Former Member
May 17, 2010 4 minute read
How to configure Mixed Costing
61318,363
Mixed costing is very useful in some cases. For example, it’s the only way to release a standard cost estimate for each procurement alternative that is associated with a valuation type.
Recently I got some requests to explain in details how the mixed costing works. I hope this blog can help to explain.
The prerequisite for the mixed costing is as below:
– A quantity structure type is configured in the customizing
– This quantity structure type is associated to a costing version in the Customizing.
– The Procurement alternatives for the material have bee defined
– The mixing ratios for the procurement alternatives are defined based on the quantity structure type
– The material is costed with the above-defined costing version.
1. Define the quantity structure type
The path to configure mixed costing is as below (ECC 6.0):
The tcode for quantity structure type is OMXA.
Now I created the qty structure type “MIX”.
“Time Dependency” – This controls the time period in which the quantity structure will be used. It can be time indepenent, based on fiscal year, or based on each period.
“Percent validation” – Tick this indicator if you want to ensure that the sum of the existing mixing ratios for a material and quantity structure type totals 100%.
2. Associate the quantity structure type to a costing version
The path is right after that for the quantity structure type.
For the attached screenshot, the mixed costing will be called with the qty structure type MIX, when costing version = 1 & costing type = 19, or when costing version = 99 & costing type = 01 & valuation variant = 001. The system will not do mixed costing for the other combinations of costing version & costing type & valuation variant.
In this transaction, you can also define:
– Variant for transfer price determination
– Exchange rate type for currency translation
The configuration for the costing version can also be checked via costing variant configuration(tcode OKKN). It’s a more convenient way as the configuration is based on the combination.
In the Assignment tab, click the costing version button.
You’ll see for the costing variant PPC1 (costing type 01, valuation variant 001), costing version 99 is assigned the qty structure type “MIX”.
3. Define procurement alternatives
The tcode is CK91N. Here we need to create the procurement alt per material/plant.
I created two proc alternatives for different versions. It’s also possible to create alternatives for different valuation type/process cateogry/etc…
For process category
– Production
you can choose to create procurement alternatives for in-house production either with production versions or by using the BOM and routing.
– Purchase order
You can then enter a vendor and the relevant purchasing org in the initial screen.
In the cost estimate for a procurement alternative with reference to a vendor, strategy “L” (price from purchasing info record) is always automatically set to highest priority strategy. If you want to have a different logic, you may consider note 636967 and 319832.
You can also create an unspecified procurement alternative. To do this, do not enter a vendor or a purchasing organization. The material is then valuated with the prices in the material master and not using the purchasing info record.
– Subcontracting
In this case the system will require you to enter the information on the BOM, vendor and purchasing org.
– Stock transfer
You’ll be required to enter the source plant
4. Define Mixing Ratios for the procurement alternatives
The tcode is ck94
Here we can create the mixing ratios for the material per qty structure type.
Since our Qty Structure type “MIX” is based on fiscal year, here we only need to enter the “fiscal year” information.
If it’s based on period, we need to create the mixing ratios for each period.
Here all the proc alt created via CK91N will be displayed. And you can assign the mixing radio to them as you want.
– MR indicator
Set this indicator if you want to include a procurement alternative in mixed costing. It will ensure this procurement alt will be included in a mixed costing (even with a weighting of 0).
– Mixing Ratio
This is the most import figure in this transaction. You can enter equivalence numbers or percentages. But if “Percent validation” is ticked for the qty structure type, the sum of the existing mixing ratios must totals 100%.
5. Cost the material with the above-defined costing version.
Create a cost estimate for material YS-FRAME-01/plant IWS0 with costing variant PPC1 and costing version 99. The mixed costing is successfully carried out, as expected.
Please note, the costing lot size of mixed costing is different with the normal costing.
For more information please refer to note 402440, which provided very detailed explanation of the logic together with some examples.
FollowLikeRSS Feed
6 Comments
You must be Logged on to comment or reply to a post.
