AC415 Lesson: Settlement: Special Subjects
Onthebasisofthesettlementruleswhichyouestablishforeachorder,thesystem
automaticallydeterminestheprocessingsequenceandassignsahierarchynumber
between000and999totheorder. Theordersaresettledfromthehighesttolowest
hierarchynumber. Inotherwords,000isatthetopofthehierarchy,whichmeans
that it is the last to be settled.
Ifyouentersettlementrulesthatwillnotresultinthecompletesettlementofyour
ordersinasinglesettlementrun,thesystemwilldisplaytheappropriatemessage.
Youcanmanuallyenterhierarchynumberstospecifythesequenceinwhichthe
ordersshouldbesettled. Inthiscase,youwillhavetorepeatsettlementprocessing
until all objects can be settled to zero.
Figure 40: Settlement: Alternative Posting Period
During order settlement you can enter a posting period that differs from the
settlement period. This means that you can correct settlements from the prior
periodafterithasbeenclosedandlockedandpostthecorrectioninthecurrent
period.
Todothis,entertheperiodtobecorrectedinthe“SettlementPeriod”field. The
postingperiodistheperiodinwhichthecorrectionisposted. Thepostingperiod
mustbetheperiodimmediatelyafterthecorrectionperiod.
You must process the correction settlement prior to making settlements in the
postingperiod. Thesystemwillnotallowyoutoenterapostingperiodwhichhas
alreadybeensettled. If youdeterminethatacorrectionsettlementfortheprior
periodisrequiredafterprocessingsettlementsinthepostingperiod,youmustfirst
reverseallthesettlementsperformedinthepostingperiod.
Thesettlementperiodandpostingperiodmustbewithinthesamefiscalyear.
119
Q2/2005 © 2005 SAP AG. All rights reserved.
第 130 页 / 共 193 页
Unit4: Period-endClosing AC415
Settlementcorrectionsarepossibleinbothindividualandcollectiveprocessing.
120
©2005SAPAG.Allrightsreserved. Q2/2005
第 131 页 / 共 193 页
AC415 Lesson: Settlement: Special Subjects
Facilitated Discussion
Discussion Questions
Usethefollowingquestionstoengagetheparticipantsinthediscussion. Feelfree
to use your own additional questions.
121
Q2/2005 © 2005 SAP AG. All rights reserved.
第 132 页 / 共 193 页
Unit4: Period-endClosing AC415
Lesson Summary
You should now be able to:
• Createsimplesettlement rulesautomatically
• Use the hierarchical settlement
• Settleordersin analternativeposting period
122
©2005SAPAG.Allrightsreserved. Q2/2005
第 133 页 / 共 193 页
AC415 Unit Summary
Unit Summary
You should now be able to:
• Describetransactionsintheperiod-endclosingthatcanleadtodebitpostings
on the orders
• Define and use the overhead costing sheet
• Post overheads on internal orders and understand the results in the
information system
• Credit orders through periodic reposting
• Distinguishbetweenandusethevarioussettlementoptions
• Enter settlement rules
• Defineandusetheallocation,sourceandPAtransferstructures
• Understandtheresultsofthesettlementusingspecialreports
• Createsimplesettlement rulesautomatically
• Use the hierarchical settlement
• Settleorders inanalternativepostingperiod
123
Q2/2005 © 2005 SAP AG. All rights reserved.
第 134 页 / 共 193 页
UnitSummary AC415
124
©2005SAPAG.Allrightsreserved. Q2/2005
第 135 页 / 共 193 页
Unit 5
Planning and Budgeting
117
You will find further information in the Instructor Guide in SAPNet on pages
39 to 47.
Unit Overview
We describe the various planning methods for overhead cost orders and carry
out overall planning for overhead cost orders. We list the automatic planning
functionsavailableforplanninginternalordersanddistinguishbetweenorders
with and without planning integration.
The participants learn to budget an overhead cost order and to set up and test
an availability check.
Unit Objectives
After completing thisunit, you will beableto:
• Describe different planning methods
• Explain the plan profile
• Performoverallanddetailedplanningontheinternalorder
• List the options for automatic planning
• Distinguishbetweenorderswithandorderswithoutintegratedplanning
• Set up the profiles for the budgeting
• Enter budgets on overhead cost orders
• Set up the availability control
• Understandtheresultsofthebudgetingandavailabilitycontrol
• Transfer the budgetsinto the following year
Unit Contents
Lesson: Planning Scope and Prerequisites.................................127
Exercise 8: Planning.......................................................135
125
Q2/2005 © 2005 SAP AG. All rights reserved.
第 136 页 / 共 193 页
Unit5: PlanningandBudgeting AC415
Lesson: Budgeting and Availability Control Concept.......................142
Exercise 9: Budgeting and Availability Control Concept ..............149
Exercise 10: Optional Exercises..........................................155
126
©2005SAPAG.Allrightsreserved. Q2/2005
第 137 页 / 共 193 页
AC415 Lesson: Planning Scope and Prerequisites
Lesson: Planning Scope and Prerequisites
Lesson Duration: 40 Minutes
118
Lesson Overview
Youlearnaboutdifferentplanningmethodsforoverheadcostordersandperform
overall and detailed planning for an order. The automatic planning functions
are listed and the differencesbetween plan-integrated and non-plan-integrated
orders are illustrated.
Lesson Objectives
After completingthislesson, youwillbeable to:
• Describe different planning methods
• Explain the plan profile
• Performoverallanddetailedplanningontheinternalorder
• List the options for automatic planning
• Distinguishbetweenorderswithandorderswithoutintegratedplanning
The instructor should explain the different planning methodsand illustrate the
differences from cost center accounting
Business Example
The IDES Group management is concerned with controlling expenditure.
