontheinternalorder

• List the options for automatic planning

• Distinguishbetweenorderswithandorderswithoutintegratedplanning

• Set up the profiles for the budgeting

• Enter budgets on overhead cost orders

• Set up the availability control

• Understandtheresultsofthebudgetingandavailabilitycontrol

• Transfer thebudgetsintothe following year

152

©2005SAPAG.Allrightsreserved. Q2/2005

第 161 页 / 共 181 页

Unit 6

Order Summarization and

Summarization Reports

Unit Overview

Herewedescribetheconceptofordersummarizationanditsrelatedsettings.

Theparticipantslearntonavigateinthesummarizationreports.

Unit Objectives

After completing thisunit, you will beableto:

• Summarize order data

• Open relevant summarization reports

• Analyze the results of the summarization

• Describetheconceptandcustomizingofordersummarization

• Navigate in the summarization report

Unit Contents

Lesson: Master Data and Order Summarization ...........................154

Exercise 11: Order Summarization.......................................157

Lesson: Summarization Report...............................................161

Exercise 12: Summarization Report.....................................163

153

Q2/2005 © 2005 SAP AG. All rights reserved.

第 162 页 / 共 181 页

Unit6: OrderSummarizationandSummarizationReports AC415

Lesson: Master Data and Order Summarization

Lesson Overview

Lesson Objectives

After completingthislesson, you will beable to:

• Summarize order data

• Open relevant summarization reports

• Analyze theresults of the summarization

Business Example

Figure 54: Master Data and Order Summarization

Foranefficientsystemofcontrolling,youoftenneedtogrouptogetherorderswith

similarcharacteristicsandanalyzethemasagroup. Youcanusethesummarization

characteristicstocreatetotalsrecords. Youcanexecutesummarizationreportsfor

thesevaluesfasterthanwhenyouusetotalsrecordsfromtheselectedorders. If

youhavealargenumberofordersyouneedtouseordersummarization.

Youcanspecifythestructureofyouranalysisbydefiningahierarchy. Eachlevel

ofthehierarchyisrepresentedbyacharacteristic. Notethatthecontrollingareais

always the first level of the hierarchy.

154

©2005SAPAG.Allrightsreserved. Q2/2005

第 163 页 / 共 181 页

AC415 Lesson: Master Data and Order Summarization

Youcansummarizebothcosts(plannedcosts,actualcosts,resultsanalysisdata)

and quantities (input and output quantities).

Thedefinitionofasummarizationhierarchydetermineswhichfieldsareusedin

summarizationand whichobjectsaresummarized.

Thelevelsofthesummarizationhierarchyarecreatedusingmasterdatafields.

Theavailablemasterdatafieldsarealreadypredefinedinthesystem.

Figure 55: Orders: Master Data - Layout

Themasterdatafieldsaredistributedoverninepredefinedgroupboxes. Youcan

displayorhidethefieldswithinthegroupboxesandsetthemas"Required"or

"Optional" entry fields.

Thegroupbox“GeneralData”islocatedintheordermasterdata. Itcomprises10

fieldsanditscontentsareforinformationpurposesonlyandhavenoeffectonthe

orderfunctions. Youcanenterinformationinthesefieldswhichhelpyouclassify

theorder. Youcanalsousethesefieldsforsummarization.

Forexample,youcanusethesefieldstoselectorders. However,pleasenotethat

thesystemdoesnotcheckwhethertheentriesinthesefieldsarevalidorconsistent.

FromRelease4.5,youcansummarizedirectlyusingordermasterdata,without

having to classify the orders first. SAP also provides a converter program

whichenablesyoutoswitchfromorderclassificationwithfreecharacteristicsto

user-defined master data fields.

155

Q2/2005 © 2005 SAP AG. All rights reserved.

第 164 页 / 共 181 页

Unit6: OrderSummarizationandSummarizationReports AC415

156

©2005SAPAG.Allrightsreserved. Q2/2005

第 165 页 / 共 181 页

AC415 Lesson: Master Data and Order Summarization

Exercise 11: Order Summarization

Exercise Objectives

After completingthisexercise, youwillbeableto:

• Configure an order summarization

• Executeasummarizationrunusinganexceptionrule

Business Example

BecausetheIDESGroupusessomanyoverheadcostorders,callingupreports

isoftentime-consuming. Youwanttospeeduptheprocessforaccessingreports

using the summarization functions.

Task:

Createasummarizationwhichreportsonthecontrollingarea,thecompanycode,

and the order type.

1. DefineahierarchyCO##. Enter“Hierarchy##forInternalOrdersOnly”

as a description.

SpecifyintheDatascope(objecttypes)that youonlywant tosummarize

internal orders.

2. AcceptthesettingsfortheDatascope(totalsrecords).

Budgetsandstructureplansaresummarizedbyoverallvalues,annualvalues,

variances/accrualcalculations,primaryandsecondarycosts.

3. Now define three hierarchy levels.

Thefirstlevelofthesummarizationreportshouldbethecontrollingarea,

thesecondlevelthecompanycode,andthethirdleveltheordertype.

