Unit3: Event-BasedPostings AC410
Figure 39: Totals Values and Line Items
TheSAPsystemmakesadistinctionbetweenlineitemsandtotalsrecords. These
are recorded in separate database tables.
A lineitem is entered for each business transaction. You can accesstheseline
items using the line item report.
Forreporting,allthelineitemsenteredforbusinesstransactionsareautomatically
storedintotalsrecords. TheamountsaretotaledintheSAPsystembasedonthe
costcenter/costelementorcostcenter/costelement/activitytypeandenablesdata
tobeevaluatedmorequickly. YoucananalyzethetotalsrecordsusingaReport
Painter/Report Writer report.
Normally,youwouldanalyzeacostcenterusingaReportPainterreport. Ifyou
requiredetailedinformationforparticularcostelementspostedtothecostcenter,
you can call up the corresponding line items.
The line item report functionsas an itemization of actual costs, plan costs or
commitments based on the posting documents. This information is displayed
as a list (ABAP list display).
Example:InFI,personnelcostsforanexternalrepairfirmwerepostedtwicein
the same month.
Lineitem1: 420000Personnelcosts5.000.--CostCenterProduction07/2003
Lineitem2: 420000Personnelcosts3.500.--CostCenterProduction07/2003
TotalsRecord420000Personnelcosts8.500.--CostCenterProduction07/2003
110
©2005SAPAG.Allrightsreserved. 2005/Q2
第 119 页 / 共 403 页
AC410 Lesson: Reports in Cost Center Accounting
Interactive Information System
Figure 40: Interactive Information System
Youcanusetheinteractiveinformationsystemtototalandanalyzeall,orselected
business transactions, according to various criteria (for example, cost center /
cost element).
The totals records in the Report Painter report are normally analyzed, but
sometimes the line items from the summary report are also selected and
examined. You canalsomove from the line itemstothecorresponding source
documents. The source document canbeanFI document, or for example, an
accounting document from a reposting.
YoucancallupotherreportsusingtheReport/Reportinterface.
111
2005/Q2 © 2005 SAP AG. All rights reserved.
第 120 页 / 共 403 页
Unit3: Event-BasedPostings AC410
Settings for Reporting
Figure 41: User Settings
Youcanspecifygeneralanduser-specificdefaultvaluesfortheselectioncriteria,
andthereportcurrency. Theadvantageofusersettingsisthatmorethanone,or
all values that you normally need to enter before executing a report group are
automaticallydisplayed. Whenyoucallareport,theSAPsystemcheckstoseeif
youhavemadealltherequiredentries. Ifthisisthecase,thenthereportcanbe
executedwithoutanyentriesrequiredintheselectionscreen.
You can enter the following default values:
• Basicdata(controllingarea,costcenterorcostcentergroup,costelement,
and so on)
• Settings for extract management
• Planning timeframe
• Reporting timeframe
• Report currency
• Other specifications, such as the version
112
©2005SAPAG.Allrightsreserved. 2005/Q2
第 121 页 / 共 403 页
AC410 Lesson: Reports in Cost Center Accounting
Figure 42: Variation
Thevariationfunctionenablesyoutoselectaseparatereportforeachelement
ofagroupthatwasgeneratedduringaselectionrun. Thisfunctionisespecially
usefulwhencreatingareportinthebackgroundfromacostcentergroup,ifyou
wanttobeabletoswitchbetweencostcenterreportsatthesametime.
The variationfunction canonly beused ifyouhaveactivated it inthereport
definition.
Inthedialogboxforthevariation,youspecifywhichnodesand/orcostcentersare
tobeoutput. Youcanchooseoneofthreeoptionsforthisindicator:
• Breakdown provides you with reports for all cost centers and all nodes
of the selected group.
• Donotbreakdownprovidesyouwithonlyonereportforthehighestnode
of the selected group.
• Individualvaluesproducesreportsexclusivelyfortheindividualcostcenters
in the selected group.
Youcansavereportsforcostcentergroupsasextractswithactivatedvariation.
Whenyoucometoanalyzeyourextractsforthegroup,youcanthenaccessreports
for the individual cost centers quickly.
113
2005/Q2 © 2005 SAP AG. All rights reserved.
第 122 页 / 共 403 页
Unit3: Event-BasedPostings AC410
Figure 43: Line Item Report: Maintain layout
The SAP system provides you with standardized layouts. You can define
additional variantsfor global or user-specificuse.
You can select as many fields as required from the group of available fields
(including customer-specific fields) for a layout that is enterprise or
user-specific.
You need to define the item (column) in the report, and the column width for
each field.
Dependingonthecolumnwidth,theSAPsystemautomaticallyusestheshorttext
orlongtextfromthefieldname. Italsousesyourlog-onlanguage(ifavailable)
for the report.
TheSAPsystemprovidesyouwithstandardizedlayouts.
You can define filters for each column. Rowsthat fulfill filter criteria are not
displayed. However,theyareincludedinthetotalsandsubtotalscalculation.
YoucandefinetotalsinteractivelybyselectingthecolumnandchoosingTotals. It
ispossibletoselect morethanonecolumnat atime.
114
©2005SAPAG.Allrightsreserved. 2005/Q2
第 123 页 / 共 403 页
AC410 Lesson: Reports in Cost Center Accounting
Exercise 8: Reports in Cost Center
Accounting
Exercise Objectives
After completingthisexercise, youwillbeableto:
• Make user settings for report selection.
• ChecktheexpensespostedinFinancialAccountingtoeachcost center in
Controlling, insummaryand line itemreports.
