AUC SETTLEMENT THROUGH INTERNAL ORDER IN SAP

TAG: AUC SETTLEMENT THROUGH INTERNAL ORDER IN SAP

ASSET UNDER CONSTRUCTION END TO END PROCESS

Posted on 20 Jul 2017

Assets under Construction (AuC) are a special form of tangible assets. They are usually displayed as a separate balance sheet item, requiring separate account determination and their own asset classes. During the construction phase of an asset, all actual postings are assigned to the AuC. Once the asset is completed, a transfer is made to the final fixed asset.

Internal orders are used to capture the costs of AuC during the construction phase. Once the AuC is completed, the final asset is created in the appropriate asset class, and the internal order is set to complete. The next settlement transfers the AuC asset value to the completed asset.

Asset Under Construction Process:

1.1 CREATE ASSETS – ASSET UNDER CONSTRUCTION

1.2 Create Assets – for Final Settlement

We have created two asset master records, one Asset under Construction and one for the final settlement.

1. 3 Posting the Closing Invoice – Acquisition without order – FB01

In this step, you post the acquisition from purchase with vendor.

1.4 Define Distribution Rules for Asset Under Construction AIAB

In this process step, you maintain the settlement rules for the Asset under Construction created in the previous steps.

You have maintained the rules for the settlement. The execution of the settlement is part of the periodic processing.

1.5 Settle Asset under Construction  – AIBU

With the execution of this step, Assets under Construction are settled according to their settlement rules.

Note Under certain conditions, you may need to capitalize an asset under construction before all suppliers have presented their closing invoices. This can cause a few difficulties, especially if the closing invoice cannot be posted until the fiscal year following the capitalization of the asset under construction, and down payments were already posted to the asset under construction.

Initially, you post the down payment normally. If you then need to capitalize the asset under construction at the end of the fiscal year, but before the closing invoice is received, you post reserves for the total amount of the expected invoice. You post these reserves directly to the capitalized asset (external acquisition with vendor, transaction type 100). In the case where you plan to distribute the values from the asset under construction to several final assets, it makes sense to post the reserve to the asset under construction first, and then capitalize it. Whichever method you use, you must reverse the down payment on the asset under construction, because the down payment is not allowed to appear in the account for down payments to fixed assets. Instead, it must appear in the account for completed assets.

To settle the asset under construction, down payments must be cleared with invoice or forecasted invoice (reserve). The asset under construction can only be settled after this clearing

2.1 Asset Acquisition for Constructed Asset (Investment Orders /Internal Order)

2.1 Create Internal Order – KO01

2.2 Release Investment Order / Internal Order  – KO02

This activity releases investment order.

2.3 Accounts Payable – Posting Invoice to Investment Order – FB60

In this activity, you can enter a supplier invoice without reference to a purchase order.

2.4 Asset under Construction Settlement  – KO8G

In contrast to assessment, you cannot perform settlement across fiscal year boundaries. The system automatically determines the posting date from the posting period/fiscal year using the last day of the posting period. There are three processing types defined for settlement:

Automatic: The system selects all the distribution rules for a sender.

Periodic: All distribution rules with settlement types PER and AuC are selected. PER rules are applied first. In investment measures, this is followed by settlement to assets under construction.

Partial capitalization: Use this processing type if you want to partially capitalize an investment measure which is not yet complete, that is, if you want to settle part of the overall cost to finished assets.

With this process step a periodic settlement is executed. All costs collected on the investment order will be settled to the automatically created AuC.

2.5 Create Internal order Settlement Rule – KO02

In this process step the settlement rules for the final settlement are maintained and the status of the investment order will be set to technical completed, which allows the final settlement of the order.

2.6 Final Settlement of the Investment Order (Collective Processing) – KO8G

The final settlement transfers the costs from the AuC asset to the completed asset and to the cost center as specified in the settlement rules. After the final settlement the balance of the investment order and of the AuC is zero.

2.7 Completion of Investment Order -KO02

In this process step the investment order is closed by changing its status to Closed.