However,theyhavenotyetdeterminedhowtheywanttoaddressthisrequirement
in the SAP System. Your task is to explain the difference between planning
andbudgetingforoverheadcostorders. Youhavespokentoseveralcostcenter
managersandhavefoundthattherearemanydifferentwaysinwhichtheywould
like to use the overhead order functions.
Somemanagerswanttoplantheirordersingreatdetail,whileotherswanttoplan
moregenerally. Theyalsowanttoknowhowtohandleorderswhicharecreated
duringthefiscalyearand,therefore,notincludedintheinitialplanningprocess.
Manyareconcernedthatusingthisapplicationwillincreasetheamountofmanual
planning that is required of them.
Youneedtopreparearesponsetothesemanagers,describinghowtheSAPsystem
supports order planning.
127
Q2/2005 © 2005 SAP AG. All rights reserved.
第 138 页 / 共 193 页
Unit5: PlanningandBudgeting AC415
Figure 41: Planning versus Budgeting
Duringorderplanning, youentercosts, activitiesandbusinessprocesseswhich
youexpecttoincurduringthelifecycleofanorder. Withorderplanning,youcan
compareplanandactualcosts,andcarryoutdifferentiatedvarianceanalysis.
Youadministratetheapprovedcostframeworkforanorderoranordergroupusing
BudgetManagement. Thebudgetistheapprovedcoststructureforanorderand
differsfromthecostplaninthatitisbinding. Thebudgetisthedevicebywhich
managementapprovestheexpectedcostsforanorderoveragiventimeframe.
You can enter theorder budgetmanuallyorcopybudgetinformationfromany
plan version.
Figure 42: Planning Scope and Methods
128
©2005SAPAG.Allrightsreserved. Q2/2005
第 139 页 / 共 193 页
AC415 Lesson: Planning Scope and Prerequisites
Costplanningisgenerallyperformedonorderswithlongdurations. Orderswhich
only exist for a veryshort period, such as orders for unexpected small repairs,
are usually not planned.
Internalorderplanningprovidesthreedifferentlevelsofcostplanning:
• Overall planning is the simplest way of planning costs for orders. You
canestimateoverallandannualvaluesforanorderindependentfromcost
elements.
• Whenmoredetailedinformationisavailableforaninternalorder,youcan
useprimaryandsecondarycostandrevenueplanning. Thistypecoversthe
planningofprimarycosts,activityinputsandrevenuesinmanualplanning.
Inautomaticplanning,youcanchargetheorderwithoverheads,distribution
costs,periodicrepostingcosts,assessmentcosts,indirectactivityallocation
costs, process costs, and settlement costs. If the order is integrated into
planning, you can carry out a plan credit using periodic repostings or
settlement.
• If you have access to more detailed information on sources of supply,
quantities,andprices,youcanperformunitcosting. Withunitcostingyou
can planonelevelbelowthecost element level.
Youcanplanstatisticalkeyfiguresasabasisforallocationsandasameansto
calculatethemanagementkeyfiguresfor yourorders.
Figure 43: Planning Profile for Overall Planning
Foroverallplanning,youneedtocreateaplanningprofile(notaplannerprofile)
and assign it to the order type. Of courseyou can use delivered standard SAP
profiles as well.
Within the profile you can specify the time horizon and whether you want to
plan on a yearly or overall basis.
129
Q2/2005 © 2005 SAP AG. All rights reserved.
第 140 页 / 共 193 页
Unit5: PlanningandBudgeting AC415
Pleasenotethatonlythosecostcenters,costelements,activitytypesandstatistical
keyfiguresthatareorganizedintogroupsandstoredintheplanningprofilecan
be taken into account during planning.
Forunitcosting, youneedtodefineandassignacostingvariant(CO-PC).The
costingvariantwillbetheinterfacetothebillofmaterials,materialmasterdataand
routing(theso-calledquantitystructure)whichyouneedforplanningonthislevel.
Figure 44: Overall Planning
Overallplanningisthemostbasicformoforderplanning. Here,youcreateaplan
byestimatingthelikelycostswhichwillbeincurredforanorder. Inadditionto
thedetailed,costelement-basedplanningvaluesusedincostcenteraccounting,
youcanalsosavegeneraloverallplanningvaluesforeachfiscalyearseparately
from cost elements. Youmaintain thesevaluesparallel tothevaluesfromcost
element planning and unit costing.
Youcanplaneitheroverall valuesorvaluesforindividualyears. Forplanning,
youneedtodefineaplanningprofilefirstandstoreitintheordertype.
You cancall up theprimarycostplanning, unit costing, revenueplanning, and
activityinput planning functionsstraight from the overall planningscreen. As
wellastheOverallValuescolumn,thesystemalsodisplaystheplannedtotal,the
unit costing values, and the cost element plan. The total planned value is the
sumofallthecostplanningformsused(overall,costandrevenueelement,unit
costing, and activity input planning).
130
©2005SAPAG.Allrightsreserved. Q2/2005
第 141 页 / 共 193 页
AC415 Lesson: Planning Scope and Prerequisites
Figure 45: Versions: Settings forIntegrated Planning
Youcanplanyourinternalordersinmultipleversions.
Whenyoucreateacontrollingarea,theSAPsystemautomaticallycreatesversion
000,whichisvalidforfivefiscalyears. Youcanalsoplanalternativeversions.
Note that the SAP system always uses version 000 when referencing actual
postings.
Alternativeversionsallowonlyplandatastorageforinternalorders,orthestorage
of parallel valuationsif you use Transfer Prices.
Therearetwoindicatorsusedforintegratedplanningintheversion:
• Integrated planning
– This indicator governs whether planning data is passed on to Profit
CenterAccountingandtheSpecialPurposeLedger. Italsoensuresthat
eachplanningchangeisdocumentedwithaplanlineitem.
• Integratedplanningwithcostcenters/businessprocesses
– To ensure that internal order planning is included in Cost Center
Accounting and Activity-Based Accounting, this indicator must be
active in the plan version.