• Navigatebetweendifferentcostcentersinacostcenterreport.
• Define an individual layout in the report.
Business Example
YouwanttodisplaytheexpensespostedinFItothecostcentersusingdifferent
reports. You also want to use some reporting tools that reduce the reporting
workloadandenableflexibleevaluationofinformation.
Task 1:
Youoften call up reportsthat havethesameselection criteria. To simplify the
process, youcanstorethesecriteriaasdefault values.
1. Storecontrollingarea1000intheusersettings, thecurrentperiodasthe
Reportingperiodinthecurrentfiscalyear,andversion0,asFurtherentries.
2. Call the cost centers: Plan/Actual/Variance report. Check whether your
selectioncriteriaaretransferredfromtheusersettings.
Task 2:
Display the costs from the exercise activity on general ledger account posting
in the report.
1. ProcessthecurrentperiodCostcenters: Plan/Actual/Variancereportforcost
center groupB## incontrollingareaEurope(1000), inthecurrent period
and for plan version 0.
2. The report provides an overview of the costs in the entire consulting
department. Use the variation function to display the costs of different
cost centers. Thengotothesummaryreportin cost center301##(FI/CO
Consulting).
Continued on next page
115
2005/Q2 © 2005 SAP AG. All rights reserved.
第 124 页 / 共 403 页
Unit3: Event-BasedPostings AC410
3. CalluptheActuallineitemsforareportrow. Whichadditionalinformation
on the cost element do you receive compared to the specifications in the
summary report?
4. Display the original FI document. How many line items are on the FI
document?
5. DisplaythecostaccountingdocumentforthesameCOlineitem. Howmany
lineitemsareonthecostAccountingdocument?
WhatcausesthedifferenceintheFI document?
Remain in the line item display.
Task 3:
Definealayoutinthelineitemreportaccordingtoyourrequirements.
1. Asyoudonotenteranyquantitieswhenposting, deletetheTotalquantity
entered andPosted unit of measurecolumns, then include other columns
of your choice.
2. SaveyourlayoutasLayout##, thenenteradescriptionforit. Indicatethe
layoutasUser-specific. Thisensuresthatonlyyoucanuseit.
3. CallupSelectlayouttocheckwhetheryourlayoutisavailableforselection,
as well as the SAP layouts.
116
©2005SAPAG.Allrightsreserved. 2005/Q2
第 125 页 / 共 403 页
AC410 Lesson: Reports in Cost Center Accounting
Solution 8: Reports in Cost Center
Accounting
Task 1:
Youoften call up reportsthat havethesameselection criteria. To simplify the
process, youcanstorethesecriteriaasdefault values.
1. Storecontrollingarea1000intheusersettings, thecurrentperiodasthe
Reportingperiodinthecurrentfiscalyear,andversion0,asFurtherentries.
a) CCA:InformationSystem→UserSettings
b)
Basic data
FieldNameorDataClass Values
Controlling Area 1000
Reporting timeframe
Fiscal year Current
Period Current
Further Details
Plan version 0
Save your data!
2. Call the cost centers: Plan/Actual/Variance report. Check whether your
selectioncriteriaaretransferredfromtheusersettings.
a) CCA:InformationSystem→Reports forcost center accounting→
Plan/ActualComparisons→Costcenters: Actual/Plan/Variance
Continued on next page
117
2005/Q2 © 2005 SAP AG. All rights reserved.
| FieldNameorDataClass | Values |
|---|---|
| Controlling Area | 1000 |
| Fiscal year | Current |
|---|---|
| Period | Current |
第 126 页 / 共 403 页
Unit3: Event-BasedPostings AC410
Task 2:
Display the costs from theexercise activity on general ledger account posting
in the report.
1. ProcessthecurrentperiodCostcenters: Plan/Actual/Variancereportforcost
center groupB##in controllingareaEurope(1000), inthecurrent period
and for plan version 0.
a)
FieldNameorDataClass Values
Controlling Area 1000
Fiscal year Current
From period Current
To period Current
Plan version 0
Cost center (values) B##
Program → Execute
2. The report provides an overview of the costs in the entire consulting
department. Use the variation function to display the costs of different
costcenters. Thengotothesummaryreportincostcenter 301##(FI/CO
Consulting).
a) Navigation On/Off icon
Inthenavigationlist,choosecostcenter301##.
3. CalluptheActuallineitemsforareportrow. Whichadditionalinformation
on the cost element do you receive compared to the specifications in the
summary report?
Answer: Positionyour cursor onareport row.
Double-click on Report row
ChoosetheCostCenters: ActualLineItemsreport.
Additional information:
a)Fromwhichlineitemstheoveralltotalforthecostelementresults
b)Theoffsettingaccountof thepostinginquestion
Continued on next page
118
©2005SAPAG.Allrightsreserved. 2005/Q2
| FieldNameorDataClass | Values |
|---|---|
| Controlling Area | 1000 |
| Fiscal year | Current |
| From period | Current |
| To period | Current |
| Plan version | 0 |
| Cost center (values) | B## |
第 127 页 / 共 403 页
AC410 Lesson: Reports in Cost Center Accounting
4. Display the original FI document. How many line items are on the FI
document?
Answer: Position your cursor ona line item.
Environment→Sourcedocumentordouble-clickthereportrow
12 Line items
5. DisplaythecostaccountingdocumentforthesameCOlineitem. Howmany
lineitemsareonthecostAccountingdocument?
WhatcausesthedifferenceintheFIdocument?
Remain in the line item display.
Answer: Position your cursor ona line item.
