第 214 页 / 共 441 页
Unit5: AvailabilityCheck SCM600
Lesson Summary
You should now be able to:
• Describethebasicprinciplesandfunctionoftheavailabilitycheck
206
©2008SAPAG.Allrightsreserved. 2008
第 215 页 / 共 441 页
SCM600 Lesson: Sample Scenarios
Lesson: Sample Scenarios
Lesson Overview
Thislessonprovidesanumberofsamplescenariostoillustratehowtheavailability
checkworks. Youwillalsobeintroducedtobackorderprocessing.
Lesson Objectives
After completingthislesson, youwillbeable to:
• Usetheavailabilitycheckaspartoforderprocessing
Business Example
• Youwanttocreateordersformaterials,forwhichthereisinsufficientstock.
• Todothis,youneedtochecktheavailablestockandmayrequireinformation
on the earliest possible delivery dates.
• Insomecases,thecustomeralsoallowspartialdeliveriesifthefullamount
cannot be delivered on the requested date.
Sample Scenarios
Figure81: 1. Case: ConformationonRequiredDeliveryDate
Usingdeliveryscheduling,thesystemcheckswhetherthegoodswillbeavailable
for the material availability date.
207
2008 © 2008 SAP AG. All rights reserved.
第 216 页 / 共 441 页
Unit5: AvailabilityCheck SCM600
The availability check includes:
• Current stock
• Plannedinwardmovements(suchaspurchaseorders,purchaserequisitions,
planned orders)
• Forecastoutwardmovements(suchasexistingsalesorders,deliveries).
Incase1,thesituationregardingoutwardmovementsisasfollows:
The existing inward movements are:
• Stock: 100 pieces
• Existingpurchaseorderswithquantitiesof50and60pieces
Thefollowingfutureoutwardmovementsalsoalreadyexist:
• Existingsalesorderswithquantitiesof100,40and50units.
Inthisoutboundsituation,younowenteranothersalesorderfor10units.
Thesystemcarriesoutdeliveryscheduling(backwardscheduling)basedonthe
customer’srequesteddeliverydateanddeterminesthematerialavailabilitydate. It
then runs an availability check for this date.
Figure82: ResultforCase1: ConfirmationRequiredDeliveryDate
The availability check shows that the system can confirm the 10 units for the
requested delivery date.
208
©2008SAPAG.Allrightsreserved. 2008
第 217 页 / 共 441 页
SCM600 Lesson: Sample Scenarios
Figure 83: 2. Case: Confirmation fora LaterDate
TheoriginalsituationinScenario2isthesameasthefirst:
The existing inward movements are:
• Stock: 100 pieces
• Existingpurchaseorderswithquantitiesof50and60pieces
Thefollowingfutureoutwardmovementsalsoalreadyexist:
• Existingsalesorderswithquantitiesof100,40and50pieces.
Inthiscase,however,thecustomerrequiresa“completedelivery”.
Inthisoutboundsituation,younowenteranothersalesorderfor20units.
Thesystemcarriesoutdeliveryscheduling(backwardscheduling)basedonthe
customer’srequesteddeliverydateanddeterminesthematerialavailabilitydate. It
then runs an availability check for this date.
209
2008 © 2008 SAP AG. All rights reserved.
第 218 页 / 共 441 页
Unit5: AvailabilityCheck SCM600
Figure 84: ResultforCase 2: Confirmation foraLaterDate
In case of stock shortage, the system uses the availability check and delivery
scheduling to determine the next possible date on which the goods can be
confirmed for the customer.
Duetothecompletedeliveryagreement,thequantitiescannotbesplitup.
You haveto confirm the20unitsfor alater date.
Based on the materials availability date, the system uses delivery scheduling
(forwardscheduling)tocalculatetheconfirmationdateforthe20units.
Figure 85: 3. Case: Partial deliveries
210
©2008SAPAG.Allrightsreserved. 2008
第 219 页 / 共 441 页
SCM600 Lesson: Sample Scenarios
If the customer and type of sales document allow it, the required sales order
quantitycanalsobesplitintoseveralpartialdeliveries.
The situationin case3is the sameasfor 1 and2:
The existing inward movements are:
• Stock: 100 pieces
• Existingpurchaseorderswithquantitiesof50and60pieces
Thefollowingfutureoutwardmovementsalsoalreadyexist:
• Existingsalesorderswithquantitiesof100,40and50pieces.
Incase3,however,thecustomerneedsthegoodsassoonaspossibleandallows
youtosplitthedeliveryquantitiesupinpartialdeliveries,ifnecessary.
Inthisoutboundsituation,younowenteranothersalesorderfor20units.
Thesystemcarriesoutdeliveryscheduling(backwardscheduling)basedonthe
customer’srequesteddeliverydateanddeterminesthematerialavailabilitydate. It
then runs an availability check for this date.
Figure 86: Result for Case 3: Partial deliveries
When there is not enough stock, the system uses the availability situation and
deliveryschedulingtodeterminethenextpossibledateforwhichthegoodscan
be confirmed to the customer.
The “partial deliveries permitted” agreement means that the quantity can be
split up.
Youcanconfirmthe20unitsfortwolaterdates,eachwith10units.
211
2008 © 2008 SAP AG. All rights reserved.
第 220 页 / 共 441 页
Unit5: AvailabilityCheck SCM600
Usingthematerialavailabilitydate,thesystemusesdeliveryscheduling(forward
scheduling)tocalculatetwopartialdeliveries,eachwith10units.