Touseintegratedplanningforindividualorders,youalsoneedtosettherelevant
indicator in theorder master. You can createa default setting for this in the
order type.
131
Q2/2005 © 2005 SAP AG. All rights reserved.
第 142 页 / 共 193 页
Unit5: PlanningandBudgeting AC415
Figure 46: Effectsof Plan-Integrated Orderson planning
Withinintegratedplanningforinternalorders,youcanintegratecostelement
andactivityinputplanningforaninternalorderintocostcenterorbusinessprocess
planning. All the planned business allocations on the internal order are then
automaticallyupdatedonthesender/receivercostcenteroronthesender/receiver
business process.
Youcanonlyuseintegratedplanningforinternalorderswhentheinternalorder
alreadyexistsatthetimeofcostcenterplanning. Inthecaseoflongtermorders,
you can use integrated planning.
• If you are planning activity inputs for an integrated planning order, the
plannedactivityisupdatedtothecostcenterprovidingtheactivity.
• During planned settlement of the order, the order costs are debited from
the receiver.
• Overheadcalculationsonplan-integratedordersdebittheinternalorderand
credit a cost center.
• Ifyouareusingassessmentanddistribution,theplannedcostsofasender
costcenterareallocatedbasedonpre-definedassessmentanddistribution
keys.
• Periodicrepostingsofplan-integratedorderstocostcentersaresupported.
132
©2005SAPAG.Allrightsreserved. Q2/2005
第 143 页 / 共 193 页
AC415 Lesson: Planning Scope and Prerequisites
Figure 47: Copy Actual to Plan or Plan to Plan
Youcancopybothactualvaluesandplannedvaluesfrominternalordersintoa
plan version.
The actual business transactions are assigned to the corresponding, manually
planned business transactions.
133
Q2/2005 © 2005 SAP AG. All rights reserved.
第 144 页 / 共 193 页
Unit5: PlanningandBudgeting AC415
134
©2005SAPAG.Allrightsreserved. Q2/2005
第 145 页 / 共 193 页
AC415 Lesson: Planning Scope and Prerequisites
Exercise 8: Planning
125
Exercise Duration: 15 Minutes
Exercise Objectives
After completingthisexercise, youwillbeableto:
• Planordersusingtheoverallplanningfunctionandusetheoptionsavailable
fordetailedplanningwithcostelementsorunitcosting.
Business Example
Basedonyourdiscussionswiththecostcentermanagers,youknowthattheIDES
Group usestheoverallplanningfunctionsto producepreliminary plansfor the
future. Foreachfiscalyear,unitcostingisusedtoproducemoredetailedplanning
atcostelementoractivitylevel,inparticularforshort-termorders.
Totestthisfunction,youwillbeusingcostelementplanningtocreateacurrent
fiscal year plan for your PC repair/maintenance order. Since this isa standing
order, youcreateanoverallplanforthefollowingtwofiscalyears. Youusethe
unitcostingfunctiontocreateaplanfor yourmarketingbrochureorder forthe
currentfiscalyear. Sincethisisashort-termindividualorder,nootherplanningis
required.
Task 1:
CreateaplanforyourPCrepair/maintenanceorder usingtheoverallplanning
andcostelementplanningfunctions. Usetheoverallplanningtoplanthenext
two fiscal years.
Use overallplanning tocreate adetailedplanfor thecurrent fiscal year at cost
element level.
1. Usingtheoverallplanningfunction,planEUR50,000forallfiscalyears,
EUR 16,000 for thenext fiscal year, and EUR 17,500 for thefollowing
fiscal year. Check and save your order plan.
Caution: Notethatwhenyouaccessunitcostingorcost element
planningviatheoverallplanningfunctionandselect“Save”onthe
unitcostingorcostelementplanningscreens,thedataisonlysaved
temporarily. YoumustselectSaveattheoverallplanninglevelin
ordertosavetheplansforyourorderproperly.
Continued on next page
135
Q2/2005 © 2005 SAP AG. All rights reserved.
第 146 页 / 共 193 页
Unit5: PlanningandBudgeting AC415
2. For the current fiscal year and plan version 0, use the overall planning
screen to plan EUR 10,000 for direct labor costs (cost element 420000),
EUR 3,600 for spare parts (cost element 404000), EUR 400 for office
supplies (cost element 476000), and EUR 1,000 for IT materials (cost
element 476100).
Save your cost element planning information.
Task 2:
Usetheunitcostingfunctiontoproduceaplanforyourmarketingbrochures
for the current fiscal year.
Usetheoverallplanningscreentobranchtounitcosting.
1. Useunitcostingtoplantheanticipatedcostsforthepublicationofyourcell
phone marketing brochures.
UsetheVariableitem categoryfor yourentries.
Youneedtoorder60hoursofprinting,atacostofEUR50perhour.
Plan 2 daysof photographic services at EUR 1,000 per day. Plan both
itemsusingthecostelement417000(PurchasedServices).
Defineasubtotalrow(categoryS)forTotalPurchasedServices.
You alsoneed packagingmaterialsfor your brochures. Plan5000 pieces
of packaging at EUR 1 each. These costs should be planned using the
packaging materials cost element405000.
Createatotalsrow(categoryS)fortheTotalUnitCostingPlan.
Save the order plan.
2. Call up the Orders: Actual/Plan/Variance report for your marketing
brochures for the whole fiscal year.
136
©2005SAPAG.Allrightsreserved. Q2/2005
第 147 页 / 共 193 页
AC415 Lesson: Planning Scope and Prerequisites
Solution 8: Planning
Task 1:
CreateaplanforyourPCrepair/maintenanceorder usingtheoverallplanning
andcostelementplanningfunctions. Usetheoverallplanningtoplanthenext
two fiscal years.