Environment → Accounting Documents → Accounting Documents →
ChooseControllingDocument→ExpandDocument
11 Line items
The credit posting on the balance sheet account is not relevant to Cost
AccountingandisthereforenottransferredtoManagementAccounting.
Task 3:
Definealayoutinthelineitemreportaccordingtoyourrequirements.
1. Asyoudonotenteranyquantitieswhenposting, deletetheTotalquantity
entered and Posted unit of measurecolumns, then include other columns
of your choice.
a) Return to the line item display.
Settings → Layout → Change
Select the Position icon. Select Total Quantity and Posted Unit of
Measure.
Icon Right arrow“Hideselected fields”
Changetolist: SwitchtotheHiddenFieldslist andselect thefields
you require.
→Icon Left arrow“Showselected fields”
Transfer icon.
Continued on next page
119
2005/Q2 © 2005 SAP AG. All rights reserved.
第 128 页 / 共 403 页
Unit3: Event-BasedPostings AC410
2. SaveyourlayoutasLayout##, thenenteradescriptionforit. Indicatethe
layoutasUser-specific. Thisensuresthatonlyyoucanuseit.
a) Settings → Layout → Save
FieldNameorDataClass Values
Layout Layout##
Name
User-specific Select
Transfer further settings
3. CallupSelectlayouttocheckwhetheryourlayoutisavailableforselection,
as well as the SAP layouts.
a) Settings → Layout → Choose
120
©2005SAPAG.Allrightsreserved. 2005/Q2
| FieldNameorDataClass | Values |
|---|---|
| Layout | Layout## |
| Name | |
| User-specific | Select |
第 129 页 / 共 403 页
AC410 Lesson: Reports in Cost Center Accounting
Lesson Summary
You should now be able to:
• Run totals reports and line item reports and explain additional functions
in the information system.
121
2005/Q2 © 2005 SAP AG. All rights reserved.
第 130 页 / 共 403 页
Unit3: Event-BasedPostings AC410
Lesson: Account Assignment Tools
Lesson Overview
Therearevariousoptionsforsimplifyingpostingsandkeepingpossiblesourcesof
errortoaminimum. Thevariousaccountassignmenttoolsareshowninthislesson.
Lesson Objectives
After completingthislesson, you will beable to:
• Describetheconfigurationoptionsthatfacilitatepostings.
Business Example
Youintroducevariousoptionsforaccountassignmenttotheotherprojectmembers
inorder tomakethepostingsprocesseasierforthem.
Default Account Assignment and Automatic Account
Assignment
Figure44: DefaultAccountAssignmentandAutomaticAccountAssignment
Youcandefineautomaticaccountassignmentsordefaultaccountassignmentsfor
postingsoftheprimarycostelementtype. TheSAPsystemthenautomatically
includesthespecified(additional)accountassignmentfortheprimarypostings
122
©2005SAPAG.Allrightsreserved. 2005/Q2
第 131 页 / 共 403 页
AC410 Lesson: Account Assignment Tools
you make. You define automatic and default account assignments for cost
elements that you always post to a particular cost center. You can also define
theassignmentofanoverheadorderorprofitcentertoacostelement. Whether
automatic or default, the account assignments are default values that can be
overwritten in the application.
Automaticofdefaultaccountassignmentsarerequiredforprimarycostelements
used in automatically-generated postings such as price differences, exchange
rate differences, and discounts.
Youenterthedefaultaccountassignmentinthecostelementmasterrecord.
Here, youentertheaccount assignmentatcontrollingarealevel andataccount
level.
You enter automatic account assignments in Customizing in the activity
“MaintainAutomaticAccountAssignment”. Inthisactivity,youcanalsodefine
moredetailedaccountassignmentstobusinessareasorprofitcenters.
Whenthesystemderivestheinformation,itdeterminesthemostdetailedaccount
assignment. ItreadstheentriesinCustomizingfirst. Ifthesystemdoesnotfind
any data here, then it uses the master data for cost elements. The assignment
objectsdefinedforautomaticaccountassignmentsthereforetakepriorityoverthe
additionalaccountassignmentsforthedefaultaccountassignment.
Validation
Figure 45: Validation
123
2005/Q2 © 2005 SAP AG. All rights reserved.
第 132 页 / 共 403 页
Unit3: Event-BasedPostings AC410
You can increase the accuracy of the Management Accounting data by using
validationandsubstitution. Invalidationandsubstitution,theSAPsystemchecks
whetherthedataenteredmeetsoneormoreoftheconditionsthatyoudefined.
Thesecheckstakeplaceduringdataentry,therebyensuringthatonlyvaliddata
is posted.
Youcreatevalidationsandsubstitutionsforthecontrollingareaandforaparticular
event. An event is a particular point in transaction processing. Thefollowing
eventshavebeendefinedfortheManagementAccountingcomponent:
• The“document row”(0001)calluppointusesdatafromtheManagement
Accountingdocumentheader(COBK)andManagementAccountingcoding
block(COBL)structures. Itcontrolspostinginexternalaccountingaswell
as in Management Accounting.
• The “document header” (0100) callup point uses data from COBK and
affects only manual Management Accounting postings, such as transfer
postings or activity allocations.
• The “CO Internal Posting: Sender/Receiver” (0002) event is only used
for Management Accounting internal postings, and is used for checking
sender-receiverrelationshipsinperiodicallocations.
Youusevalidationtocarryoutvaliditychecksonobjectssuchascostelementsor
costcenters. Iftheconditionsyouspecifiedforexecutingbusinesstransactions
arenot met, theSAPsystemdisplaysauser-definedmessage. Thiscould bea
warning, error, or information message, or the system stops your posting with
immediate effect.