Figure 87: 4. Case: Check with Replenishment LeadTime
Youcantakeintoaccountallinwardandoutwardmovements. Itisrecommended,
however, that you only implement an availability check at the end of the
replenishment lead time.
Thereplenishmentleadtimecanbespecifiedforeachmaterial.
• Tradinggoods: planneddeliverytime+goodsreceiptprocessingtime,
• Finished goods: in-house production time.
The system assumes that the material will be available at the end of the
replenishment lead time by the latest.
Theavailabilitycheckisonlyrununtiltheendofthereplenishmentleadtime.
Ifyoucheckavailabilityincase4withoutincludingreplenishmentleadtime,the
resultisthesameasforcase2. Thecustomerrequiresacompletedelivery. You
cannot make 20 units available until the same date on which the last purchase
order for 60 unitsarrives(inward movement).
However,ifthesystemchecksavailabilityusingthereplenishmentleadtime,you
can confirm 20 units for the requested date.
212
©2008SAPAG.Allrightsreserved. 2008
第 221 页 / 共 441 页
SCM600 Lesson: Sample Scenarios
Backorder Processing
Figure 88: Backorder Processing
There are two types of backorder processing:
Manual with backorder processing
• Youcanusebackorderprocessingtolistsalesdocumentsformaterialsandto
processthemmanuallywithreferencetotheconfirmation. Thismeansthat
ATPquantitiescanbereassignedandanyshortfallcanbecleared.
Via rescheduling
• Youcanusethedeliverypriority(proposedfromthecustomermasterrecord
forthesalesorder)asasortingcriteriainautomaticrescheduling.
213
2008 © 2008 SAP AG. All rights reserved.
第 222 页 / 共 441 页
Unit5: AvailabilityCheck SCM600
214
©2008SAPAG.Allrightsreserved. 2008
第 223 页 / 共 441 页
SCM600 Lesson: Sample Scenarios
Exercise 8: Availability Check
Exercise Objectives
After completingthisexercise, youwillbeableto:
• Processorderswithashortageofavailablestock
• Check available stock
Business Example
Youbeganmarketinganewproducttwomonthsago. Demandforthisproducthas
beengreaterthanoriginallyanticipated,resultinginstockshortages.
Task 1:
Istheimplementationofanavailabilitycheckdependentonthematerial?
1. You want to determine whether an availability check takes place for the
materialwiththenumberT-AS5##duringorderentryinplant1000.
Hint: Displaythematerial master. IntheAvailabilitycheckfield
on the Sales: general/plant tab page, you can see whether an
availabilitycheckshouldbecarriedoutforthismaterialduringorder
entry,andifso,whattypeofavailabilitycheck.
Task 2:
You want to determine for which delivering plant the availability check takes
place during order entry.
1. Check which delivering plant is proposed during order entry for sales
organization1000,distributionchannel12andmaterialmasterT-AS5##.
___________________________________________________________
Hint: Displaythematerialmaster. IntheDeliveringplantfieldon
theSales: salesorg. 1tabpage,youcanseewhichdeliveringplant
isproposedfromthematerialmasterduringorderentry.
2. Check which delivering plant is proposed during order entry for sales
organization1000,distributionchannel12,division00andcustomermaster
T-S50B##.
Continued on next page
215
2008 © 2008 SAP AG. All rights reserved.
第 224 页 / 共 441 页
Unit5: AvailabilityCheck SCM600
___________________________________________________________
Hint: Displaythecustomermaster. IntheDeliveringplantfieldon
theShippingtabpage, enterthedeliveringplant, proposedduring
order entry from the customer master.
3. Inwhatsequenceisthemasterdataaccessedduringorderprocessingforthe
plant proposal?
___________________________________________________________
___________________________________________________________
___________________________________________________________
4. Cantheavailabilitycheckbecarriedoutinanotherplantastheoneproposed?
___________________________________________________________
Task 3:
You receive a purchase order.
1. Createastandardorderbasedontheexistingpurchaseorder.
Purchase order:
Customer: T-S50B##
PO number: 7-311
Requesteddeliverydate: in 5 days
Material: T-AS5##
Quantity: 10
2. Asthereisnotenoughmaterialavailablefortherequesteddeliverydate,the
systemremainsontheavailabilitycontrolscreenduringorderentry.
Hint: If youhavealreadylefttheavailabilitycontrol screen, you
cancallitupagainbyselectingCheckitemavailability.
For which plant is availability checked?
___________________________________________________________
3. Howmanypiecescanbeconfirmedfortherequesteddeliverydate?
___________________________________________________________
Continued on next page
216
©2008SAPAG.Allrightsreserved. 2008
第 225 页 / 共 441 页
SCM600 Lesson: Sample Scenarios
4. Howlongisituntilthecompletequantitycanbeconfirmed?
___________________________________________________________
5. Whycanthecompletequantitybeconfirmedonthisdate?
___________________________________________________________
6. Youdecidetoconfirmthatacompletedeliverywillbemadetothecustomer
at a later date.
7. Displaytheschedulelinesforitem10. Whichlineswithschedulelinesare
displayed?
___________________________________________________________
8. Savetheorderand writedown theordernumber.
___________________________________________________________
Task 4:
You receive another purchase order.
1. Createanotherstandardorderbasedonthepurchaseorder.
Purchaseorder:
Customer: T-S50B##
PO number: 7-411
Requesteddeliverydate: in 5 days
Material: T-AS5##
Quantity: 15
2. Asthereisnotenoughmaterialavailableagainfortherequesteddelivery
date,thesystemremainsontheavailabilitycontrolscreenduringorderentry.