Former Member
May 31, 2010 at 9:00 pm
Hi Expert,
When i will post MB1B, system occur a error message F5800 of Inconsistent currency information as below:
Inconsistent currency information
Message no. F5800
Diagnosis
The currency information for the financial accounting component must be transferred fully for each currency type.
If, for example, the sending application sends corporate group currency data to Accounting, this currency data must be transferred for every company code line item.
An error has occurred for line item '0000000002' of the financial accounting document (company code '5000') with currency type '12' (currency key 'CNY'). This could be for one of three reasons:
Line item '0000000002' does not have any currency data for currency type '12', although at least one other line item has currency data for currency type '12'. Line item '0000000002' contains currency data for currency type '12', although at least one other line item contain no currency data for currency type '12'.
Line item '0000000002' has no currency data for currency type '12', although the currency type '12' corresponds to the local currency ( currency type '10').
System Response
Data processing within Financial Accounting can only take place with consistent currency information.
Procedure
The calling application probably contains a system error. Contact the calling application to locate the error.
PS: I have already activated transfer price with material ledger.
Could you please help to solve it? tks.
Like 0
Share
Former Member
September 12, 2015 at 8:44 am
One of the best document on Mixed Costing !
Regards,
Sharvari Joshi.
Like 0
Share
KAPIL MEHTA
February 28, 2018 at 2:42 pm
Hi
I read your article and it is very informative. I just have one query - Can you please suggest standard SAP report which gives standard cost breakup along with procurement alternative level information, if product involved Mixed costing.
I have checked S_ALR_87099930 & S_P99_41000111, but they do not show name/description/identification of Procurement alternative.
Regards
Kapil
Like 0
Share
Former Member
March 29, 2018 at 2:27 am
Hi Expert,
Can this set up be apply for one material which have been set up two difference BOM and two difference production Line?
thank you,
TZM
Like 0
Share
Tapan Rana
February 1, 2021 at 11:02 am
Yes
Like 0
Share
Maria Cirjan
November 3, 2022 at 11:54 am
Hi,
Thank you for the very good description. I have managed to setup all settings displayed above and run costing run via CK40n.
I am facing two issues:
after running ck40n the material price still appears with status KA - costed w/o errors instead of released w/o errors. (mm03 doesn't execute it goes into an infinite loading loop for the mixed costing material)
i have other materials set up with different costing version for which I am no longer able to run a second costing run in the same period.
Any suggestions would be highly appreciated
Like 0
Share
Mixed-Costing (a)Within-a-PLANT (b) Across-Plant/Comp.Code
SAP mixed costing –> to cost a material using multiple alternative methods, e.g. when you manufacture a material with different internal processes, then specify these through separate production versions. When we execute a cost estimate the system calculates the cost for each production version then calculates an average unit cost using weighting factors. When we display a cost estimate with transaction CK13N, we display the total cost and details of each procurement alternative.
Set-up :
CK91 – define how the material is procured, either internally (prod. Versions) or externally
CK94 – specify weighting factors, e.g. production volumes to be produced for the year using each of the production versions
For actuals, a Production-order is produced with a specific production version (e.g. we select P-ver 0001). The target costs for the Production-order are calculated based on the cost estimate data related to that production version. The credit for production uses the weighted average standard cost calculated. The difference between the two multiplied by the production quantity is calculated and reported as mixed price variance when executing the variance calculation transaction (KKS1 / KKS2) using the standard delivered variance categories. When the unit cost of the production version used is higher than the standard cost, unfavourable mixed price variance is calculated; when it is lower, favourable mixed price variance is calculated.
Example : Within-a-Plant, Say one Finished Goods has two production-versions which individually cost as follows
When we set-up MIXED-costing in SAP, example say for month-08, a monthly mix of 20% from Prod.Version 0001 & 80% from Prod 0002, then at that point of time system will calculate the cost of the Finished-prod. as follows
CK11N, for the Product shows the Mixed-costing value as well as drill-down to Individual Production-Version.