124
©2005SAPAG.Allrightsreserved. 2005/Q2
第 133 页 / 共 403 页
AC410 Lesson: Account Assignment Tools
Substitution
Figure 46: Substitution
Youcanalsocarryoutvalidationcheckswhenmakingsubstitutions. However,
ifyourconditionismetforasubstitution,theSAPsystemsubstitutesthevalues
withothersdefinedbyyouwithoutinformingtheuserofthischange.
Anadditionalevent-theOrderEvent(0010)isdefinedforsubstitutions. Thisis
usedonlyfor collectiveprocessingofordermasterdata.
If you have defined a substitution that contradicts a validation condition, the
systeminformsyouof thisbydisplayingamessage. Wecanthereforesaythat
validationhaspriority, oris“stronger”thansubstitution.
125
2005/Q2 © 2005 SAP AG. All rights reserved.
第 134 页 / 共 403 页
Unit3: Event-BasedPostings AC410
Lesson Summary
You should now be able to:
• Describetheconfigurationoptionsthatfacilitatepostings.
126
©2005SAPAG.Allrightsreserved. 2005/Q2
第 135 页 / 共 403 页
AC410 Lesson: Correction Postings
Lesson: Correction Postings
Lesson Overview
Theoptionsforcorrectingpostingerrorsareshownhere.
Lesson Objectives
After completingthislesson, youwillbeable to:
• Correctoriginalpostingsmadetoincorrectcostcenters.
Business Example
PostingdocumentsfromHRandMMareoftenveryextensive. Trytodeviseeasy
waystocorrectfaultyaccountassignmentsinManagementAccounting.
Manual Postings of Costs and Revenues
Figure 47:
Youcanmanuallyrepostprimarycostsandrevenuesusingevent-basedrepostings.
Youusethisfunctionmainlytoadjust(correct)postingerrors.
Whenyoumakeaninternalreposting,theprimarycostsarereposted(underthe
original cost element)to areceivingorder. If theoriginaltransaction isposted
using an incorrect cost or revenue element, the transaction must be corrected
intheoriginalapplicationcomponentinorder toensurereconciliationbetween
external and internal accounting.
127
2005/Q2 © 2005 SAP AG. All rights reserved.
第 136 页 / 共 403 页
Unit3: Event-BasedPostings AC410
Note that no sender checkismade, in other wordsthe system doesnot check
whetherthecostsyourepostactuallyexistonthesendingcostcenter. Thismeans
thatnegativecostsmayappearonthesendingcostcenter.
The business transaction is documented by means ofline items on the sender
side and receiver side.
Youcanusethesystemtomakeevent-basedrepostingsautomatically. Following
a collective posting in FI that was assigned to a clearing cost center, these
automaticrepostingsareusedtopostthevaluesinManagementAccountingtothe
actualoriginatorsofthecosts. Forexample, salarypostingsfromthepersonnel
departmentcanbepostedintheirentiretytoaclearingcostcenter,thuskeeping
thenumberofpostingsinFinancialAccountingtoaminimum. Thissummarized
postingispassed through toManagement Accounting. In order for thepayroll
informationtobeusefultoManagementAccounting,however,thecostsneedto
beassignedtotheresponsiblecostcenters. Therepostingcreditstheclearingcost
centeranddebitstheoriginatorofthecostsbytheappropriateamount.
Reposting line items
Figure 48: Reposting line items
The function for reposting line items enables you to repost specific line items
fromManagementAccountingdocuments. Thisfunctionisdesignedtoenable
you to correct primary postings that you assigned to the wrong accounts. To
dothis, theManagement Accountingdocument mustcontainareferencetothe
original FI document.
128
©2005SAPAG.Allrightsreserved. 2005/Q2
第 137 页 / 共 403 页
AC410 Lesson: Correction Postings
Reposinglineitemsistheequivalentofareversalonthesenderobject.
Youcanalsoenter morethanonereceiver object.
RepostinglineitemscreatesManagementAccountingdocumentswhich,unlike
event-basedrepostingsofcosts,alwayscontainareferencetotheFIdocument.
As a result, you can trace a line item reposting back to the original Financial
Accounting document.
If you repost a line item in Management Accounting, the original account
assignment object remains noted in the FI document. To correct the account
assignmentobjectintheFIdocument,youwillneedtoreversetheFIdocument.
IfyouhavealreadycarriedoutalineitemrepostinginManagementAccounting
for this document, you will first need to reverse this reposting before you can
reverse the document in FI.
129
2005/Q2 © 2005 SAP AG. All rights reserved.
第 138 页 / 共 403 页
Unit3: Event-BasedPostings AC410
130
©2005SAPAG.Allrightsreserved. 2005/Q2
第 139 页 / 共 403 页
AC410 Lesson: Correction Postings
Exercise 9: Reposting Line Items
Exercise Objectives
After completingthisexercise, youwillbeableto:
• Make corrections by reposting line items
• ProvideargumentsforwhyerrorpostingsshouldbecorrectedinFinancial
Accounting and inManagement Accounting.
Business Example
In the project team, you have agreed to correct error postings in Management
Accounting or Financial Accounting after discussion with the Financial
Accounting department. You post a line item in Management Accounting to
become familiar with the function and how the information is presented. You
wouldalsoliketocheckwhetheritispossibletoreversethedocumentinFinancial
AccountingiftheadjustmenthasalreadybeenmadeinManagementAccounting.