Hint: If youhavealreadylefttheavailabilitycontrol screen, you
cancallitupagainbyselectingCheckitemavailability.
Youknowthatthematerialcanalsobetakenfromplant1400inStuttgart.
You therefore want to see if the material could be made available earlier
there. Check the availability for plant 1400.
Hint: Tocheckavailabilityforanotherplant,chooseOtherplants
on the availability control screen.
Continued on next page
217
2008 © 2008 SAP AG. All rights reserved.
第 226 页 / 共 441 页
Unit5: AvailabilityCheck SCM600
3. How many pieces can be confirmed from plant 1400 for the requested
delivery date ?
___________________________________________________________
4. Why can the full amount be confirmed from plant 1400 on the requested
delivery date?
___________________________________________________________
5. Youdecidetodeliverthematerialstothecustomerfromplant1400andmake
thefulldeliveryfromplant1400. Savetheorderandwritedownthenumber.
___________________________________________________________
Task 5:
Youwanttodisplaythescopeofthecheckfromthepreviousorder.
1. Youwanttoknowifpurchaseordersenteredinthesystemweretakeninto
account during the availability check for the previous order. Display the
previousorderandchecktheelementsforinward/outwardmovementsthat
havebeentakenintoconsiderationduringtheavailabilitycheck.
Hint: Youcandisplaythescopeofthecheckinthesalesorderfrom
either the availability control screen or the availability overview
screen. Choose Scope of check.
2. Youalsowanttodeterminewhetherthereplenishmentleadtimehasbeen
takenintoaccount duringtheavailabilitycheck.
Task 6:
Youreceiveanotherpurchaseorder foranothermaterial.
1. You want to gain an overview, first of all, of the actual stock and
requirementssituationfortheothermaterial. Displaythecurrentstockand
requirementslistformaterialT-AS4##. Writedownhowmanypiecesarein
stock in plant 1000.
___________________________________________________________
Hint: Inventorymanagementiscarriedoutinmaterialsmanagement.
Choose Logistics → Materials Management → Inventory
Management→Environment→Stock→Stock/RequirementsList.
2. Createastandardorderbasedonthepurchaseorder.
Continued on next page
218
©2008SAPAG.Allrightsreserved. 2008
第 227 页 / 共 441 页
SCM600 Lesson: Sample Scenarios
Purchaseorder:
Customer: T-S50A##
PO number: 7-621
Requesteddeliverydate: in 10 days
Material: T-AS4##
Quantity: 25
Savetheorderand writedown theordernumber.
___________________________________________________________
3. Youwanttogainanoverviewoftheactualstockandrequirementssituation
forthethismaterialinplant1000. Displaythecurrentstockandrequirements
list for material T-AS4##. Record how many units were required in the
sales order.
___________________________________________________________
4. Onwhatdatewastherequirementtransferred? Whichdateinthesalesorder
corresponds to this date?
___________________________________________________________
___________________________________________________________
Task 7:
When are backorders Created?
1. Whenisabackorder createdforanorder item?
___________________________________________________________
2. Whatarethetwodifferent typesof backorders?
3. Which field from the customer master can be used as a sorting criterion
for rescheduling?
___________________________________________________________
Task 8:
Questions on the availability check
1. Whycantheresultofanavailabilitycheckinthesalesorderdependentona
partialdeliveryagreementdifferfromanormalavailabilitycheck?
___________________________________________________________
Continued on next page
219
2008 © 2008 SAP AG. All rights reserved.
第 228 页 / 共 441 页
Unit5: AvailabilityCheck SCM600
2. Why is the completion of delivery scheduling a prerequisite for the
availability check in the sales order.
___________________________________________________________
3. Whyisdeliveryschedulingcarriedoutaftertheavailabilitycheck,iftheitem
cannotbeconfirmedfortherequireddeliverydate.
___________________________________________________________
220
©2008SAPAG.Allrightsreserved. 2008
第 229 页 / 共 441 页
SCM600 Lesson: Sample Scenarios
Solution 8: Availability Check
Task 1:
Istheimplementationofanavailabilitycheckdependentonthematerial?
1. You want to determine whether an availability check takes place for the
materialwiththenumberT-AS5##duringorderentryinplant1000.
Hint: Displaythematerial master. IntheAvailabilitycheckfield
on the Sales: general/plant tab page, you can see whether an
availabilitycheckshouldbecarriedoutforthismaterialduringorder
entry,andifso,whattypeofavailabilitycheck.
a) Logistics→SalesandDistribution→MasterData →Products→
Material →Trading Goods →Display
Choose Sales: General/Plant Data.
Plant 1000
Anavailabilitychecktakesplaceforthismaterial(checkinggroup01
daily requirement).
Task 2:
You want to determine for which delivering plant the availability check takes
place during order entry.
1. Check which delivering plant is proposed during order entry for sales
organization1000,distributionchannel12andmaterialmasterT-AS5##.
___________________________________________________________
Hint: Displaythematerialmaster. IntheDeliveringplantfieldon
theSales: salesorg. 1tabpage,youcanseewhichdeliveringplant
isproposedfromthematerialmasterduringorderentry.
a) Logistics→SalesandDistribution→MasterData →Products→
Material →Trading Goods →Display
Choose Sales: sales org. 1.