Mixed-Costing within a Plant
And when we Create the production-Order, say with Version-‘0001’ then the Production-Order’s TARGET Cost is costed as per Version-0001 & the variance is created for the difference.
CK91 – For Production
CK94 – Set-up Production-MIX
Mixed Costing – Thru Procurement Alternatives (Purchase-order, Subcontracting, Stock-Transfer) etc
CK91 : Procurement Alternative
In Stock-Transfer, one can set-up special-procurement plant thru which STO will come to plant for which the Procurement Alternative is being generatedOne procurement alternative is Stock transfer from Plant10 to Plant 21
Similarly we can set-up Procurement-alternative with another Plant Stock-transfer as well as Vendor’s Purchase and Subcontracting.
Again in CK94, we can select specific alternatives for each month/year and define the MIXING Ratios
When do do Costing-run CK11N or thru CK40N, (below screen-shot is of CK11N), System computes the costing as per mixing-ratio defined in CK94.
Share this:
Loading...
Posted on July 29, 2020By MonikaPatel mps4hana.comPosted in Product-Costing
RELATED
12.1 S4TWL – Reference and Simulation Costing : 2349294January 31, 2020In "12. Financials - Controlling"
COGM & COGS in Product CostingJune 27, 2020In "Product-Costing"
WN : 1809 – Controlling – Production Cost-Analysis EnhancementJanuary 29, 2020In "Production-Order Costing"
Post navigation
PreviousPrevious post:PRODUCT-COSTING USER-EXIT
NextNext post:MACRS : ASSET ACQUISITIONS(MID-QUARTER-CONVENTION) S_ALR_87012047
LEAVE A REPLY
Top of Form
Skip to content
MP's S/4HANA
SAP S/4HANA – It is a learning Journey. #LearningandSharing #SharingIsCaring
Home
1. About Me
2. Contact Me
SAP Finance LOB
3. S/4HANA Innovations
My “SAP-Blogs”
S/4HANA Finance
Digital Transformation
My “Me-Blogs”
Mixed-Costing (a)Within-a-PLANT (b) Across-Plant/Comp.Code
SAP mixed costing –> to cost a material using multiple alternative methods, e.g. when you manufacture a material with different internal processes, then specify these through separate production versions. When we execute a cost estimate the system calculates the cost for each production version then calculates an average unit cost using weighting factors. When we display a cost estimate with transaction CK13N, we display the total cost and details of each procurement alternative.
Set-up :
CK91 – define how the material is procured, either internally (prod. Versions) or externally
CK94 – specify weighting factors, e.g. production volumes to be produced for the year using each of the production versions
For actuals, a Production-order is produced with a specific production version (e.g. we select P-ver 0001). The target costs for the Production-order are calculated based on the cost estimate data related to that production version. The credit for production uses the weighted average standard cost calculated. The difference between the two multiplied by the production quantity is calculated and reported as mixed price variance when executing the variance calculation transaction (KKS1 / KKS2) using the standard delivered variance categories. When the unit cost of the production version used is higher than the standard cost, unfavourable mixed price variance is calculated; when it is lower, favourable mixed price variance is calculated.
Example : Within-a-Plant, Say one Finished Goods has two production-versions which individually cost as follows
When we set-up MIXED-costing in SAP, example say for month-08, a monthly mix of 20% from Prod.Version 0001 & 80% from Prod 0002, then at that point of time system will calculate the cost of the Finished-prod. as follows
CK11N, for the Product shows the Mixed-costing value as well as drill-down to Individual Production-Version.
Mixed-Costing within a Plant
And when we Create the production-Order, say with Version-‘0001’ then the Production-Order’s TARGET Cost is costed as per Version-0001 & the variance is created for the difference.
CK91 – For Production
CK94 – Set-up Production-MIX
Mixed Costing – Thru Procurement Alternatives (Purchase-order, Subcontracting, Stock-Transfer) etc
CK91 : Procurement Alternative
In Stock-Transfer, one can set-up special-procurement plant thru which STO will come to plant for which the Procurement Alternative is being generatedOne procurement alternative is Stock transfer from Plant10 to Plant 21
Similarly we can set-up Procurement-alternative with another Plant Stock-transfer as well as Vendor’s Purchase and Subcontracting.