Task 1:
Repostthecostsforofficesupplies(costelement476000)tothe“Organization”
costcenterthatwereassignedduringthefirstexerciseinthisunittothe“FI/CO
Consulting” cost center.
1. Repostthelineitemsforyourdocumentfromexercise7(younoteddown
thedocumentnumber)incompanycode1000andinthecurrentfiscalyear.
Postthe07(3,000.00to the301##cost center) posting itemto the201##
cost center (Organization).
Task 2:
Check the result of the reposting.
1. ProcesstheCostcenters: actual/plan/variancereportforthecurrentperiod
andplanversion0. Executethereportforthereceivingcostcenter201##
(Organization).
Continued on next page
131
2005/Q2 © 2005 SAP AG. All rights reserved.
第 140 页 / 共 403 页
Unit3: Event-BasedPostings AC410
2. Displaytheactuallineitemsforthecostcentersinreportrow476000Office
supplies. Accessthesourcedocumentforthelineitem. Whichcostcenteris
displayedasthesenderforcostelement476000onthedocument?
3. Howcanyouensurethatthecorrectreceivercostcenter201##(Organization)
isalsodisplayedontheFinancialAccountingdocument?
Task 3:
Solve the following task:
1. CheckwhetheritispossibletoreversethedocumentinFI(reversalreason
01),eventhoughtheerrorpostingwasalreadycorrectedinCO.Reversal:
Yes/No:___________________________________________________________
Reason:
Continued on next page
132
©2005SAPAG.Allrightsreserved. 2005/Q2
第 141 页 / 共 403 页
AC410 Lesson: Correction Postings
Task 4:
Solve the following tasks:
1. WhenisitusefultocorrectanerrorpostinginFinancialAccountingandin
Management Accounting?
2. Astaffmemberfromtheprojectteamislessexperiencedwiththereposting
function than you are, and would like to know the following: A newly
opened cost center hasnot yet been debited with primarycosts. Isit still
possibletorepostcostsfromthiscostcentertoanothercostcenter?
Isitpossibletorepostlineitemsfromthiscostcenter?
133
2005/Q2 © 2005 SAP AG. All rights reserved.
第 142 页 / 共 403 页
Unit3: Event-BasedPostings AC410
Solution 9: Reposting Line Items
Task 1:
Repostthecostsforofficesupplies(costelement476000)tothe“Organization”
costcenterthatwereassignedduringthefirstexerciseinthisunittothe“FI/CO
Consulting” cost center.
1. Repostthelineitemsforyourdocumentfromexercise7(younoteddown
thedocumentnumber)incompanycode1000andinthecurrentfiscalyear.
Continued on next page
134
©2005SAPAG.Allrightsreserved. 2005/Q2
第 143 页 / 共 403 页
AC410 Lesson: Correction Postings
Postthe07(3,000.00to the301##cost center) posting itemto the201##
cost center (Organization).
a) CCA:ActualPostings→RepostLineItems→Enter
FieldNameorDataClass Values
Document number See exercise 7
Inlineitem07,changeaccountassignment1from
Cost center 301## to cost center 201##.
Save your data.
Task 2:
Check the result of the reposting.
1. ProcesstheCostcenters: actual/plan/variancereportforthecurrentperiod
andplanversion0. Executethereportforthereceivingcostcenter201##
(Organization).
a) CCA:InformationSystem→Reports forcost center accounting→
Plan/ActualComparisons→Costcenters: Actual/Plan/Variance
b)
FieldNameorDataClass Values
Controlling Area 1000
Fiscal Year Current
From period Current
To period Current
Plan version 0
Cost center (values) 201##
Program → Execute
Continued on next page
135
2005/Q2 © 2005 SAP AG. All rights reserved.
| FieldNameorDataClass | Values |
|---|---|
| Document number | See exercise 7 |
| FieldNameorDataClass | Values |
|---|---|
| Controlling Area | 1000 |
| Fiscal Year | Current |
| From period | Current |
| To period | Current |
| Plan version | 0 |
| Cost center (values) | 201## |
第 144 页 / 共 403 页
Unit3: Event-BasedPostings AC410
2. Displaytheactuallineitemsforthecostcentersinreportrow476000Office
supplies. Accessthesourcedocumentforthelineitem. Whichcostcenteris
displayedasthesenderforcostelement476000onthedocument?
Answer: Positionyourcursoronreportrowcostelement476000.
Double-click on Report row.
Select the Actual Line Items report.
Positionyourcursoronthelineitemwiththerepostingamount3000.
Environment→SourceDocumentordouble-clickthereportrow
Cost center 201##
3. Howcanyouensurethatthecorrectreceivercostcenter201##(Organization)
isalsodisplayedontheFinancialAccountingdocument?
Answer: Reversal of incorrectly assigned posting in FI and reposting to
cost center 201##
Task 3:
Solve the following task:
1. CheckwhetheritispossibletoreversethedocumentinFI(reversalreason
01),eventhoughtheerrorpostingwasalreadycorrectedinCO.Reversal:
Yes/No:___________________________________________________________
Reason:
a) Accounting→FinancialAccounting→GeneralLedger→Document
→ Reverse → Individual Reversal
b)
FieldNameorDataClass Values
Document number See exercise 1.1
Company code 1000
Fiscal Year Current
Reversal reason 01
Save your data.
Errormessage:ReverseManagementAccountingrepostingdocument
first.
Continued on next page
136
©2005SAPAG.Allrightsreserved. 2005/Q2
| FieldNameorDataClass | Values |
|---|---|
| Document number | See exercise 1.1 |
| Company code | 1000 |
| Fiscal Year | Current |
| Reversal reason | 01 |
第 145 页 / 共 403 页
AC410 Lesson: Correction Postings
Task 4:
Solve the following tasks:
1. WhenisitusefultocorrectanerrorpostinginFinancialAccountingandin
Management Accounting?