Sales organization 1000
Distribution channel 12
Delivering plant1400is proposed fromthematerial master for this
material.
Continued on next page
221
2008 © 2008 SAP AG. All rights reserved.
第 230 页 / 共 441 页
Unit5: AvailabilityCheck SCM600
2. Check which delivering plant is proposed during order entry for sales
organization1000,distributionchannel12,division00andcustomermaster
T-S50B##.
___________________________________________________________
Hint: Displaythecustomermaster. IntheDeliveringplantfieldon
theShippingtabpage, enterthedeliveringplant, proposedduring
order entry from the customer master.
a) Logistics → Sales and Distribution → Master Data → Business
Partner→Customer→Display→SalesandDistribution
SelecttheSalesAreaData: Shippingtabpage.
Deliveringplant1000isproposedfromthecustomer master forthis
customer.
3. Inwhatsequenceisthemasterdataaccessedduringorderprocessingforthe
plant proposal?
___________________________________________________________
___________________________________________________________
___________________________________________________________
a) Duringorderentry,theplantproposalaccessesthemasterdatainthe
following sequence:
1. Customer-material information
2. Customer master
3. Material master
Ifdifferent deliveringplantshavebeen specifiedin themaster data,
the proposal which correspondsto thissequencewill be transferred
for the sales order items.
4. Cantheavailabilitycheckbecarriedoutinanotherplantastheoneproposed?
___________________________________________________________
a) You have the option of overwriting the proposal manually in the
customer sales order.
Aspartoftheavailabilitycheck,youalsohavetheoptionofchecking
in other plants.
Continued on next page
222
©2008SAPAG.Allrightsreserved. 2008
第 231 页 / 共 441 页
SCM600 Lesson: Sample Scenarios
Task 3:
You receive a purchase order.
1. Createastandardorderbasedontheexistingpurchaseorder.
Purchaseorder:
Customer: T-S50B##
PO number: 7-311
Requesteddeliverydate: in 5 days
Material: T-AS5##
Quantity: 10
a) Logistics→SalesandDistribution→Sales→Order→Create
2. Asthereisnotenoughmaterialavailablefortherequesteddeliverydate,the
systemremainsontheavailabilitycontrolscreenduringorderentry.
Hint: If youhavealreadylefttheavailabilitycontrol screen, you
cancallitupagainbyselectingCheckitemavailability.
For which plant is availability checked?
___________________________________________________________
a) Plant 1000
3. Howmanypiecescanbeconfirmedfortherequesteddeliverydate?
___________________________________________________________
a) Nothingcanbeconfirmedfortherequireddeliverydate.
4. Howlongisituntilthecompletequantitycanbeconfirmed?
___________________________________________________________
a) Only at the latest data proposed under Complete delivery/delivery
proposal.
5. Whycanthecompletequantitybeconfirmedonthisdate?
___________________________________________________________
a) Thisisthedateonwhichreplenishmenttimeends.
Continued on next page
223
2008 © 2008 SAP AG. All rights reserved.
第 232 页 / 共 441 页
Unit5: AvailabilityCheck SCM600
6. Youdecidetoconfirmthatacompletedeliverywillbemadetothecustomer
at a later date.
a) Complete delivery: choose Copy.
7. Displaytheschedulelinesforitem10. Whichlineswithschedulelinesare
displayed?
___________________________________________________________
a) Choose Schedules lines for item.
Therearetwoschedulelines. Thefirsthastherequireddeliverydate,
theorderquantityandtheconfirmedquantity0. Thesecondschedule
linehastheconfirmeddeliverylineandtheconfirmedquantity.
8. Savetheorderandwritedowntheordernumber.
___________________________________________________________
a) → Save
Thedocumentnumberisassignedinternallybythesystem.
Task 4:
You receive another purchase order.
1. Createanotherstandardorderbasedonthepurchaseorder.
Purchase order:
Customer: T-S50B##
PO number: 7-411
Requesteddeliverydate: in 5 days
Material: T-AS5##
Quantity: 15
a) Logistics→SalesandDistribution→Sales→Order→Create.
2. Asthereisnotenoughmaterialavailableagainfortherequested delivery
date,thesystemremainsontheavailabilitycontrolscreenduringorderentry.
Hint: If youhavealreadylefttheavailabilitycontrol screen, you
cancallitupagainbyselectingCheckitemavailability.
Continued on next page
224
©2008SAPAG.Allrightsreserved. 2008
第 233 页 / 共 441 页
SCM600 Lesson: Sample Scenarios
Youknowthatthematerialcanalsobetakenfromplant1400inStuttgart.
You therefore want to see if the material could be made available earlier
there. Check the availability for plant 1400.
Hint: Tocheckavailabilityforanotherplant,chooseOtherplants
on the availability control screen.
a) Availability control screen
ChooseOtherplants→Plant1400→Checkplants.
The complete quantity can be confirmed on the required date from
plant 1400.
3. How many pieces can be confirmed from plant 1400 for the requested
delivery date ?
___________________________________________________________
a) 15 pieces
4. Why can the full amount be confirmedfrom plant 1400on the requested
delivery date?
___________________________________________________________
a) Thereissufficientstockinplant1400andthereplenishmentleadtime
is shorter.
5. Youdecidetodeliverthematerialstothecustomerfromplant1400andmake
thefulldeliveryfromplant1400. Savetheorderandwritedownthenumber.
___________________________________________________________
a) Choose Copy plant.
Choose Save.
Thedocumentnumberisassignedinternallybythesystem.