Again in CK94, we can select specific alternatives for each month/year and define the MIXING Ratios
When do do Costing-run CK11N or thru CK40N, (below screen-shot is of CK11N), System computes the costing as per mixing-ratio defined in CK94.
Share this:
Posted on July 29, 2020By MonikaPatel mps4hana.comPosted in Product-Costing
RELATED
12.1 S4TWL – Reference and Simulation Costing : 2349294January 31, 2020In "12. Financials - Controlling"
COGM & COGS in Product CostingJune 27, 2020In "Product-Costing"
WN : 1809 – Controlling – Production Cost-Analysis EnhancementJanuary 29, 2020In "Production-Order Costing"
Post navigation
PreviousPrevious post:PRODUCT-COSTING USER-EXIT
NextNext post:MACRS : ASSET ACQUISITIONS(MID-QUARTER-CONVENTION) S_ALR_87012047
LEAVE A REPLY
Top of Form
Bottom of Form
This site uses Akismet to reduce spam. Learn how your comment data is processed.
SEARCH SITE FOR TOPIC
Top of Form
Search for:
Bottom of Form
MY SAP-BLOG CATEGORIES
0 My-POV-Blogs
Digital Transformation
S/4HANA Analytics
S/4HANA Tools POV
S/4HANA Migration Cockpit
S/4HANA Readiness Check
Simplification-Checklist
SAP S/4HANA Editions – POV
S/4HANA 1511 POV
S/4HANA 1610 POV
S/4HANA 1709 POV
S/4HANA 1809 POV
S/4HANA 1909 POV
SAP S/4HANA Cloud for Advanced Financial close
CertiQ
S/4HANA Best Practice
S/4HANA Finance
Asset-Accounting
Classical Planning – PnL, PCtr, CCtr, ProdOrd, Proj
COPA – Margin Analysis
Material-Ledger Material-Valuation
Material-Ledger with Actual Costing
Product-Costing
Production-Order Costing
Profit-Center Accounting
S/4HANA Group-Reporting
S/4HANA Realtime Consolidation
S/4HANA MasterData
S/4HANA On-Premise
S/4HANA 1610
S/4HANA 1709
S/4HANA 1809
S/4HANA 1909
S/4HANA 1909 – Finance
S/4HANA 2020 – Finance
S4TWL
0. Finance (8-16)
10. Financials Asset-Accounting
12. Financials – Controlling
24. Inventory
25. Logistics-PLM
T-Config
OBYC
Technical / ABAP
ABAP
FIORI
S4 DATA-Model Changes
Uncategorized
z. Finance
Auxiliary Account
Controlling
Credit Management
Finance AP/AR
Finance Accounts Payables (FI-AP)
Project-Systems (Project-WBS)
MY LEARNING-SAP PAGES
1. About Me
2. Contact Me
3. S/4HANA Innovations
CO PCA – Profit Center Accounting in S/4HANA
CO. Account-Based CO-PA
CO. Transfer Prices in S4
FIN 0. Currency types in S/4 FINANCE
FIN 1. ACDOCA – The Universal Journal
FIN 2. SAP S/4HANA GL Account
FIN 3. Extension Ledger in S/4HANA
FIN 7. Inventory Valuation thru Material LEDGER (ML)
FIN. Accelerated Close
FIN. New Asset Accounting
MD. BP – Business Partner
MD. Material Number Field Length Extension
SD. PRDC_ELEMENTS : S/4HANA SD-Pricing
4. RTR-Finance
1. RTR-Finance Processes
Credit Management
CM – 1. Purpose
CM – 2. Functional
CM – 3. THE DIFFERENCE
CM – 5. Tables
CM – 6. Credit Management in SAP S/4HANA : Process Steps thru FIORI Apps
Financial-Close – Process Steps : ECC Vs S/4HANA
House Banks in S/4HANA
Product Costing
Product Costing RUN and BOM (Process-TCODES)
Project-WBS Process
S/4HANA New Asset-Accounting
Tax
Indian TAX Reforms
GST – 2017 Goods and Service TAX
ECC GST – MM & FI
SAP Product Add-On for GST
SAP S/4HANA – GST
Stock-Transfer Process -with GST Invoice
VAT 2005 – Value Added TAX
5. FI-Integration
1. SDFI
1 SDFI Account Assignment / Costing
2. MMFI
MIGO – Stock Upload and Reversal (Process-TCODEs)
MMFI Account-Determination
3. PPFI
Production Order – Discrete Manufacturing
Production-Order : Accounting
Production-Order Costing – Planned vs Actual, Order-Balance, Settlement-Rule
SAP Finance LOB
xMy SAP-Blogs
yMy Linked-in Blogs
zMY SCN blog-posts LINKS
YOU CAN ALSO FOLLOW ME ON
INSIDE SAP S/4HANA – FROM OPEN.SAP.COM