Answer: Ifyouwantthecorrectreceivercostcentertobedisplayedinthe
accountingdocument,youwillneedtoreversethedocumentinFinancial
Accounting, otherwise you can repost the document in Management
Accounting.
2. Astaffmemberfromtheprojectteamislessexperiencedwiththereposting
function than you are, and would like to know the following: A newly
opened cost center hasnot yet been debited with primarycosts. Isit still
possibletorepostcostsfromthiscostcentertoanothercostcenter?
Isitpossibletorepostlineitemsfromthiscostcenter?
Answer: Manualrepostingofcostsispossible? nocheckonsender
Repostingoflineitemsisnotpossible? nolineitemposted.
137
2005/Q2 © 2005 SAP AG. All rights reserved.
第 146 页 / 共 403 页
Unit3: Event-BasedPostings AC410
Lesson Summary
You should now be able to:
• Correctoriginalpostingsmadetoincorrectcostcenters.
138
©2005SAPAG.Allrightsreserved. 2005/Q2
第 147 页 / 共 403 页
AC410 Lesson: Automatic Commitment and Funds Reservation
Lesson: Automatic Commitment and Funds Reservation
Lesson Overview
The commitment is inthe MaterialsManagement componentsand represent a
fundscommitment inthecostcenteraccounting, i.e. costtobeexpectedinthe
future.
Lesson Objectives
After completingthislesson, youwillbeable to:
• Explainautomaticcommitmentsandfundscommitment.
Business Example
Asyourequireinformationonfuturepaymentcommitmentsinyourcostcenter,
consider the use of commitments.
Automatic commitment
Figure 49: Automatic commitment
139
2005/Q2 © 2005 SAP AG. All rights reserved.
第 148 页 / 共 403 页
Unit3: Event-BasedPostings AC410
Commitments are payment obligations that are not entered into the accounts,
butthat leadtoactualcostsat alater date. They areincurred in thepurchasing
function, inthe“MaterialsManagement”component:
• The internal communication for a purchasing request is known as a
purchaserequisition(fromtheorderingpartytothepurchaser). Apurchase
requisitionisaprovisionalobligation,thatcanbechangedatanytime. You
donotneedtoassignaCOobjecttoapurchaserequisitionrow. Ifyoudo
notdoso,thenthecommitmentisnotdisplayedinManagementAccounting.
• Apurchaseorderisacontractualagreementtopurchasegoodsorservices
fromavendoraccordingtoagreedconditions. Apurchaseorderrepresentsa
firmcommitmentsinceitisbasedonacontractualobligation. Youneedto
specifyaManagementAccountingobjectforaPOrowthatisassignedtoa
costelement. ThecommitmentisalsodisplayedinManagementAccounting.
Ifyoucreateapurchaseorderwith referencetoapurchaserequisition, the
commitment isreclassified (asa purchase order commitment) in Management
Accounting.
Thecommitmentisreducedbyprocessinggoodsreceiptsagainstthepurchase
order. Actual costs are posted to the Management Accounting object. This
businesstransaction iscontinueduntil thepurchaseorderisprocessed, andthe
commitment amount is zero.
YoumustactivateCommitmentManagement,inManagementAccounting,in
the controlling area. Furthermore, the cost center must not be blocked for the
execution of commitments (locking indicator).
Commitmentsarenotreducedwhenyoucreateanoutlineagreement. Theseare
only incurred when you create the contract release order (contract), or goods
release order (scheduling agreements).
140
©2005SAPAG.Allrightsreserved. 2005/Q2
第 149 页 / 共 403 页
AC410 Lesson: Automatic Commitment and Funds Reservation
Funds Commitment
Figure 50: Funds Commitment
You can use the manual funds commitment function (manual commitment)
to enter expected costs that were not entered in the system using a purchase
requisition or purchaseorder. Thisenablesyou to reserveplanned amounts at
an early stage.
The funds commitment must be reduced when you enter corresponding
transactionssuch aspurchaserequisitions, purchaseorders, and invoices. You
reduce the funds commitment by entering the corresponding amount for a
reservationitem. Theamountyouentermustnotexceedtheamountstillopen.
Youcanspecifyreductionreferencesinthereductionhistoryforacommitment
reductionalreadyentered. Thereferencesaretoafollow-updocumentthatwill
cause(orhavealreadycaused)theactualcosts. Thisisforinformationpurposes
only.
141
2005/Q2 © 2005 SAP AG. All rights reserved.
第 150 页 / 共 403 页
Unit3: Event-BasedPostings AC410
Lesson Summary
You should now be able to:
• Explainautomaticcommitmentsandfundscommitment.
142
©2005SAPAG.Allrightsreserved. 2005/Q2
第 151 页 / 共 403 页
AC410 Lesson: Direct Activity Allocation
Lesson: Direct Activity Allocation
Lesson Overview
Thedirectactivityallocationdealswiththemeasurement,posting,andallocation
of an organizational activity.
Lesson Objectives
After completingthislesson, youwillbeable to:
• Executeadirectaccountingallocationandcorrectanaccountingallocation.
Business Example
Youwanttoenterall(consulting)activities,whichyouprovideforacustomer,to
acostobject. Youcanusethistocreatethebillingdocuments.
Direct Activity Allocation
Figure 51: Direct Activity Allocation
Direct activity allocation deals with the measurement, posting, and allocation
of an organizational activity.