Continued on next page
225
2008 © 2008 SAP AG. All rights reserved.
第 234 页 / 共 441 页
Unit5: AvailabilityCheck SCM600
Task 5:
Youwanttodisplaythescopeofthecheckfromthepreviousorder.
1. Youwanttoknowifpurchaseordersenteredinthesystemweretakeninto
account during the availability check for the previous order. Display the
previousorderandchecktheelementsforinward/outwardmovementsthat
havebeentakenintoconsiderationduringtheavailabilitycheck.
Hint: Youcandisplaythescopeofthecheckinthesalesorderfrom
either the availability control screen or the availability overview
screen. Choose Scope of check.
a) Logistics→SalesandDistribution→Sales→Order→Display.
Choose Display availability
Choose Scope of check
Inthiscase,purchaseordersarealsocheckedalongsideotherinward
and outward movements.
2. Youalsowanttodeterminewhetherthereplenishmentleadtimehasbeen
takenintoaccount duringtheavailabilitycheck.
a) WhenyoudisplaytheScopeof check, thefield Check withoutRLT
is not selected. Thismeans that in this case the replenishment lead
time has been taken into account.
Task 6:
Youreceiveanotherpurchaseorder foranothermaterial.
1. You want to gain an overview, first of all, of the actual stock and
requirementssituationfortheothermaterial. Displaythecurrentstockand
requirementslistformaterialT-AS4##. Writedownhowmanypiecesarein
stock in plant 1000.
___________________________________________________________
Hint: Inventorymanagementiscarriedoutinmaterialsmanagement.
Choose Logistics → Materials Management → Inventory
Management→Environment→Stock→Stock/RequirementsList.
a) Logistics → Materials Management → Inventory Management →
Environment→Stock→Stock/RequirementsList
YoucanseetheplantstockinthelinewiththeMRPelementW-BEST,
in the Available qty column.
Continued on next page
226
©2008SAPAG.Allrightsreserved. 2008
第 235 页 / 共 441 页
SCM600 Lesson: Sample Scenarios
2. Createastandardorderbasedonthepurchaseorder.
Purchaseorder:
Customer: T-S50A##
PO number: 7-621
Requesteddeliverydate: in 10 days
Material: T-AS4##
Quantity: 25
Savetheorderand writedown theordernumber.
___________________________________________________________
a) Logistics→SalesandDistribution→Sales→Order→Create→
Save
Thedocumentnumberisassignedinternallybythesystem.
3. Youwanttogainanoverviewoftheactualstockandrequirementssituation
forthethismaterialinplant1000. Displaythecurrentstockandrequirements
list for material T-AS4##. Record how many units were required in the
sales order.
___________________________________________________________
a) Logistics → Materials Management → Inventory Management →
Environment→Stock→Stock/RequirementsList
Youcanseetherequirementfromthesalesorderinthelinewiththe
MRPelementK-AUFT,intheRec./reqdquantitycolumn.
25 pieces
4. Onwhatdatewastherequirementtransferred? Whichdateinthesalesorder
corresponds to this date?
___________________________________________________________
___________________________________________________________
a) The requirements date (date in the first column) corresponds to the
material availabilitydatefromthesalesorder.
Task 7:
When are backorders Created?
1. Whenisabackorder createdforanorder item?
Continued on next page
227
2008 © 2008 SAP AG. All rights reserved.
第 236 页 / 共 441 页
Unit5: AvailabilityCheck SCM600
___________________________________________________________
a) Abackordercanbeexecutedifanorderitemisbackdated. Anorder
itemisbackdatediftheorderquantityisnotcompleteortherequired
deliverydatehasnotbeenconfirmedintime.
2. Whatarethetwodifferent typesof backorders?
a) Abackordercanbeimplementedusingmanualbackorderprocessingor
rescheduling.
3. Which field from the customer master can be used as a sorting criterion
for rescheduling?
___________________________________________________________
a) The deliverypriorityis taken fromthecustomer master in thesales
orderandcanbeusedasasortcriterionforordersduringrescheduling.
Task 8:
Questions on the availability check
1. Whycantheresultofanavailabilitycheckinthesalesorderdependentona
partialdeliveryagreementdifferfromanormalavailabilitycheck?
___________________________________________________________
a) Ifonlypartoftherequiredquantityisavailableontherequireddelivery
date and the customer agrees to a partial delivery, then a delivery
split can be carried out and a partial quantity can be confirmed for
the required delivery date.
Ifthecustomerdoesnotallowpartialdelivery, thecompleteamount
can only be confirmed for a later date.
2. Why is the completion of delivery scheduling a prerequisite for the
availability check in the sales order.
___________________________________________________________
a) The availability check takes place on thematerial availability date.
Thematerialsarerequired on this date, so thatthere isenoughtime
remainingforpacking,loadingandsoonbeforetherequireddelivery
date. This means the material availability date must be determined
in the sales order before the availability check is carried out. It is
determined using delivery scheduling.
3. Whyisdeliveryschedulingcarriedoutaftertheavailabilitycheck,iftheitem
cannotbeconfirmedfortherequireddeliverydate.
Continued on next page
228
©2008SAPAG.Allrightsreserved. 2008
第 237 页 / 共 441 页
SCM600 Lesson: Sample Scenarios
___________________________________________________________
a) Iftheitemcouldnotbeconfirmedfortherequireddeliverydate,then
thesystemcarriesout deliveryschedulingfromtheearliestpossible
dateavailable(forwardscheduling),inordertodeterminethedelivery
date (confirmation date).