Inside SAP S/4HANA Episode 78: Three-Year Anniversary Special Episode – Women in TechNovember 23, 2022
In this special episode to celebrate our third anniversary, our hosts Maria Silipo and Fernanda Rodrigues from SAP Engineering talk to Jessica Heath, Director of Platform GotoMarket at Red Hat, and Jennifer Röder, Chief of Staff to President and Chief Product Officer of SAP S/4HANA from SAP. They talk about their careers, the challenges of being women in the […]
Inside SAP S/4HANA Episode 77: How SAP S/4HANA Cloud, Public Edition Helps Vorwerker Diakonie to Support People in NeedNovember 2, 2022
In this new Inside SAP S/4HANA podcast episode, our host, Yannick Peterschmitt, talks to André Rieb, IT Project Manager from the german non-profit organization Vorwerker Diakonie. André shares the company's experience with the adoption of SAP S/4HANA Cloud, public edition, the start of their journey, the challenges, how to manage the end user adoption, […]
Inside SAP S/4HANA Episode 76: Manufacturing Performance with Cloud ERP at Smart Press Shop GmbH Pt. 2October 19, 2022
In the second part of our Inside SAP S/4HANA episode about Manufacturing Performance with Cloud ERP, our host, Markus Oertelt, Outbound Product Manager for Maintenance Management, continues his talk with his guests from Smart Press Shop GmbH, Project Manager Dr. Timo Böhm and Managing Director Hendrik Rothe. This week, they go into details about their implem […]
Inside SAP S/4HANA Episode 75: Manufacturing Performance with Cloud ERP at Smart Press Shop GmbH Pt. 1October 6, 2022
In the following two Inside SAP S/4HANA podcast episodes, our host, Markus Oertelt, Outbound Product Manager for Maintenance Management at SAP SE, is joined by two guests from Smart Press Shop GmbH: Project Manager Dr. Timo Böhm and Managing Director Hendrik Rothe. In the first episode of this series, they talk about their project start with SAP S/4HANA Clou […]
Inside SAP S/4HANA Episode 74: Registration of Indirect Taxation Abroad with SAP S/4HANA Cloud at TheValueChainSeptember 21, 2022
In this week's episode, our host Ulrich Hauke, Product Manager for SAP S/4HANA for Finance, is joined by Carlos Castanheira and Youssef Loutfi from our SAP Gold Partner TheValueChain and SAP colleague Calin Cernea from SAP Engineering. Together, they explore the Registration of Indirect Taxation Abroad – in short RITA – with SAP S/4HANA Cloud. Listen in […]
Inside SAP S/4HANA Episode 73: Moving SAP S/4HANA to the Public Cloud with Red Hat and Microsoft AzureSeptember 7, 2022
In this new Inside SAP S/4HANA podcast episode, our host, Yannick Peterschmitt, is joined by Prakash Pattaiyan, Principal Program Manager for SAP on Azure Engineering at Microsoft, and Ricardo Garcia Cavero, Principal Portfolio Architect at Red Hat. Together, they talk about moving SAP S/4HANA to the Public Cloud with Red Hat and Microsoft and list some of t […]
Inside SAP S/4HANA Episode 72: Learn from Rizing How to Acclimate Your Company to the CloudJuly 27, 2022
In this week's episode, our host Yannick Peterschmitt, Head of SAP S/4HANA Product Success Enablement, is joined by Jodi Hayes-Roth, CEO of Human Capital Management at Rizing and her colleague, Len Harms, Chief Experience Officer at Rizing. Together, they talk about SuccessFactors, another SAP application recently implemented by Rizing, and give tips on […]
Episode 71: Asset Management in SAP S/4HANAJuly 13, 2022
In this new Inside SAP S/4HANA podcast episode, our hosts, Markus Oertelt and Gerhard Welker, both Outbound Product Managers for Maintenance Management, are joined by Boris Mohr, Chief Product Owner for Maintenance Management. In this week's discussion, our three SAP experts share their professional experience on how to smoothly run processes for Asset […]