Use overallplanning tocreate adetailedplanfor thecurrent fiscal year at cost
element level.
1. Usingtheoverallplanningfunction,planEUR50,000forallfiscalyears,
EUR 16,000 for thenext fiscal year, and EUR 17,500 for thefollowing
fiscal year. Check and save your order plan.
Caution: Notethatwhenyouaccessunitcostingorcost element
planningviatheoverallplanningfunctionandselect“Save”onthe
unitcostingorcostelementplanningscreens,thedataisonlysaved
temporarily. YoumustselectSaveattheoverallplanninglevelin
ordertosavetheplansforyourorderproperly.
a) SAP EasyAccess→Internal Orders→ Planning →Overall Values
→ Change Enter your PC repair/maintenance order number in the
Order field.
Press Enter.
Enter 50000 in the Overall field.
Enter16000inthefieldforthenextfiscalyear.
Enter17500inthefieldforthenextfiscalyear+1.
ChooseENTERtoviewtheupdatedPlannedtotalcolumn.
Choose Check.
If no errors are found, save your plan.
2. For the current fiscal year and plan version 0, use the overall planning
screen to plan EUR 10,000 for direct labor costs (cost element420000),
EUR 3,600 for spare parts (cost element 404000), EUR 400 for office
supplies (cost element 476000), and EUR 1,000 for IT materials (cost
element 476100).
Continued on next page
137
Q2/2005 © 2005 SAP AG. All rights reserved.
第 148 页 / 共 193 页
Unit5: PlanningandBudgeting AC415
Save your cost element planning information.
a) SAP EasyAccess→Internal Orders→Planning →Overall Values
→ Change
PlaceyourcursorinthePlanfieldforthecurrentfiscalyear.
ChooseExtras→DetailedPlanning→PrimaryCosts
In the Total plan costs column, enter:
-10000forcostelement420000,Directlaborcosts.
Usethe“Position…”pushbuttontonavigatemorequickly.
- 3600for costelement 404000, Spareparts.
- 400forcostelement476000, Officesupplies.
- 1000forcost element476100, IT materials.
ChooseSavetotemporarilysaveyourcostelementplan.
Save your overall plan
Task 2:
Usetheunitcostingfunctiontoproduceaplanforyourmarketingbrochures
for the current fiscal year.
Usetheoverallplanningscreentobranchtounitcosting.
1. Useunitcostingtoplantheanticipatedcostsforthepublicationofyourcell
phone marketing brochures.
UsetheVariableitem categoryfor yourentries.
Youneedtoorder60hoursofprinting,atacostofEUR50perhour.
Plan 2 daysof photographic services at EUR 1,000 per day. Plan both
itemsusingthecostelement417000(PurchasedServices).
Defineasubtotalrow(categoryS)forTotalPurchasedServices.
You alsoneed packagingmaterialsfor your brochures. Plan5000 pieces
of packaging at EUR 1 each. These costs should be planned using the
packaging materials cost element405000.
Createatotalsrow(categoryS)fortheTotalUnitCostingPlan.
Save the order plan.
a) EnterthenumberofyourmarketingbrochureorderintheOrderfield.
Press Enter.
Makesurethecursorisinthefieldforthecurrentfiscalyear.
Continued on next page
138
©2005SAPAG.Allrightsreserved. Q2/2005
第 149 页 / 共 193 页
AC415 Lesson: Planning Scope and Prerequisites
Choose Extras → Unit Costing.
Confirmthepop-upcontainingthecostingvariantPC02.
For item 1, enter:
- V in the Category column.
- 60 in the Quantity column.
- H in the Unit of measure field.
-PrintingServicesintheDescriptioncolumn.
- 50 in the Price - total field.
- 417000 in the Cost element field.
For item 2, enter:
- V in the Category column.
- 2 in the Quantity column.
- D(days) in the Unit of measurefield.
-PhotographicServicesintheDescriptioncolumn.
- 1000 in the Price - total field.
- 417000 in the Cost element field.
For item 3, enter:
- S in the Category column.
- Place the cursor in the Formula field. Either double-click on the
lineorselectInsert TotalsItem. Theformula=(1:3)shouldappear
in the Formula column.
-TotalPurchasedServicesintheDescriptionfield.
For item 4, enter:
- V in the Category column.
- 5000 in the Quantity column.
-PC(pieces)inthe Unitof measurecolumn.
- Packaging in the Description field.
- 1 in the Price - total field.
- 405000 in the Cost element column.
For item 5, enter:
- S in the Category column.
Continued on next page
139
Q2/2005 © 2005 SAP AG. All rights reserved.
第 150 页 / 共 193 页
Unit5: PlanningandBudgeting AC415
- Place cursor in the Formulafield. SelectInsert TotalsItem. The
formula=(1:5)shouldappearintheFormulacolumn.
-TotalUnitCostingPlanintheDescriptionfield.
-ChooseENTERtoviewtheresultsintheValue–Totalcolumn.
SelectSavetotemporarilysaveyourunitcostingplan.
ChooseSave tosavethechangestotheorderplan.
2. Call up the Orders: Actual/Plan/Variance report for your marketing
brochures for the whole fiscal year.
a) SAPEasyAccessmenu→InternalOrders→InformationSystem→
ReportsforInternalOrders→Plan/ActualComparisons→Orders:
Actual/Plan/Variance
Enter1000in theControllingareafield.
EnterthecurrentfiscalyearintheFiscalyearfield.
Enter 1 in the From period field.
Enter 12 in the To period field.
Enter 0 in the Plan version field.
Enterthenumberofyourmarketingbrochureorderinthe“Orvalue(s)”
field.
Choose Execute.