229
2008 © 2008 SAP AG. All rights reserved.
第 238 页 / 共 441 页
Unit5: AvailabilityCheck SCM600
Lesson Summary
You should now be able to:
• Usetheavailabilitycheckaspartoforderprocessing
230
©2008SAPAG.Allrightsreserved. 2008
第 239 页 / 共 441 页
SCM600 Lesson: Transportation Processing
Lesson: Transportation Processing
Lesson Overview
Thislessonprovidesabriefoverviewoftransportationprocessingoptions.
Lesson Objectives
After completingthislesson, youwillbeable to:
• Explain thefunctionof theshipmentdocument
• Describehowshipmentcostsarebilledtothecustomer
• Explainhowfinancialinformationistransferredfromthebillingdocument
into the accounting document
Business Example
• Youwanttotransportmaterialsfrommorethanonedeliveryononetruck.
• Freightcostsareincurred,whichyoubilltothecustomer.
• Youwanttocheckwhichaccountshavebeenpostedintheaccountdocument
belonging to the billing document.
Transportation Processing
Figure 89: Document Flow with Outgoing Shipment
The shipment function is optional.
231
2008 © 2008 SAP AG. All rights reserved.
第 240 页 / 共 441 页
Unit5: AvailabilityCheck SCM600
Youcanuseittocombinedeliverieswiththesametransportationrequirements,
suchasforwardingagent,destination,routeormeansoftransport.
Normally,youcreateashipmentbeforeyoupostgoodsissue.
Thesettlementofshipmentcostsfromtheshipmentisalsooptional.
Figure 90: Creating Shipments
Usingthe“Createshipment”function,thesystemdeterminesthedeliveriesdue
for transportationandcreatestheshipmentsrequired.
The individual deliveries can be assigned to the shipments manually. The
sequenceof the deliverieswithin ashipment isdetermined automatically from
the sequence in which they are listed.
Figure 91: Loading and Packing Shipments
232
©2008SAPAG.Allrightsreserved. 2008
第 241 页 / 共 441 页
SCM600 Lesson: Transportation Processing
Atthetimeofshipment,itemswhichwerenotalreadypackedinthedelivery,can
bepackedinshippingunitsusingshippingmaterials. Thefunctionalityusedhere
isbasically the same asfor loading in thedelivery. However, items cannot be
generatedorenteredmanuallyforinventorymanagement/billing.
Packeditemsareassignedtotherequiredmeansoftransport(trucks,forexample).
Shippingunitsfromthedeliveryarecopiedandcannolongerbechanged.
Unlike packing in the delivery, packing in the shipment can be carried out for
several deliveries.
Figure 92: Billing the Shipment Costs to the Customer
Youcaninvoicethecustomer forshipmentcosts, whicharebased on effective
shipmentcosts,thathavebeencalculatedinthetransportationandshipmentcost
processingareasforsettlementwiththeforwardingagent. Thefreightcoststhen
appearasanadditionalentryinthecustomerbillingdocument.
233
2008 © 2008 SAP AG. All rights reserved.
第 242 页 / 共 441 页
Unit5: AvailabilityCheck SCM600
Figure 93: Connection to Financial Accounting
Thesystemtransfersbillingdocumentdataininvoices,creditanddebitmemosto
financialaccountingandpoststhistothedeterminedaccounts.
Youcansetaccountdeterminationtobedependent onvariousdifferentcriteria
in Customizing, so that the corresponding accounts can be determined. The
followingcriteriaaredefinedinthestandardsystem:
• Chart of accounts
• Sales organization
• Account assignment group of the payer
(customerscanbecategorized,forexample,accordingtowhethertheyare
domestic or foreign customers)
• Account assignment group of the material
(materialscanbecategorized, forexample, accordingtowhether theyare
services or retail goods)
• Accountkey(itispossibletodividethisupintothedifferentprice,surplus
and discount elements)
Settingaccountdeterminationrequiresagreementfromfinancialaccountingand
cost accounting, for thereasonsmentioned above.
234
©2008SAPAG.Allrightsreserved. 2008
第 243 页 / 共 441 页
SCM600 Lesson: Transportation Processing
Exercise 9: Transportation Processing
Exercise Objectives
After completingthisexercise, youwillbeableto:
• Edit partial deliveries
• Describe transportation processing
• Carry outaccountdeterminationforabilling documentintheaccounting
document.
Business Example
Althoughyouareabletodeliverthecompletequantityontherequesteddelivery
date,thecustomeronlywantstoreceivepartofthedeliveryatthispoint.
As there are other customer outbound deliveries to make on the day that the
deliveryisdue,whichareonroutetothisparticularcustomer,youcanputseveral
outbound deliveries together in one shipment.
After theprocesshasbeencompletedandtheinvoicesarecreated, youwantto
ensurethattherightaccountshavebeenpostedinaccounting.
Task 1:
A sales order should be partially delivered.
1. Displaythestandardorderfromthelastexerciseonthescreen. Determine
whether theordercould be partiallydelivered.
Whichagreementreferringtoacompletedeliverycanbeseenintheorder
header?
Hint: The Complete Delivery field in the order header is on the
SalesoverviewscreenandontheShippingtabpage.
__________________________________________________________
Continued on next page
235
2008 © 2008 SAP AG. All rights reserved.