Inside SAP S/4HANA by Solution Management EP08: Intelligent Technologies - SAP Process AutomationJune 30, 2022
Replacing human intervention on high-volume, repetitive, and time-consuming tasks by machines is no longer a rarity, because it is already an integral part of today's business world. Shifting the responsibility for completing activities from humans to machines to minimize manual effort and human error makes business processes more cost-efficient, error- […]
Episode 70: SaaS and Manufacturing – Myth or Reality?June 29, 2022
There exists a common belief that handling manufacturing processes is too complex for a SaaS model and that manufacturing is simply not possible in the SaaS world. Our host Markus Oertelt has met up with Larissa Alessandra Krüsi, Head of Manufacturing at Scheer GmbH, to discuss why this myth doesn't hold true in the reality of the intelligent enterprise […]
FOLLOW ME ON TWITTER
My Tweets
BLOG STATS
242,958 hits
BLOGS I FOLLOW
Mana Clicks
Discover WordPress
The Daily Post
WordPress.com News
HOURS & INFO
India
Mon,Tue,Wed : 10:00am to 11:00am IST
Skip to content
Skip to breadcrumbs
Skip to header menu
Skip to action menu
Skip to quick search
Support Wiki
Spaces
Help
Log in
Pages
…
Other functions in Product Costing
Skip to end of banner
Go to start of banner
Mixed Costing
Skip to end of metadata
Created by Humberto Ordosgoitia, last modified by Feng Dong on Mar 19, 2021
Go to start of metadata
Mixed Costing
You can use Mixed Costing when:
- Use different production process to manufacture a product. - Use different sources for procuring a process.
A mixed cost estimate allows you to calculate a mixed price. You can update the mixed price as a standard price, and also use this mixed price to valuate materials controlled with S price.
To be able to create the mixed price, there must exist a procurement alternative for each of the production processes or supply sources.
The mixed price is resultant by applying a weighting factor for each of the cost estimates to the procurement alternatives using equivalence numbers. The system first costs the procurement alternatives, before mixing the cost estimates (using the defined mixing ratios) and calculating the mixed price.
How to carry out a mixed costing:
Define the Procurement alternatives: It is necessary to create one or more procurement alternative for each process category.
Define a quantity structure type in Customizing:
Define mixing ratios for the procurement alternatives in the application as based on the quantity structure type defined above:
Assign this quantity structure type to a costing version in Customizing:
You have carried out the material costing based on the above defined costing version:
Relevant notes
-If the costing lot size of a mixed costing cannot be explained please check the note 402440 which describes in detail how it is calculated.
-With mixed costing the system usually puts strategy 'Price form purchasing info record' to priority 1 if it is included in the valuation variant at any priority. Please see for further details notes:
898633 Mixed costing: Sequence of the valuation strategies. 319832 MixCostg: Only mat.master price w/cost est f.vendor.
-With the note 636967, when you enter strategy U (valuation price with USEREXIT) as priority 1, this strategy remains priority 1, and strategy L (price from purchasing information record), which is also required, receives priority 2.