140
©2005SAPAG.Allrightsreserved. Q2/2005
第 151 页 / 共 193 页
AC415 Lesson: Planning Scope and Prerequisites
Lesson Summary
You should now be able to:
• Describe different planning methods
• Explain the plan profile
• Performoverallanddetailedplanningontheinternalorder
• List the options for automatic planning
• Distinguishbetweenorderswithandorderswithoutintegratedplanning
141
Q2/2005 © 2005 SAP AG. All rights reserved.
第 152 页 / 共 193 页
Unit5: PlanningandBudgeting AC415
Lesson: Budgeting and Availability Control Concept
Lesson Duration: 40 Minutes
132
Lesson Overview
You learntocreateabudget for an internal order and familiarizeyourself with
thebudgetprofile. Yousetupanavailabilitycontrolandobservetheeffectson
the orders. You see how to transfer a budget and how the budgeting works in
different currencies.
Lesson Objectives
After completingthislesson, you will beable to:
• Set up the profiles for the budgeting
• Enter budgets on overhead cost orders
• Set up the availability control
• Understandtheresultsofthebudgetingandavailabilitycontrol
• Transfer thebudgetsintothe following year
Theinstructorshouldshowhowtoassignbudgetsandthattheavailabilitycontrol
can be used toconsolidateand test thesebudgets.
Business Example
You should also review the system options for the budgeting and availability
controlandmakearecommendationforitsusewithinIDES.
142
©2005SAPAG.Allrightsreserved. Q2/2005
第 153 页 / 共 193 页
AC415 Lesson: Budgeting and Availability Control Concept
Figure 48: Budget Management
Thesystemrecognizesthefollowingbudgettypes:
• Theoriginalbudgetisthebudgetthatwasoriginallyallocated.
• Budget updatesforordersincludesupplementsand returnsandareused
whenunforeseeneventsandadditionalrequirementsforceacorrectiontothe
original budget
• Thecurrentbudgetincludestheoriginalbudgetandallbudgetupdates.
In addition to the budget update functions, you can also make changes to the
originalbudget. Youcanfreezetheoriginalbudgetusingstatusmanagement. To
do this, you must create a user status which prohibits the Budgeting business
transactionbutwhichallowsbudgetsupplementsandreturns.
Whenyoucreateorupdateyourbudget,thesystemdocumentsthetransactionina
lineitem. Youcanthendisplaythebudgetlineitems. Youcanalsoentertextfor
budgetlineitemsthatprovidesadditionalinformationforbudgeting.
In order tocreatea budget for an order, you must definea budget profile and
assignittotheordertype. Thebudgetprofiledefinestheparametersforbudgeting.
InCustomizing,youmustdefineanumberrangeforyourbudgetdocuments. To
do so, use number range 04.
Whenyousavethebudget,thesystemchecksthatthesumoftheannualvalues
matches the overall value for the order.
143
Q2/2005 © 2005 SAP AG. All rights reserved.
第 154 页 / 共 193 页
Unit5: PlanningandBudgeting AC415
Figure 49: Profile for Budgeting
Inordertocreateabudgetforanorder,youmustdefineabudgetprofileandassign
ittotheordertype. Thebudgetprofiledefinestheparametersforbudgeting. In
Customizing, youmust defineanumber range for your budget documents. To
do so, use number range 04.
Intheprofile,youcanspecifywhethertheavailabilitycontrolcannotbeactivated,
is activated manually via a function in the component menu, or is activated
automatically during budgeting. You cancheck funds availability usingeither
the annual or overall budgeted value.
Figure 50: Availability Control
144
©2005SAPAG.Allrightsreserved. Q2/2005
第 155 页 / 共 193 页
AC415 Lesson: Budgeting and Availability Control Concept
Certainbusinesstransactionsresultinactualcostsandcommitmentsbeingposted
totheorder. Commitmentsrepresentobligationswhichwillleadtoactualcosts
throughsubsequentbusinessevents. Apurchaseorder,forexample,mayresult
in a commitment in Management Accounting which is then reduced by the
subsequent goods and invoice receipts.
Actual costs and commitments are funds allotted to an order and they can be
checkedagainstthebudgetusingtheavailabilitycontrol.
InCustomizing,youdefinehowavailabilitycontrolwill operateforyourorder
types:
• Is availability control active?
• Forwhichtransactionswillavailabilitycontrolapply?
• What are the tolerance limits?
• Whatactionwillbeinitiatedwhentolerancelimitsareexceeded?
• Shouldcertaintypesofcostsbeexemptedfromavailabilitycontrol?
Figure 51: Budgeting and Availability Control Concept
Youusethetolerancestodefinehowthesystemshouldrespondtoagivendegree
ofbudgetoverrun. Inourexample,ifthebudgetisexceededby5%(105%),the
system generatesa warning and a message is sent automatically to the person
responsible for thebudget. If thebudget is exceededby 15% (115%), an error
messageisdisplayed. Thedocumentthatcausedthebudgettobeexceededcan
nolongerbeposted. Thetolerancelevelsfor budgetsaredefinedinthebudget
profileaccordingtobusinesstransactiongroups. Differenttolerancelevelscanbe
set for different business transaction types.
145
Q2/2005 © 2005 SAP AG. All rights reserved.
第 156 页 / 共 193 页
Unit5: PlanningandBudgeting AC415
Ifyouselecttheaction WarningandMail, youmust specifyabudget manager
inCustomizing. Ifnobudgetmanagerisentered,thesystemgeneratesanerror
message. Abudgetmanagermaybeestablishedfor eachordertypeandobject
class. Ifmorethanonebudgetmanagerisdefinedforanordertypeandclass,a
mail will besenttoeach individual. Forexample, intheaboveillustration, the
userPeterMillerwill receiveamail for anydeviationsthatoccur inordertype
0100, object class OCOST.
Figure 52: Budget Carryforward
Youcantransferunusedfundstothenextfiscalyearusingthebudgetcarryforward
function. TheSAPsystemwillcarryforwardthedifferencebetweenthebudget
and the actual amounts for theyear specified.