第 244 页 / 共 441 页
Unit5: AvailabilityCheck SCM600
2. WhatmasterdataisusedforproposingtheCompleteDeliveryflagin the
order header?
3. Do you have the option of distributing individual order items (with the
corresponding item order quantity) to different deliveries, if the field
CompleteDeliveryisnotcheckedintheorderheader?
4. Do you have the option of distributing the full amount of order items to
different deliveries, if the Complete Delivery field is not checked in the
order header?
5. What agreements referring to partial deliveries can be found in item 10
of the order?
___________________________________________________________
Hint: You can find the Part.dlv./item field for the order item on
the Shipping tab page.
6. What master data is used for proposing the Partial Delivery flag in the
order item?
__________________________________________________________
Continued on next page
236
©2008SAPAG.Allrightsreserved. 2008
第 245 页 / 共 441 页
SCM600 Lesson: Transportation Processing
7. Create an outbound delivery for the previous sales order (from exercise
6-2). In this delivery, only 10 units from the total of 25 units should be
delivered initially.
Hint: Tobeabletoentertheoutbounddeliveryatanearlierdate,set
theselectiondate20daysintothefuture. UseshippingpointZ0##.
Changethequantitytobedeliveredto10pieces.
Savetheoutbounddeliveryandwritedowntheordernumber.
_______________________________________________
Task 2:
Youwanttoexaminepossiblemethodsoftransportforthedelivery.
1. Check whether the outbound delivery you have already created (from
exercise1-7) canbe processed for transport.
Whatisthetransportationplanningstatusofthedelivery?
Hint: Displaytheoutbounddeliveryonthescreen. OntheTransport
tab page, you can see whether this delivery can be processed
for transport in the Trns.plan.stat. field. Use F1 help to see an
explanation of the status.
________________________________________________________
Continued on next page
237
2008 © 2008 SAP AG. All rights reserved.
第 246 页 / 共 441 页
Unit5: AvailabilityCheck SCM600
2. You want toloadseveral itemsfromdifferent deliveries, that allhavethe
same ship-to party, into the container. Do you have the option of doing
thisin theshipment document and enteringwhich itemsare to be loaded
into which container?
3. YouhaveputtogetherseveraldeliveriesfordifferentcustomersinHamburg
into one shipment document for one lorry load. Do you have the option
of dividing the shipping costs to the customer depending on the number
of items being delivered to them?
4. Whatisthedifferencebetweenashipmentdocumentandatransferorder?
Task 3:
Youwanttopickyourdelivery,postgoodsissueandbillthetransaction. Youthen
wanttocheckwhichaccountshavebeenfoundintheaccountingdocument.
1. First enter the transfer order for picking for the previous delivery for
warehousenumber010inplant1000. Writedownthedocumentnumber.
________________________________
2. Post goods issue for the outbound delivery.
3. Enterabillingdocumentfortheoutbounddeliveryandwritethedocument
number.
________________________________
Continued on next page
238
©2008SAPAG.Allrightsreserved. 2008
第 247 页 / 共 441 页
SCM600 Lesson: Transportation Processing
4. Displaytheaccountingdocumentforthebillingdocumentandwritedown
whichaccountshavebeenpostedforwhichamounts.
Hint: You can display the accounting document for the billing
documentwiththetransactionDisplaybillingdocument:
ChooseAccountingoverviewandselecttheaccountingdocument.
_________________________________________________________
_________________________________________________________
_________________________________________________________
239
2008 © 2008 SAP AG. All rights reserved.
第 248 页 / 共 441 页
Unit5: AvailabilityCheck SCM600
Solution 9: Transportation Processing
Task 1:
A sales order should be partially delivered.
1. Displaythestandardorderfromthelastexerciseonthescreen. Determine
whether the order could bepartiallydelivered.
Whichagreementreferringtoacompletedeliverycanbeseenintheorder
header?
Hint: The Complete Delivery field in the order header is on the
SalesoverviewscreenandontheShippingtabpage.
__________________________________________________________
a) Logistics→SalesandDistribution→Sales→Order→Display
Choose the Shipping tab page.
The Complete dlv. field is not selected. This means that individual
itemscanbesplitupintoseparatedeliveries.
2. WhatmasterdataisusedforproposingtheCompleteDeliveryflagin the
order header?
Answer: TheindicatorforCompletedeliveryintheorderheaderisproposed
from the customer master.
3. Do you have the option of distributing individual order items (with the
corresponding item order quantity) to different deliveries, if the field
CompleteDeliveryisnotcheckedintheorderheader?
Answer: Yes. Itemscanbesplitupintoseparatedeliveries.
4. Do you have the option of distributing the full amount of order items to
different deliveries, if the Complete Delivery field is not checked in the
order header?
Answer: IftheCompletedeliveryfieldisnotselectedintheorderheader,
then it is still dependent on the partial delivery agreement at item level,
whether theamountordered canbedividedup.
5. What agreements referring to partial deliveries can be found in item 10
of the order?
Continued on next page
240
©2008SAPAG.Allrightsreserved. 2008
第 249 页 / 共 441 页
SCM600 Lesson: Transportation Processing
___________________________________________________________
Hint: You can find the Part.dlv./item field for the order item on
the Shipping tab page.
a) OntheShippingtabpageforitem10,thePart.dlv./itemfieldisempty
(Partial deliveriesallowed). This means that partial deliveries are
allowed.
6. What master data is used for proposing the Partial Delivery flag in the
order item?
