第 161 页 / 共 257 页
AC412 Lesson: Periodic Activity Allocation
Cost Activity Actual Plan OperatingRate
center type Activity activity
(=%variance+100)
PC## MAH## %
a) Operating rateof the cost center PC##
CCA:InformationSystem→ReportsforCostCenterAccounting→
Plan/ActualComparisons→CostCenters: Actual/Plan/Variance
Cost center: PC##
Period: Current period infiscal year
Version: 0
Choose Execute.
Cost Activity Actual Plan OperatingRate
center type Activity activity
(=%variance+100)
PC## MAH## 1,200h 1,000h 120%
5. Executetheaccrualforbothofyourproductioncostcenters(H_PROD##)
andthecurrent periodin an UPDATERUN. Whichcostsareposted in
actualtothecostcentersundercostelement489000? Describetheresultsof
theactualcostscalculation forthecostcenterPC##.
Cost element 489000:
Cost center Activitytype TotalValue FixedValue
PC## MAH##
Continued on next page
149
2006/Q2 © 2006 SAP AG. All rights reserved.
| Cost center | Activity type | Actual Activity | Plan activity | OperatingRate |
|---|---|---|---|---|
| (=%variance+100) | ||||
| PC## | MAH## | % |
| Cost center | Activity type | Actual Activity | Plan activity | OperatingRate |
|---|---|---|---|---|
| (=%variance+100) | ||||
| PC## | MAH## | 1,200h | 1,000h | 120% |
| Cost center | Activitytype | TotalValue | FixedValue |
|---|---|---|---|
| PC## | MAH## |
第 162 页 / 共 257 页
Unit3: ActualCostAllocation AC412
CalculationforPC##withactivitytypeMAH##: ___________
a) To execute the accrual:
CCA:Period-EndClosing→SingleFunctions→Accrual
Costcentergroup: H_PROD##
Period: Currentperiodinfiscalyear
Update Run
Select Detaillist.
Choose Execute.
Expandusingthedisplayvariant“FixedValue”.
Costcenter Activitytype TotalValue FixedValue
PC## MAH## 11,000,- 5,000,-
Thefixedcosts(5,000.00)arepostedinActualasplanned. Thevariable
plancostsforhazardouswastearemultipliedwiththeoperatingrate
andpostedinactual(5,000.00*120%=6,000.00). Thispostingresults
intheaboveorderbeingcredited. AllFIpostingsforhazardouswaste
will then be posted to this order.
6. ChecktheresultsoftheaccrualinthePlan/ActualVarianceReportforthe
costcenterPC##. Whichcostsarepostedtothecostcentersinactualfor
the current period?
Continued on next page
150
©2006SAPAG.Allrightsreserved. 2006/Q2
| Costcenter | Activitytype | TotalValue | FixedValue |
|---|---|---|---|
| PC## | MAH## | 11,000,- | 5,000,- |
第 163 页 / 共 257 页
AC412 Lesson: Periodic Activity Allocation
Cost center CostElement Actualcosts PlanCosts
PC## 489000
a) Toestablishtheresultsofaccrualcalculation,select:
CCA:InformationSystem→ReportsforCostCenterAccounting→
Plan/ActualComparisons→CostCenters: Actual/Plan/Variance
Cost center: PC##
Period: Current period infiscal year
Version: 0
Choose Execute.
Costcenter CostElement Actualcosts PlanCosts
PC## 489000 11,000,- 10,000,-
Continued on next page
151
2006/Q2 © 2006 SAP AG. All rights reserved.
| Cost center | CostElement | Actualcosts | PlanCosts |
|---|---|---|---|
| PC## | 489000 |
| Costcenter | CostElement | Actualcosts | PlanCosts |
|---|---|---|---|
| PC## | 489000 | 11,000,- | 10,000,- |
第 164 页 / 共 257 页
Unit3: ActualCostAllocation AC412
Task 2:
Indirect Activity Allocations
ForthecostcenterQualityAssuranceQUAL##, youcanentertheexactactual
activity per period (sender activity), but youcannot enter which receiver cost
centers consumedtheseactivities, as this istoocomplex. However, you know
fromexperiencethatthenumberofhoursrequiredtocarryoutqualityassurance
hoursdependsonthenumberofproducedunits. Asdifferentunitsareproduced
(PCsand chips), youmust determineaweightedaverage/ratio that reflectsthe
timeand effortrequired to carryouttheinspection.
1. SenderactivitiesEnter thesenderactivitiesfor thecost centerQUAL##
andtheactivitytypeQUAH##(160h)atthecurrentdate. Sincetheactivity
typecategoryisActual3,youcanenterthissenderactivity. Theallocation
of these posted quantitiesshould automatically occur every period using
indirect activity allocation.
a) Sender activities
CCA:ActualPostings→SenderActivities→Enter
Go to the list screen.