YoucannotcarryforwardbudgetsfororderswhichhavesystemstatusComplete
or which are flagged for deletion, nor can you carry forward negative budget
amounts.
You can execute the carry forward run more than once for a fiscal year. Each
executionoftheprogramcarriesforwardbudgetnotpreviouslyprocessed. You
canalsoreturnfundstothe“old”fiscalyear,uptotheamountofbudgetactually
carried forward.
Toexecutethecarryforwardprogram,enterthefiscalyearofthebudgetyouwant
to carryforwardand aselectionvariant whichspecifieswhichordersare to be
included. YoumustmaintaintheselectionvariantinCustomizing.
Commitments are not considered in the calculation of the unused funds. You
should, therefore, carryforwardyourcommitmentsbeforecarryingforwardthe
budget.
146
©2005SAPAG.Allrightsreserved. Q2/2005
第 157 页 / 共 193 页
AC415 Lesson: Budgeting and Availability Control Concept
Figure53: BudgetingandAvailabilityControlinDifferentCurrencies
Multinationalbusinesslocationsmayrequireyoutoperformbudgetingindifferent
currencies. FromRelease4.0,youcanchoosedifferentcurrenciestoenteryour
budget. Allbudgetitemsareconvertedandsavedautomaticallyinthecontrolling
area currency and the object currency.
If you choose budgeting in the controlling area currency, all budget items are
entered in the controlling area currency.
Ifyouchoosebudgetingintheobjectcurrency, youcanenterthebudgetinthis
currency for each object. The object currency is stored in the master record
of the object.
Whenbudgetinginafreely-definablecurrency,youcanchooseforeachbudgeting
transaction, inwhich currency it should beentered.
Youshouldspecifyinthebudgetprofileoftheordertypeortheprojectprofile,in
whichcurrencythebudgetitemsfortheorderortheprojectcanbeentered.
InR/3Enterpriseupwards,theavailabilitycontrolfunctionisnolongerexecuted
in the controlling area currency but in the object currency. This eliminates
exchange rate fluctuations.
147
Q2/2005 © 2005 SAP AG. All rights reserved.
第 158 页 / 共 193 页
Unit5: PlanningandBudgeting AC415
148
©2005SAPAG.Allrightsreserved. Q2/2005
第 159 页 / 共 193 页
AC415 Lesson: Budgeting and Availability Control Concept
Exercise 9: Budgeting and Availability
139
Control Concept
Exercise Duration: 15 Minutes
Exercise Objectives
After completingthisexercise, youwillbeableto:
• Budget an overhead order
• Establish availability control
• Test the availability control function
Business Example
Youmustcreateabudgetforyourmarketingbrochureorder. Theamountshould
bemonitoredusingtheavailabilitycontrolfunctions,thatis,everydebitmadeon
the order should first betestedagainst the budget.
Mostoftheavailabilitycontrolconfigurationhasalreadybeencompletedforyour
orderthroughthebudgetprofileassignedtoyourordertype. However,because
youareresponsibleforthebudget,youneedtoenterthisinthesystemsothatthe
system can inform you of any irregularities.
Onceyouhavefinishedmakingthenecessaryavailability control settings, test
them by posting items to the general ledger account that exceed the tolerance
limits.
Task 1:
Fulfil the following task:
1. InyourexistingMA##ordertype, createaneworderfor collecting the
costsofthecellphonemarketingcampaign. Theshorttextforthisorderis
“Cell Phone## Marketing Campaign”.
Assigntheordertocompanycode1000, businessarea9900, and profit
center 1402.
Release the order.
Task 2:
Fulfil the following task:
1. AllocatethemarketingcampaignabudgetofEUR10,000forthecurrent
fiscal year.
Save your budget
Continued on next page
149
Q2/2005 © 2005 SAP AG. All rights reserved.
第 160 页 / 共 193 页
Unit5: PlanningandBudgeting AC415
Task 3:
InCustomizing, review the availabilitycontrol fortheorder type(MA##) of
yourmarketingcampaignorderandcompletetheconfiguration.
1. Whatbudget profileisassignedtoyourordertype?
___________________________________________
2. Whattolerancelimitshavebeensetforthisbudgetprofileincontrolling
area 1000?
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
3. EnteryourselfasthebudgetmanagerforordertypeMA##incontrolling
area 1000 and object class OCOST.
Use your user ID (AC415-##)
Task 4:
Post the costs for your marketing campaign to check the availability control
functions.
1. TestthetolerancelimitsbydebitingyourorderwithG/Laccountpostings
sothatallthewarningscenariosthathavebeensetupinthesystemarecalled
uponeaftertheother. (Warning,warningbymail,mail,anderrormessage)
TherelevantmailislocatedintheSAPEasyAccessmenuunderOffice→
Workplace.
150
©2005SAPAG.Allrightsreserved. Q2/2005
第 161 页 / 共 193 页
AC415 Lesson: Budgeting and Availability Control Concept
Solution 9: Budgeting and Availability
Control Concept
Task 1:
Fulfil the following task:
1. InyourexistingMA##ordertype, createaneworderfor collecting the
costsofthecellphonemarketingcampaign. Theshorttextforthisorderis
“Cell Phone## Marketing Campaign”.
Assigntheordertocompanycode1000, businessarea9900, and profit
center 1402.
Release the order.
a) SAPEasyAccess→MasterData→OrderManager→MasterData
→ Create
EnterMA## in theOrder type field.
Choose Master data.
Enter“CellPhoneMarketingGroupCampaign##”intheShorttext
field.
Enter1000 in the Company code field.
Enter9900 in the Business area field.
Enter1402 in the Profit center field.
Release the order.
Save your order.
Make a note of the order number!
Task 2:
Fulfil the following task:
1. AllocatethemarketingcampaignabudgetofEUR10,000forthecurrent
fiscal year.