Thank You

Jayanth Maydipalle

Tagged Accounts Payable - Posting Invoice to Investment Order, AIAB, AIBU, Asset Acquisition for Constructed Asset (Investment Orders /Internal Order), ASSET UNDER CONSTRUCTION, asset under construction in sap, Asset under Construction Settlement, auc settlement through internal order in sap, CLOUD, Create Assets - Asset Under construction, Create Assets - for Final Settlement, Create Internal order Settlement Rule, Define Distribution Rules for Asset Under Construction AIAB, Final Settlement of the Investment Order (Collective Processing), INTERNAL ORDER, INVESTMENT ORDER, KO01, KO02, KO8G, LOCAL LEDGER, NEW ASSET ACCOUNTING, on premise, Parallel ledger, Posting the Closing Invoice - Acquisition without order, Release Investment Order / Internal Order, SAP S/4 HANA BEST PRACTICES, SAP S/4 HANA FINANCE 1610Leave a comment

Aditya Sibal

August 24, 2020 3 minute read

AUC creation through Investment measure (WBSE).

782,842

Introduction

This blog post is about AUC creation through an Investment measure (WBSE).

Here, will try to explain the process flow of AUC creation through Investment measure WBSE, which is regularly followed in Capex projects.

What is AUC?

AUC is a different form of asset, without depreciation. Requires separate account determination & Asset classes.

Parameters Covered in Blog Post:

Configurational for creation of AUC from WBSE

Process Flow

Configurational Process as below :

Step (A)

Define Asset Class for AUC

Path : SPRO>>Investment Management>>Project as Investment Measures>>Master Data>>Asset Under Construction>>Define Asset Classes

Investment Measure –  This indicator specifies AUC can only be created with investment measure relation/ reference.

No Direct creation.

Step (B)

Define Investment Profile :

Path : SPRO>>Investment Management>>Projects as Investment Measures>>Define Investment Profile

The investment profile as in the below screenshot plays a very important role in AUC creation.

It acts as a bridge between investment measure(WBSE) in our case and Asset class.

The area I have hidden is the place where we mention the Asset Class at the time of configuration of the Investment profile.

In the below screenshot, the Asset class is assigned, as created in Step (A).

Check – Manage AUC, When you set this indicator, the system automatically creates AuC for investment measure(in our case WBSE).

When the WBSE system status is Rel, AUC will be created automatically.

Step (C)

Define Investment Profile/Project Profile Assignment

Path : SPRO>>Investment Management>>Projects as Investment Measures>>Master Data>>Define Investment Profile

In the same option you will get :

(Define Investment Profile & Define Investment Profile/Project Profile Assignment)

As mentioned in the below screenshot, we will tag the Investment profile & Project profile with each other.

This step too has great relevance if you want to call a specific Investment profile for the project profile.

If left blank, then the user needs to opt/ choose the investment profile manually in the project.

Step (D)

Determine Depreciation Areas in the Asset Class

Path: SPRO>>Investment Management>>Projects as Investment Measures>>Master Data>>Assets under Construction>>Define Asset Classes

In the same option you will get :

(Determine Depreciation Areas in the Asset Class)

Kindly note for every AUC Asset class, depreciation areas are maintained with the depreciation key ‘0000″, having NO Depreciation calculated.

Process Flow as below :

Choose Investment profile

As displayed in the above screenshot, opt appropriate value for investment profile as highlighted below(green box).

For the generation of AUC, the linkage of Investment profile and Investment measure(in our case: WBSE) is a Pre-Requisite.

Release WBSE

As soon as you change the system status of WBSE from CRTD to REL.

AUC will be generated.

WBSE & Investment profile linked to each other

Release WBSE (Investment Measure)

Investment Profile tagged to WBSE calls the asset class for AUC, as mentioned in the Investment profile

Condition in Asset class for AUC (Investment Measure checked) is called.

This indicator specifies AUC can only be created with investment measure relation/ reference. with No Direct creation.

Further asset class calls depreciation key with no depreciation.

WBSE with system status “REL AUC”

Follow the path as described below to view AUC from WBSE.

In the blog post, I have tried giving a brief overview of how AUC can be created through WBSE by using an investment profile, which is a very important integrational point.

In the next proceeding blog post, will demonstrate settlement with respect to AUC.