Sendercenter: QUAL##
Activitytype: QUAH##
Activityquantity: 160 h
Save your entries.
2. EnterthestatisticalkeyfigureNPROD(producedunits)fortheproduction
cost centers PC## and CHIP##, under today's date. This statistical key
figureservesasthebasisfortheallocationofqualitychecks.
ReceiverCenter Statistical Key Total
Figure
PC## NPROD 120 pieces
CHIP## NPROD 400 pieces
a) ToenterthestatisticalkeyfigureNPROD,select:
CCA:ActualPostings→StatisticalKeyFigures→Enter
Go to the list screen.
Save your entries.
3. Cycle Processing:
Continued on next page
152
©2006SAPAG.Allrightsreserved. 2006/Q2
| ReceiverCenter | Statistical Key Figure | Total |
|---|---|---|
| PC## | NPROD | 120 pieces |
| CHIP## | NPROD | 400 pieces |
第 165 页 / 共 257 页
AC412 Lesson: Periodic Activity Allocation
YouwanttoallocatetheactivitiesofcostcenterQUAL##totheproduction
costcenters. Todothis,youusethequantitiesalreadyentered,anddistribute
them to the receiver cost centers (cost center group H_PROD##) using
the statistical key figure NPROD. Based on experience, you know that
inspectionsforPCstake10timesmore timethanfor chips, andtherefore
you apply a weighted ratio.
Atthestartofthecurrent fiscalyear, createacyclenamedILVQ##that
takescorresponding defaultsintoconsideration.
Inthefirstsegment(S1), youdefineforthesegmentheader that100%of
theactualpostedquantitiesaretobeallocatedaccordingtothereceiver
tracingfactorVariableportionbasedonactualstatisticalkeyfigures.
EnterthecostcenterQUAL##withtheactivitytype QUAH##assender
andthecostcentergroup H_PROD##asreceiver.
DefinethestatisticalkeyfigureNPRODasthereceivertracingfactor.
Usingweightingfactors,youdeterminethatcostcenterPC##(forexample,
1000) requires ten times asmuch time and effort as cost center CHIP##
(for example, 100).
Assignthecycletoacyclerungroup,whichyoucreateunderanewrun
groupAG##(“withParallelProcessing”). Thisensuresthatallcyclescan
run in parallel in the course.
Check and save the cycle.
a) To create a cycle, select:
CCA: Period-End Closing → Single Functions → Allocations →
Indirect Activity Allocation
Extras → Cycle → Create
Cycle: ILVQ##
Start date: 01/01/ current fiscal year
Choose Enter.
Text: Allocation Quality ##
Attach segment
Choose Enter.
Segmentname: S1–“IndirectAAQuality##”
Segment header tab:
Sender Values:
Continued on next page
153
2006/Q2 © 2006 SAP AG. All rights reserved.
第 166 页 / 共 257 页
Unit3: ActualCostAllocation AC412
Rule: Posted quantities
Share in: 100% Actual values
Receiver Tracing Factor:
Rule: Variable portions type
Actual statistical key figures
Scaling: No scaling
Sender/Receiver:
Sender: Cost center QUAL##
Sender: Activity type: QUAH##
Receiver: Costcenter group: H_PROD##
Receiver Tracing Factor:
Var. portiontype: Actual statistical keyfigures
Statistical key figure: NPROD
Receiver weighting factors(per 100)
CHIP##:
PC##:
(ProducedunitsofPCsrequire10timesmoretimeandefforttocheck
than chips.)
Header: Cycle→Check→Formal check
Save your entries.
Goto → Cycle Run Group:
Enter AG## and choose Create.
Enter “With Parallel Processing”.
Choose Enter.
Save your entries.
Choose Back.
Save the entirecycleand exit the screen.
4. Run the cycle ILVQ## for the current period in the test run. What
quantitiesareallocatedfromthesender? Howmanyqualityhoursareposted
to the receiver?
Continued on next page
154
©2006SAPAG.Allrightsreserved. 2006/Q2
第 167 页 / 共 257 页
AC412 Lesson: Periodic Activity Allocation
Sender: Receiver:
PC## h CHIP##: 1 h
PC##: 10 h
Explain the quantity calculation.
Repeat the cycle in an update run.
a) Execute cycle
CCA: Period-End Closing → Single Functions → Allocations →
Indirect Activity Allocation
Period: Current to current
Fiscal Year: Current fiscal year
Cycle: ILVQ##
Choose Enter.
Select Test run.
Choose Execute.
Results:
Hint: To display the sender and receiver activity quantity,
change thelayoutdisplay ifnecessary.
Sender: Receiver:
PC## -160 h CHIP##: 40 h
PC##: 120 h
Repeat the cycle in an update run.