-With mixed costing it is not possible to consider additive costs. Please see KBA note 1573495 ‘Additive Costs do not appear in a Mixed Costing Scenario’.
-Note 1995003 - CK74N/CK75N cannot be run in background.
-Note 1946259 - Dump RAISE_EXCEPTION in the program SAPLCKMLMVSCR running CK40N or CK11N
-With KBA 1664797 Release standard prices for valuation segments of split-valuated materials, it's possible to release the price on the valuation type level.
No labels
Privacy
Terms of Use
Legal Disclosure
Copyright
Trademark
Cookie Preferences
Community
Topics
Groups
Answers
Blogs
Events
Programs
Resources
What's New
Explore SAP
Home
Community
Blogs
Ask a Question
Write a Blog Post
Login / Sign-up
Former Member
May 17, 2010 4 minute read
How to configure Mixed Costing
61318,371
Mixed costing is very useful in some cases. For example, it’s the only way to release a standard cost estimate for each procurement alternative that is associated with a valuation type.
Recently I got some requests to explain in details how the mixed costing works. I hope this blog can help to explain.
The prerequisite for the mixed costing is as below:
– A quantity structure type is configured in the customizing
– This quantity structure type is associated to a costing version in the Customizing.
– The Procurement alternatives for the material have bee defined
– The mixing ratios for the procurement alternatives are defined based on the quantity structure type
– The material is costed with the above-defined costing version.
1. Define the quantity structure type
The path to configure mixed costing is as below (ECC 6.0):
The tcode for quantity structure type is OMXA.
Now I created the qty structure type “MIX”.
“Time Dependency” – This controls the time period in which the quantity structure will be used. It can be time indepenent, based on fiscal year, or based on each period.
“Percent validation” – Tick this indicator if you want to ensure that the sum of the existing mixing ratios for a material and quantity structure type totals 100%.
2. Associate the quantity structure type to a costing version
The path is right after that for the quantity structure type.
For the attached screenshot, the mixed costing will be called with the qty structure type MIX, when costing version = 1 & costing type = 19, or when costing version = 99 & costing type = 01 & valuation variant = 001. The system will not do mixed costing for the other combinations of costing version & costing type & valuation variant.
In this transaction, you can also define:
– Variant for transfer price determination
– Exchange rate type for currency translation
The configuration for the costing version can also be checked via costing variant configuration(tcode OKKN). It’s a more convenient way as the configuration is based on the combination.
In the Assignment tab, click the costing version button.
You’ll see for the costing variant PPC1 (costing type 01, valuation variant 001), costing version 99 is assigned the qty structure type “MIX”.
3. Define procurement alternatives
The tcode is CK91N. Here we need to create the procurement alt per material/plant.
I created two proc alternatives for different versions. It’s also possible to create alternatives for different valuation type/process cateogry/etc…
For process category
– Production
you can choose to create procurement alternatives for in-house production either with production versions or by using the BOM and routing.
– Purchase order
You can then enter a vendor and the relevant purchasing org in the initial screen.
In the cost estimate for a procurement alternative with reference to a vendor, strategy “L” (price from purchasing info record) is always automatically set to highest priority strategy. If you want to have a different logic, you may consider note 636967 and 319832.
You can also create an unspecified procurement alternative. To do this, do not enter a vendor or a purchasing organization. The material is then valuated with the prices in the material master and not using the purchasing info record.
– Subcontracting
In this case the system will require you to enter the information on the BOM, vendor and purchasing org.
– Stock transfer
You’ll be required to enter the source plant
4. Define Mixing Ratios for the procurement alternatives
The tcode is ck94
Here we can create the mixing ratios for the material per qty structure type.
Since our Qty Structure type “MIX” is based on fiscal year, here we only need to enter the “fiscal year” information.
If it’s based on period, we need to create the mixing ratios for each period.
Here all the proc alt created via CK91N will be displayed. And you can assign the mixing radio to them as you want.