You need to create the corresponding (measurable) tracing factors in the SAP
system. TheseareknownasactivitytypesinCostCenterAccounting. Todirectly
allocateactivity,createanactivitytype(activitytypecategory1=manualentry,
manual allocation).
143
2005/Q2 © 2005 SAP AG. All rights reserved.
第 152 页 / 共 403 页
Unit3: Event-BasedPostings AC410
Ifyouwanttoenteradirectactivityallocation,enterthecostcenterthatprovides
theactivity(sender costcenter), theobjectthat receivestheactivity (receiver),
thetype(activitytype),andthequantityoftheactivityprovided. Notethatonly
onecostcenterfromthesendercanbeallocatedtoaninternalactivityallocation.
ThereceivercanbeanyrealManagementAccountingobjectsuchasacostcenter,
an order, a project, and so on.
Toallocateactivitiesdirectly,youneedtodefinewhichcostcentersaretoprovide
which activity types, by planning activity output. You do this by planning
activity output.
During direct activity allocation, the sender cost center is credited, and the
receiving cost objects are debited. Debiting and crediting are executed a
secondarycostelement(category“43”). Debitingandcreditingaretheactivity
provided, multiplied by the activity price.
Thecostelementusedfordirectallocationofinternalactivityisderiveddirectly
fromthemasterdatafortheactivitytype. Thecost elementcannotbechanged
in the allocation transaction.
Directactivityallocationisrecordedbylineitemsonthesendersideandreceiver
side.
Figure 52: Reposting Direct Activity Allocation
Repostinginternalactivityallocationisusedtoadjustpostingfields.
Asearchfunctionisavailable,whichprovidesyouwiththedocumentsyouare
looking for.
144
©2005SAPAG.Allrightsreserved. 2005/Q2
第 153 页 / 共 403 页
AC410 Lesson: Direct Activity Allocation
Thetotalquantityoftheallocatedactivitymustremainthesame,althoughyou
can allocatethequantities to different receivers.
You can make adjustments inperiods, but not in the same period from which
the document to be adjusted originates. However, the fiscal year must remain
the same.
Youcanrepostthefollowingdocumentsfordirectactivityallocation:
• DocumentsenteredmanuallyintoCostCenterAccounting
• Management Accounting documentsfor confirmations (from Production
Planning and Controlling)
• ManagementAccountingdocumentsfortimerecording(fromtimesheet)
Reposting creates a reference in the reposting document to the Management
Accounting source document.
145
2005/Q2 © 2005 SAP AG. All rights reserved.
第 154 页 / 共 403 页
Unit3: Event-BasedPostings AC410
146
©2005SAPAG.Allrightsreserved. 2005/Q2
第 155 页 / 共 403 页
AC410 Lesson: Direct Activity Allocation
Exercise 10: Direct Activity Allocation
Exercise Objectives
After completingthisexercise, youwillbeableto:
• Debit the corresponding cost objects (direct activity allocation) with the
consultant activities
Business Example
In your project team, you have agreed that the consultants who work for a
companyaretodirectlydebitthecostobjectssetupforthisonceaweek. Foreach
companycustomer,theCO-OPAteam(overheadcostorders)hasalreadysetup
aninternalorderasacostobject. Onthisinternalorder,youcananalyzetowhat
extenteachcompanyhasusedconsultingactivityfromtheconsultingdepartment.
Task 1:
Theconsultantsenterthenumberofconsultinghoursthattheyhaveworkedfor
different projects.
1. The internal orders that already exist in the system act as cost collectors
(consulting company A and consulting company B). The consultants
normallyentertheirownactivity,andthustriggerdirectactivityallocation.
For test purposes, enter the consulting activity for the consultants, using
today's date in version 0, with screen variant Order. Now post the
following data in the list entry:
Sendercostcenter Activity Receiver Totalquantity
Type Order
301## (FI/CO J## Consulting 800
Consulting) companyA
301## (FI/CO S## Consulting 1000
Consulting) companyA
302##(LOConsulting) J## Consulting 600
companyB
302##(LOConsulting) S## Consulting 800
companyB
Continued on next page
147
2005/Q2 © 2005 SAP AG. All rights reserved.
| Sendercostcenter | Activity Type | Receiver Order | Totalquantity |
|---|---|---|---|
| 301## (FI/CO Consulting) | J## | Consulting companyA | 800 |
| 301## (FI/CO Consulting) | S## | Consulting companyA | 1000 |
| 302##(LOConsulting) | J## | Consulting companyB | 600 |
| 302##(LOConsulting) | S## | Consulting companyB | 800 |
第 156 页 / 共 403 页
Unit3: Event-BasedPostings AC410
2. Display all the screen variants for direct activity allocation again in the
match-code. Why is the sender category never mentioned in the screen
variant name, but the receiver object is?
Task 2:
Check the postings (for direct activity allocation) in reports in Cost Center
Accounting.
1. Call thecost centers: actual/plan/variance report for thecurrentperiod
andplanversion0. Executethereportreportincostcenter301##(FI/CO
Consulting).
2. Page down to displaytheallocated quantities.
3. Display the actual line items for cost centers for the report row in the
secondary cost element 6262## (senior consulting ##), or6261## (junior
consulting##). SwitchtotheSecondaryCosts: Activityallocationlayout.
Cost allocation line item display variant.
4. Callthecostcenters: ActivityPricesreportforthecostcentergroupB30##
inversion0forallperiodsinthecurrentfiscalyear,toobtainanoverview
of all the prices.