4. Defineanexceptionrule(E##)usingtheCostvarianceagainstplanin

percent rule basis (via F4 Help).

ForThresholdredenter40%andforThresholdyellowenter30%.

Save your entries.

157

Q2/2005 © 2005 SAP AG. All rights reserved.

第 166 页 / 共 181 页

Unit6: OrderSummarizationandSummarizationReports AC415

Solution 11: Order Summarization

Task:

Createasummarizationwhichreportsonthecontrollingarea,thecompanycode,

and the order type.

1. DefineahierarchyCO##. Enter“Hierarchy##forInternalOrdersOnly”

as a description.

SpecifyintheDatascope(object types)thatyouonlywant tosummarize

internal orders.

a) SAPReferenceIMG→Controlling→InternalOrders→Information

System→Summarization→MaintainSummarizationHierarchies

Choose New entries.

EnterCO## in the Hierarchy field.

Enter“Hierarchy##forInternalOrdersOnly”asadescription.

Choose Save.

Double-clickonDatascope(object types).

IntheInternalOrdersline,checktheSummarizecheckbox.

2. Acceptthesettingsforthe Datascope(totalsrecords).

Budgetsandstructureplansaresummarizedbyoverallvalues,annualvalues,

variances/accrualcalculations,primaryandsecondarycosts.

a) Double-clickonDatascope(totalrecordstables).

Pleasedonotchangethesettinginthe“Notsummarize”column.

3. Now define three hierarchy levels.

Thefirstlevelofthesummarizationreportshouldbethecontrollingarea,

thesecondlevelthecompanycode,andthethirdleveltheordertype.

a) Double-click on Hierarchy levels.

Choose New entries.

Make the following entries:“”

Hierarchy Level Hierarchy Field

CO## 2 BUKRS(forcompanycode)

CO## 3 AUART(forordertype)

Choose Save.

Continued on next page

158

©2005SAPAG.Allrightsreserved. Q2/2005

Hierarchy Level Hierarchy Field
CO## 2 BUKRS(forcompanycode)
CO## 3 AUART(forordertype)

第 167 页 / 共 181 页

AC415 Lesson: Master Data and Order Summarization

4. Defineanexceptionrule(E##)usingtheCostvarianceagainstplanin

percent rule basis (via F4 Help).

ForThresholdredenter40%andforThresholdyellowenter30%.

Save your entries.

a) SAPReferenceIMG→Controlling→InternalOrders→Information

System→Summarization→DefineExceptionRules

Choose New Entries.

In the Rule No. field, enter: E##.

CallupthepossibleentriesfunctionintheRulebasisfield(F4).

SelectCost varianceagainstplaninpercent.

InthePercentage/Thresholdredfield,enter: 40.

InthePercentage/Thresholdyellowfield,enter: 30.

Choose Save.

159

Q2/2005 © 2005 SAP AG. All rights reserved.

第 168 页 / 共 181 页

Unit6: OrderSummarizationandSummarizationReports AC415

Lesson Summary

You should now be able to:

• Summarize order data

• Open relevant summarization reports

• Analyze theresults of the summarization

160

©2005SAPAG.Allrightsreserved. Q2/2005

第 169 页 / 共 181 页

AC415 Lesson: Summarization Report

Lesson: Summarization Report

Lesson Overview

For anefficient systemof controlling, youoften need to grouptogether orders

withsimilarcharacteristicsandanalyzethemasagroup. Youwilllearntodefinea

summarizationhierarchyandexecuteasummarizationrun.

Lesson Objectives

After completingthislesson, youwillbeable to:

• Describetheconceptandcustomizingofordersummarization

• Navigate in the summarization report

Business Example

Toperformreportingefficiently, especiallywithregardtosystemperformance,

you want to install order summarization.

Figure 56: Summarization Report

Inthesummarizationrunthesystemselects,foreachlevelofthehierarchy,the

ordersinaccordancewiththespecifiedcharacteristicsandcomputesatotal for

theordersthatarelocatedbelowthatlevel. Thetotalvaluesarewrittenforeach

hierarchy group to a summarization object.

Youcanscheduleabackgroundprocessforthesummarizationrunoruseparallel

processing,ifyouhavealargenumberoforderswithinyourhierarchy.

161

Q2/2005 © 2005 SAP AG. All rights reserved.

第 170 页 / 共 181 页

Unit6: OrderSummarizationandSummarizationReports AC415

Theinformationsystemincludesspecialreportsforinternalordersummarization

objects.

Youcanusethesummarizationreporttonavigatebetweenallordersinallorder

typesforallcompanycodesinonegivencontrollingarea. Onaselectedlevelyou

canalsouseanotherreporttoshowthedataofthatlevelinadifferentway.

Pleasenotethatifanorderiscreatedandpostedafterthesummarizationrun,it

doesnotappearinthehierarchy. Inthiscase,youhavetorunthesummarization

again.

162

©2005SAPAG.Allrightsreserved. Q2/2005