Regards

Aditya Sibal

FollowLikeRSS Feed

Alert Moderator

Assigned Tags

PLM Project System (PS)

SAP Portfolio and Project Management

SAP Portfolio and Project Management for SAP S/4HANA

auc

sap im

SAP Investment Management

sap ppm

View more...

Similar Blog Posts

Costing & PR creation from Easy Cost Planning – SAP PS

By Aditya SibalOct 23, 2020

Capex Projects- Capitalization by accounting principle in S4 HANA

By T.P.R. MathavanDec 09, 2019

SAP PS - Budget Management

By Aditya SibalAug 18, 2020

Related Questions

Settlement

By venkatesh kulkarniFeb 21, 2009

Reverse values manually transferred from AUC to AUC

By Former MemberMar 19, 2014

User Exit for Direct Acquisition to Investment Measure AuC

By Former MemberApr 15, 2012

Join the Conversation

SAP TechEd

Tune in for tech talk. Stay for inspiration. Upskill your future.

SAP BTP Learning Group

SAP Business Technology Platform Learning Journeys.

Coffee Corner

Join the new Coffee Corner Discussion Group.

7 Comments

Nathan Genez

August 24, 2020 at 12:31 pm

I just have to ask… why would you use that first screenshot if you’re going to block out the whole thing?  You’re telling the reader that it has no informative value, so why include it at all?

I don’t understand why so many people are doing this with screenshots. I can understand hiding a customer’s company code description for identification purposes, but there is nothing revealing about company code value 1000, or a GL account number and description, or in this case, a project number. If it doesn't reveal anything, why hide it?

Like 4

Reply

Alert Moderator

Share

Aditya Sibal

Blog Post Author

August 24, 2020 at 1:01 pm

Agreed, but I felt it will be covered in the information stated through description part, at the same time, I have access to the system where I felt is will be safe to hide parameters mentioned in screen shots

although, again I would highlight that most of the areas are mentioned in descriptive content.also, please take this blog as a logical blogpost, do you feel project number, master number will make a difference?

Why not concentrate on the areas which are logically highlighted!

thanks for the comments!!

regards

aditya

Like 0

Reply

Alert Moderator

Share

Nathan Genez

September 7, 2020 at 12:23 pm

Well, it's highly distracting to the reader. It's harder to see what the point of an image is when it's half covered in black boxes.

Like 0

Reply

Alert Moderator

Share

Aditya Sibal

Blog Post Author

September 10, 2020 at 9:23 am

Hi Nathan

Have changed the first 2 screenshots.

Regards

Aditya

Like 0

Reply

Alert Moderator

Share

Cyrus Minab

October 2, 2020 at 11:17 pm

Waste of time with the screenshots being redacted, seriously why do even bother

Like 2

Reply

Alert Moderator

Share

Naveen Sharma

September 22, 2021 at 12:59 pm

Hi Aditya

It is indeed very detail explanation of AUC through WBSE. Is there any document of yours for AUC through Internal Order, because we have not using/activated WBSE in our organisation, so not much knowledge about that and even no Transaction codes mentioned here in the process flow to follow the WBSE blindly.

Regards

Prakash

prakash@radico.co.in

Like 0

Reply

Alert Moderator

Share

Branislav Haniačik

September 25, 2021 at 4:49 pm

Please describe on which blog you describe the settlement with respect to AUC.

I'm interested in settling on several investment measure (several asset subnummbers with different FM items)

Regards

Braňo

Like 0

Reply

Alert Moderator

Share

Asset Acquisition for Constructed Assets (External Procurment)
·         Create Assets
·         Posting the Closing Invoice
·         Define Distribution Rules for Asset Under Construction
·         Settle Asset under Construction
Asset Acquisition for Constructed Asset (Investment Orders)
·         Creating Investment Order
·         Releasing Investment Order
·         Accounts Payable – Posting Invoice to Investment Order
·         Monitoring Order Progress
·         Asset under Construction Settlement (collective processing)
·         Creating Assets for Complete AuC Settlement
·         Maintaining Settlement Rule for Final Settlement
·         Final Settlement of the Investment Order (Collective Processing)
·         Completion of Investment Order
返回FICO参考资料列表