– MR indicator
Set this indicator if you want to include a procurement alternative in mixed costing. It will ensure this procurement alt will be included in a mixed costing (even with a weighting of 0).
– Mixing Ratio
This is the most import figure in this transaction. You can enter equivalence numbers or percentages. But if “Percent validation” is ticked for the qty structure type, the sum of the existing mixing ratios must totals 100%.
5. Cost the material with the above-defined costing version.
Create a cost estimate for material YS-FRAME-01/plant IWS0 with costing variant PPC1 and costing version 99. The mixed costing is successfully carried out, as expected.
Please note, the costing lot size of mixed costing is different with the normal costing.
For more information please refer to note 402440, which provided very detailed explanation of the logic together with some examples.
FollowLikeRSS Feed
Alert Moderator
Assigned Tags
Retagging required
young sun
Similar Blog Posts
Change of resource in time ticket process order confirmation
By Former MemberMay 06, 2012
Bulk Storage Strategy in SAP EWM
By Harish PatilMar 02, 2020
5 Steps to Understanding Product Costing- Part 3 Quantity Structure
By Former MemberJan 02, 2013
Related Questions
MIC Calculation
By Satish BhagwatApr 14, 2020
ECM- Compa-ratio
By Former MemberAug 27, 2013
Blogs for Product Cost Planning (CO-PC-PCP)
By Former MemberMay 19, 2010
6 Comments
You must be Logged on to comment or reply to a post.
Former Member
May 31, 2010 at 9:00 pm
Hi Expert,
When i will post MB1B, system occur a error message F5800 of Inconsistent currency information as below:
Inconsistent currency information
Message no. F5800
Diagnosis
The currency information for the financial accounting component must be transferred fully for each currency type.
If, for example, the sending application sends corporate group currency data to Accounting, this currency data must be transferred for every company code line item.
An error has occurred for line item '0000000002' of the financial accounting document (company code '5000') with currency type '12' (currency key 'CNY'). This could be for one of three reasons:
Line item '0000000002' does not have any currency data for currency type '12', although at least one other line item has currency data for currency type '12'. Line item '0000000002' contains currency data for currency type '12', although at least one other line item contain no currency data for currency type '12'.
Line item '0000000002' has no currency data for currency type '12', although the currency type '12' corresponds to the local currency ( currency type '10').
System Response
Data processing within Financial Accounting can only take place with consistent currency information.
Procedure
The calling application probably contains a system error. Contact the calling application to locate the error.
PS: I have already activated transfer price with material ledger.
Could you please help to solve it? tks.
Like 0
Share
Former Member
September 12, 2015 at 8:44 am
One of the best document on Mixed Costing !
Regards,
Sharvari Joshi.
Like 0
Share
KAPIL MEHTA
February 28, 2018 at 2:42 pm
Hi
I read your article and it is very informative. I just have one query - Can you please suggest standard SAP report which gives standard cost breakup along with procurement alternative level information, if product involved Mixed costing.
I have checked S_ALR_87099930 & S_P99_41000111, but they do not show name/description/identification of Procurement alternative.
Regards
Kapil
Like 0
Share
Former Member
March 29, 2018 at 2:27 am
Hi Expert,
Can this set up be apply for one material which have been set up two difference BOM and two difference production Line?
thank you,
TZM
Like 0
Share
Tapan Rana
February 1, 2021 at 11:02 am
Yes
Like 0
Share
Maria Cirjan
November 3, 2022 at 11:54 am
Hi,
Thank you for the very good description. I have managed to setup all settings displayed above and run costing run via CK40n.
I am facing two issues:
after running ck40n the material price still appears with status KA - costed w/o errors instead of released w/o errors. (mm03 doesn't execute it goes into an infinite loading loop for the mixed costing material)
i have other materials set up with different costing version for which I am no longer able to run a second costing run in the same period.
Any suggestions would be highly appreciated
Like 0
Share
Find us on
Privacy
Terms of Use
Legal Disclosure
Copyright
Trademark
Cookie Preferences
Newsletter
Support