Continued on next page
151
Q2/2005 © 2005 SAP AG. All rights reserved.
第 162 页 / 共 193 页
Unit5: PlanningandBudgeting AC415
Save your budget
a) SAPEasyAccess→InternalOrders→Budgeting→OriginalBudget
→ Change
EntertheordernumberforyourmarketingcampaignintheOrder
field.
Press Enter.
Enter10000intheOriginalBudgetcolumnforyourorderforOverall
and the Current Fiscal Year.
Select Save.
Task 3:
InCustomizing, review the availabilitycontrol fortheorder type(MA##) of
yourmarketingcampaignorderandcompletetheconfiguration.
1. Whatbudget profileisassignedtoyourordertype?
___________________________________________
a) IMG→Controlling→InternalOrders→BudgetingandAvailability
Control → Maintain Budget Profile
ChooseMaintainbudgetprofilesinordertypes.
Scroll down to your order typeMA##.
The budget profile assigned to your order type MA## should be
000001.
Once you have checked the entries, go back to the SAP Reference
IMG screen.
2. Whattolerancelimitshavebeensetforthisbudgetprofileincontrolling
area 1000?
___________________________________________________
___________________________________________________
___________________________________________________
Continued on next page
152
©2005SAPAG.Allrightsreserved. Q2/2005
第 163 页 / 共 193 页
AC415 Lesson: Budgeting and Availability Control Concept
___________________________________________________
a) IMG→Controlling→InternalOrders→BudgetingandAvailability
Control→DefineToleranceLimitsforAvailabilityControl
Forcontrollingarea1000,budgetprofile000001,awarningmessage
willbedisplayedif thebusinesstransactionsperformedforanorder
useupmorethan95%ofthebudget. Awarningmessagewillbesent
bymailtothebudgetmanagerifthebusinesstransactionsperformed
foranorderexceed105%ofthebudget. Ifthebudgetisexceededby
115%,thebusinesstransactionwillbelockedandanerrormessagewill
bedisplayedexplainingwhythetransactioncannotbeexecuted.
Afteryourreview,returntotheSAPReferenceIMGscreen.
3. EnteryourselfasthebudgetmanagerforordertypeMA##incontrolling
area 1000 and object class OCOST.
Use your user ID (AC415-##)
a) IMG→Controlling→InternalOrders→BudgetingandAvailability
Control → Maintain Budget Manager
Choose Edit → New Entries.
Enter1000intheCOAr(controllingarea)field.
EnterMA## in theOrder type field.
Enter OCOST in the ObjCl field.
Enteryour userIDin theUsernamefield.
Select Save.
Task 4:
Post the costs for your marketing campaign to check the availability control
functions.
1. TestthetolerancelimitsbydebitingyourorderwithG/Laccountpostings
sothatallthewarningscenariosthathavebeensetupinthesystemarecalled
uponeaftertheother. (Warning,warningbymail,mail,anderrormessage)
Continued on next page
153
Q2/2005 © 2005 SAP AG. All rights reserved.
第 164 页 / 共 193 页
Unit5: PlanningandBudgeting AC415
TherelevantmailislocatedintheSAPEasyAccessmenuunderOffice→
Workplace.
a) SAP Easy Accessmenu →Accounting →Financial Accounting→
GeneralLedger→Posting→EnterG/LAccountDocument
EnterthecurrentdateintheDocumentdatefield.
Enter420000 in the Account field.
Choose Debit in the D/C field.
EnterEUR9501intheAmountdoc. curr. field.
EnterthenumberofyourmarketingcampaignorderintheOrder
field.
Enter113100 in the Account field.
Choose Credit in the D/C field.
Enter* inthe Amount doc. curr. field.
Press Enter.
Select Save.
Hint: Notethebudgetwarningmessage.
PressEntertoconfirmthewarningmessage. Notethatthetransaction
isonlypostedonceyouhaveconfirmedtheerrormessage.
StayintheEnterG/LAccountDocumentscreenforthenextexercise.
Repeatthe procedure again, but this timepostan additional EUR
1,000 toyour orderusingany cost element.
Hint: Notethenewbudgetwarningmessage.
PressEntertoclearthebudgetwarningmessage.
SAPEasyAccessmenu→Office→Workplace→Inbox
Double-clickontheunreadmessagesinyourinbox.
Double-clickonthee-mailmessageaboutyourorder.
Now try posting another EUR 1,000 to your order using any cost
element.
Ifyouravailabilitycontrolsettingsarecorrect,anerrormessagewillbe
displayedexplainingthatallpostingstothisobjectarelocked.
154
©2005SAPAG.Allrightsreserved. Q2/2005
第 165 页 / 共 193 页
AC415 Lesson: Budgeting and Availability Control Concept
Exercise 10: Optional Exercises
145
Exercise Duration: 15 Minutes
Exercise Objectives
After completingthisexercise, youwillbeableto:
• Create a planned settlement.
• Read the documentation on statistical planning key figures and
plan-integrated orders
Business Example
Try tosettleyourPCrepair/maintenanceandmarketing brochureorderstosee
the difference between orders that are plan-integrated and those that are not
plan-integrated. Before you can settle your PC repair/maintenance order, you
must first set up a rule for planned settlement that allocates the costs to the
Administration and Financials cost centers.
Find more information on planning statistical key figures and the benefits of
planning using plan-integrated orders.
Task 1:
CarryoutaplannedsettlementforthecostsofyourPCrepair/maintenanceand
marketing brochure orders.
1. EnteraperiodicplannedsettlementruleforyourPCrepair/maintenance
order. Settle50% of the coststo the Administration and Financialscost
center(2100), 25% toHuman Resources(2200), and25%toPurchasing
(2300).
Save your order.