148
©2005SAPAG.Allrightsreserved. 2005/Q2
第 157 页 / 共 403 页
AC410 Lesson: Direct Activity Allocation
Solution 10: Direct Activity Allocation
Task 1:
Theconsultantsenterthenumberofconsultinghoursthattheyhaveworkedfor
different projects.
1. The internal orders that already exist in the system act as cost collectors
(consulting company A and consulting company B). The consultants
normallyentertheirownactivity,andthustriggerdirectactivityallocation.
For test purposes, enter the consulting activity for the consultants, using
today's date in version 0, with screen variant Order. Now post the
following data in the list entry:
Continued on next page
149
2005/Q2 © 2005 SAP AG. All rights reserved.
第 158 页 / 共 403 页
Unit3: Event-BasedPostings AC410
Sendercostcenter Activity Receiver Totalquantity
Type Order
301## (FI/CO J## Consulting 800
Consulting) companyA
301## (FI/CO S## Consulting 1000
Consulting) companyA
302##(LOConsulting) J## Consulting 600
companyB
302##(LOConsulting) S## Consulting 800
companyB
a) CCA:ActualPostings→ActivityAllocation→Enter
b) Select the screen variant Order
FieldNameorDataClass Values
Document date Current
Version 0
Posting date Current
Screen variant Order
Sender cost Activity Type Receiver order Activity
center provided
301## J## Consulting 800
company A
301## S## Consulting 1000
company A
302## J## Consulting 600
company B
302## S## Consulting 800
company B
Save your data.
Continued on next page
150
©2005SAPAG.Allrightsreserved. 2005/Q2
| Sendercostcenter | Activity Type | Receiver Order | Totalquantity |
|---|---|---|---|
| 301## (FI/CO Consulting) | J## | Consulting companyA | 800 |
| 301## (FI/CO Consulting) | S## | Consulting companyA | 1000 |
| 302##(LOConsulting) | J## | Consulting companyB | 600 |
| 302##(LOConsulting) | S## | Consulting companyB | 800 |
| FieldNameorDataClass | Values |
|---|---|
| Document date | Current |
| Version | 0 |
| Posting date | Current |
| Screen variant | Order |
| Sender cost center | Activity Type | Receiver order | Activity provided |
|---|---|---|---|
| 301## | J## | Consulting company A | 800 |
| 301## | S## | Consulting company A | 1000 |
| 302## | J## | Consulting company B | 600 |
| 302## | S## | Consulting company B | 800 |
第 159 页 / 共 403 页
AC410 Lesson: Direct Activity Allocation
2. Display all the screen variants for direct activity allocation again in the
match-code. Why is the sender category never mentioned in the screen
variant name, but the receiver object is?
Answer: Positionyourcursoronthescreenvariantfield.
OpenthelistofpossibleentriesusingtheMatchCodeicon(F4help).
Youcannotselectthesendercategoryonthescreenvariantbecauseactivities
can only be allocated by cost centers.
Task 2:
Check the postings (for direct activity allocation) in reports in Cost Center
Accounting.
1. Call thecost centers: actual/plan/variance report forthecurrent period
andplanversion0. Executethereportreportincostcenter301##(FI/CO
Consulting).
a) CCA:InformationSystem→Reports forcost center accounting→
Plan/ActualComparisons→Costcenters: Actual/Plan/Variance
b)
FieldNameorDataClass Values
Controlling area 1000
Fiscal Year Current
From period Current
To period Current
Plan version 0
Cost Center 301##
Program → Execute
Goto → Position → Pages → 3
2. Pagedownto displaytheallocated quantities.
Answer: Pagedowntodisplaytheallocatedquantities.
Continued on next page
151
2005/Q2 © 2005 SAP AG. All rights reserved.
| FieldNameorDataClass | Values |
|---|---|
| Controlling area | 1000 |
| Fiscal Year | Current |
| From period | Current |
| To period | Current |
| Plan version | 0 |
| Cost Center | 301## |
第 160 页 / 共 403 页
Unit3: Event-BasedPostings AC410
3. Display the actual line items for cost centers for the report row in the
secondary cost element 6262## (senior consulting ##), or6261## (junior
consulting##). SwitchtotheSecondaryCosts: Activityallocationlayout.
Cost allocation line item display variant.
Answer: Positionyourcursoronreportrowcostelement6262##.
Double-click the report row.
Choose the Actual Line Items report.
Settings → Layout → Choose
DisplayvariantSecondarycosts: Activityallocation
4. Callthecostcenters: ActivityPricesreportforthecostcentergroupB30##
inversion0forallperiodsinthecurrentfiscalyear,toobtainanoverview
of all the prices.
a) CCA:InformationSystem→Reportsforcostcenteraccounting→
Prices→ Cost centers: Activity Prices
b)
FieldNameorDataClass Values
Cost Center Group B30##
Activity type(s) J##
Multipleselectionicon S##
Copy icon.
Version 0
Fiscal Year Current
Period from Current
Price unit 1
Program → Execute
152
©2005SAPAG.Allrightsreserved. 2005/Q2
| FieldNameorDataClass | Values |
|---|---|
| Cost Center Group | B30## |
| Activity type(s) | J## |
| Multipleselectionicon | S## |
| Version | 0 |
|---|---|
| Fiscal Year | Current |
| Period from | Current |
| Price unit | 1 |
第 161 页 / 共 403 页
AC410 Lesson: Direct Activity Allocation
Lesson Summary
You should now be able to:
• Executeadirectaccountingallocationandcorrectanaccountingallocation.
153
2005/Q2 © 2005 SAP AG. All rights reserved.