__________________________________________________________
a) TheproposalforthePart.dlv./itemfieldintheorderitemcomesfrom
thecustomermaster. Ifacustomer-materialinfoalreadyexistsforthe
customerandthematerial,andtheproposalhereisdifferenttothatin
thecustomermaster,thenthisproposalhaspriority.
7. Create an outbound delivery for the previous sales order (from exercise
6-2). In this delivery, only 10 units from the total of 25 units should be
delivered initially.
Hint: Tobeabletoentertheoutbounddeliveryatanearlierdate,set
theselectiondate20daysintothefuture. UseshippingpointZ0##.
Changethequantitytobedeliveredto10pieces.
Savetheoutbounddeliveryandwritedowntheordernumber.
_______________________________________________
a) Logistics→SalesandDistribution→ShippingandTransportation→
OutboundDelivery→Create→SingleDocument→WithReference
to Sales Order
Changequantitytobedeliveredto10units.
→ Save
Thedocumentnumberisassignedinternallybythesystem.
Task 2:
Youwanttoexaminepossiblemethodsoftransportforthedelivery.
1. Check whether the outbound delivery you have already created (from
exercise1-7) canbe processed for transport.
Continued on next page
241
2008 © 2008 SAP AG. All rights reserved.
第 250 页 / 共 441 页
Unit5: AvailabilityCheck SCM600
Whatisthetransportationplanningstatusofthedelivery?
Hint: Displaytheoutbounddeliveryonthescreen. OntheTransport
tab page, you can see whether this delivery can be processed
for transport in the Trns.plan.stat. field. Use F1 help to see an
explanation of the status.
________________________________________________________
a) Logistics→SalesandDistribution→ShippingandTransportation→
Outbound Delivery → Display
Choose the Transport tab page.
AisenteredintheTrns.plan.stat. field. Thismeansthattheoutbound
deliveryhasnotyetbeenprocessedinashipmentdocument.
Itmayalsobethecasethatadeliveryisnotrelevantforashipment
document(depending on thedeliverytype).
2. You want toloadseveral itemsfromdifferent deliveries, that allhavethe
same ship-to party, into the container. Do you have the option of doing
thisin theshipment document and enteringwhich itemsare to be loaded
into which container?
Answer: You can specify which items are to be loaded together into a
containerintheshipmentdocument. Youcanalsoloaditemsfordifferent
deliveries together into one container.
3. YouhaveputtogetherseveraldeliveriesfordifferentcustomersinHamburg
into one shipment document for one lorry load. Do you have the option
of dividing the shipping costs to the customer depending on the number
of items being delivered to them?
Answer: Yes You can enter the shipment costs into a shipment cost
documentanddistributetheseaccordinglyamongstcustomers.
4. Whatisthedifferencebetweenashipmentdocumentandatransferorder?
Answer: Theshipment documentiscreatedand used togroup together
several deliveries for one shipment to a customer. For example, for one
lorry driver.
Thetransferrequestactsasabasisfor picking.
Itiscreatedforadelivery,tocontrolinternalmaterialmovements.
Continued on next page
242
©2008SAPAG.Allrightsreserved. 2008
第 251 页 / 共 441 页
SCM600 Lesson: Transportation Processing
Task 3:
Youwanttopickyourdelivery,postgoodsissueandbillthetransaction. Youthen
wanttocheckwhichaccountshavebeenfoundintheaccountingdocument.
1. First enter the transfer order for picking for the previous delivery for
warehousenumber010inplant1000. Writedownthedocumentnumber.
________________________________
a) Logistics→SalesandDistribution→ShippingandTransportation→
Picking→CreateTransferOrder→SingleDocument
Thedocumentnumberisassignedinternallybythesystem.
2. Post goods issue for theoutbound delivery.
a) Logistics→SalesandDistribution→ShippingandTransportation→
OutboundDelivery→Change→SingleDocument
Choose Post Goods Issue.
3. Enterabillingdocumentfortheoutbounddeliveryandwritethedocument
number.
________________________________
a) Logistics→SalesandDistribution→Billing→Billing Document
→ Create
Choose Execute → Save.
Thedocumentnumberisassignedinternallybythesystem.
4. Displaytheaccountingdocumentforthebillingdocumentandwritedown
whichaccountshavebeenpostedforwhichamounts.
Hint: You can display the accounting document for the billing
documentwiththetransactionDisplaybillingdocument:
ChooseAccountingoverviewandselecttheaccountingdocument.
_________________________________________________________
_________________________________________________________
Continued on next page
243
2008 © 2008 SAP AG. All rights reserved.
第 252 页 / 共 441 页
Unit5: AvailabilityCheck SCM600
_________________________________________________________
a) Logistics →Salesand Distribution → Billing →Billing Document
→ Display
Choose Accounting.
Select the accounting document.
Debitpostingispostedforthecustomeraccountandcreditpostingis
bookedfortheoutputtaxandsalesrevenueaccounts.
The debit postingsaremade on the payer’saccount. The offsetting
postingsaremadeontherevenueaccounts,salesdeductionaccounts
and, insomecases, theoutput tax accounts.
244
©2008SAPAG.Allrightsreserved. 2008
第 253 页 / 共 441 页
SCM600 Lesson: Transportation Processing
Lesson Summary
You should now be able to:
• Explain thefunctionof theshipmentdocument
• Describehowshipmentcostsarebilledtothecustomer
• Explainhowfinancialinformationistransferredfromthebillingdocument
into the accounting document
245
2008 © 2008 SAP AG. All rights reserved.