2. CarryoutaplannedsettlementforyourPCrepair/maintenanceorderfor
the current periodand plan version 0.
Run the settlement in test mode.
Ifnoerrorsoccur, runitagaininproductionmode.
3. CheckthebalanceofyourPCrepair/maintenanceorder. Intheinformation
system,calluptheplanningoverviewinthecurrentperiodandplanversion
0.
4. Perform a planned settlement for your marketing brochure order for the
currentperiodandplanversion0. Runthesettlementintestmode. Whatis
the result and why do you get this result?
Continued on next page
155
Q2/2005 © 2005 SAP AG. All rights reserved.
第 166 页 / 共 193 页
Unit5: PlanningandBudgeting AC415
_________________________________________________
Task 2:
Usetheonlinehelptoreviewtheplanningdocumentation.
1. Readthedocumentationonstatistical keyfigures.
2. Readthedocumentationonplan-integratedorders.
156
©2005SAPAG.Allrightsreserved. Q2/2005
第 167 页 / 共 193 页
AC415 Lesson: Budgeting and Availability Control Concept
Solution 10: Optional Exercises
Task 1:
CarryoutaplannedsettlementforthecostsofyourPCrepair/maintenanceand
marketing brochure orders.
1. EnteraperiodicplannedsettlementruleforyourPCrepair/maintenance
order. Settle50% of the coststo the Administration and Financialscost
center(2100), 25% toHuman Resources(2200), and25%toPurchasing
(2300).
Continued on next page
157
Q2/2005 © 2005 SAP AG. All rights reserved.
第 168 页 / 共 193 页
Unit5: PlanningandBudgeting AC415
Save your order.
a) SAPEasyAccessmenu→InternalOrders→MasterData→Special
Functions → Order → Change
EnteryourPCrepair/maintenanceordernumberintheOrderfield.
Choose Settlement rule.
Choose Plan settlement.
Double-click on version 0.
In the first row, enter:
- CTR in the Cat field.
- 2100 in the Settlement receiver field.
- 50 in the % field.
- PER in the Settlement type field.
In the second row, enter:
- CTR in the Cat field.
- 2200 in the Settlement receiver field.
- 25 in the % field.
- PER in the Settlement type field.
In the third row, enter:
- CTR in the Cat field.
- 2300 in the Settlement receiver field.
- 25 in the % field.
- PER in the Settlement type field.
Choose Check.
ChooseContinuetocleartheinformationmessage.
If no errors were found, choose Save.
2. CarryoutaplannedsettlementforyourPCrepair/maintenanceorderfor
the current periodand plan version 0.
Run the settlement in test mode.
Continued on next page
158
©2005SAPAG.Allrightsreserved. Q2/2005
第 169 页 / 共 193 页
AC415 Lesson: Budgeting and Availability Control Concept
Ifnoerrorsoccur, runitagaininproductionmode.
a) SAPEasyAccessmenu→InternalOrders→Planning→Allocations
→Settlement→ Individual Processing
EnteryourPCrepair/maintenanceordernumberintheOrderfield.
Enter 0 in the Version field.
Enter period 1 in the Periodfield.
Enter period 12 in the To field.
EnterthecurrentfiscalyearintheFiscalyearfield.
Check the Test run box.
Choose Execute.
If thereareno errors, go backto the Planned Settlement: Internal
orders screen.
Deactivate the Test Run box.
Choose Execute.
3. CheckthebalanceofyourPCrepair/maintenanceorder. Intheinformation
system,calluptheplanningoverviewinthecurrentperiodandplanversion
0.
a) SAPEasyAccessmenu→InternalOrders→InformationSystem→
ReportsforInternalOrders→PlanningReports→Order: Planning
Overview
EnteryourPCrepair/maintenanceordernumberintheOrderfield.
EnterthecurrentfiscalyearintheFiscalyearfield.
Enterthecurrent periodin thePeriodfield.
Enter the current period in the To field.
Enter 0 in the Version field.
Choose Execute.
The balance should be zero.
4. Perform a planned settlement for your marketing brochure order for the
currentperiodandplanversion0. Runthesettlementintestmode. Whatis
the result and why do you get this result?
Continued on next page
159
Q2/2005 © 2005 SAP AG. All rights reserved.
第 170 页 / 共 193 页
Unit5: PlanningandBudgeting AC415
_________________________________________________
a) SAPEasyAccessmenu→InternalOrders→Planning→Allocations
→ Settlement→ Individual Processing
EnterthenumberofyourmarketingbrochureorderintheOrderfield.
Enter 0 in the Version field.
EnterthecurrentperiodinthePeriod field.
Enter the current period inthe To field.
EnterthecurrentfiscalyearintheFiscalyearfield.
Check the Test run box.
Choose Execute.
The plan settlement cannot be processed. The order is not
plan-integrated. Therefore the planned costs cannot be credited to
the selected cost centers.
Task 2:
Usetheonlinehelptoreviewtheplanningdocumentation.
1. Readthedocumentationonstatistical keyfigures.
a) SAPEasyAccessmenu→Help→SAPLibrary→SAPERPCentral
Component→Financials→Controlling(CO)→InternalOrders→
Planning→ManualPlanning→PlanningStatisticalKeyFigures
2. Readthedocumentationonplan-integratedorders.
a) SAPEasyAccessmenu→Help→SAPLibrary→SAPERPCentral
Component→Financials→Controlling(CO)→InternalOrders→
Planning→IntegratedPlanningforInternalOrders
160
©2005SAPAG.Allrightsreserved. Q2/2005
第 171 页 / 共 193 页
AC415 Lesson: Budgeting and Availability Control Concept
Lesson Summary
You should now be able to:
• Set up the profiles for the budgeting
• Enter budgets on overhead cost orders
• Set up the availability control
• Understandtheresultsofthebudgetingandavailabilitycontrol
• Transfer the budgetsinto the following year
161