Reason: The 160 h from the cost center QUAL## (posted actual
quantities) are allocated as follows:
CHIP## receives 40h: Calculation basis: 400 portions (posted
statisticalkeyfigureNPROD=400pieces)x1(weightingfactor)
PC## receives 120h: Calculation basis: 1200 portions (posted
statisticalkeyfigureNPROD=120pieces)x10(weightingfactor)
5. Gotothecycleoverviewanddisplayallcyclesforindirectactualactivity
allocation.
Continued on next page
155
2006/Q2 © 2006 SAP AG. All rights reserved.
| Sender: | Receiver: | ||
|---|---|---|---|
| PC## | h | CHIP##: 1 | h |
| PC##: 10 | h |
| Sender: | Receiver: | ||
|---|---|---|---|
| PC## | -160 h | CHIP##: | 40 h |
| PC##: | 120 h |
第 168 页 / 共 257 页
Unit3: ActualCostAllocation AC412
Changetheoverviewlayoutsothatthecolumns“Lastchangedby”,“Cycle
rungroup”and“Lastexecutedon”arealsodisplayed.
Fromtheoverview,godirectlytothecostaccountingdocumentthatyou
generated.
Document number:
Whatamount wascreditedtoSenderQUAL##?
QUAL## >
CHIP##
QUAL##>PC##
a) Cycle Overview
CCA: Period-End Closing → Single Functions → Allocations →
Indirect Activity Allocation
Extras → Cycle →Display Overview
Select the items “Indirect Activity Allocation” and “Actual” and
choose Execute.
Changetheoverviewlayoutsothatthefields“Previousprocessing”
and“Cyclerungroup”areaddedtothedisplay.
Position the cursor on your cycle in the links selection and choose
“Previous Processing”!
Choose Enter.
Document number ____________________
Double-click thedocument (see table).
QUAL## > ~7,733,- (40h*193planprice)
CHIP##
QUAL##>PC## ~23,200 (120h*193planprice)
Continued on next page
156
©2006SAPAG.Allrightsreserved. 2006/Q2
| QUAL## > CHIP## | ||
|---|---|---|
| QUAL##>PC## |
| QUAL## > CHIP## | ~7,733,- | (40h*193planprice) |
|---|---|---|
| QUAL##>PC## | ~23,200 | (120h*193planprice) |
第 169 页 / 共 257 页
AC412 Lesson: Periodic Activity Allocation
Task 3:
Target=actualactivityallocationforcostcenterENER##:
General explanation:
Asyoucannotexactlymeasuretheactivityoftheenergycostcenter,butstillwant
todistributeitfairlytothereceiver,youusethetarget=actualactivityallocation.
This allows you to determine the activity flow from the sender relative to the
operating rate of the receiver cost centers.
1. Intheplanning overview, enterthecostcenterENER##forthecurrent
period. What quantity of energy activitiesENH## are to be transferred
(fixedandvariable)tothereceiversPC##andCHIP##?
Cost Activity ECost EActivity Quantity Quantity Quantity
center Type center Fixed Variable
ENER## ENH## CHIP## MAH## kWh kWh
ENER## ENH## PC## MAH## kWh kWh
a) Target=actualactivityallocationforcostcenterENER##:
Planningoverviewfor cost centerENER##
CCA:InformationSystem→ReportsforCostCenterAccounting→
PlanningReports→CostCenters: PlanningOverview
Cost center: ENER##
Period: Currentperiodincurrentfiscalyear
Version: 0
Choose Execute.
Costcen- Activity- ECost- E Quan- Quanti- Quanti-
ter Type center Activity tity tyFixed tyVari-
able
ENER## ENH## CHIP## MAH## 300.000 - kWh
ENER## ENH## PC## MAH## 1.200.000 - kWh
The reports shows the planned credit.
2. UsetheActual/Planvariancereporttoanalyzethecurrentoperatingrate
forthereceivercostcentersPC##andCHIP##inthecurrentperiod.
Continued on next page
157
2006/Q2 © 2006 SAP AG. All rights reserved.
| Cost center | Activity Type | ECost center | EActivity | Quantity | Quantity Fixed | Quantity Variable |
|---|---|---|---|---|---|---|
| ENER## | ENH## | CHIP## | MAH## | kWh | kWh | |
| ENER## | ENH## | PC## | MAH## | kWh | kWh |
| Costcen- ter | Activity- Type | ECost- center | E Activity | Quan- tity | Quanti- tyFixed | Quanti- tyVari- able |
|---|---|---|---|---|---|---|
| ENER## | ENH## | CHIP## | MAH## | 300.000 | - | kWh |
| ENER## | ENH## | PC## | MAH## | 1.200.000 | - | kWh |
第 170 页 / 共 257 页
Unit3: ActualCostAllocation AC412
Cost Activity Actual Planned Operat
center Type Activity Activity ing
Rate
(% variance+100)
PC## MAH## h h %
CHIP## MAH## h h %
a) OperatingrateforreceivercostcentersPC##andCHIP##
CCA:InformationSystem→ReportsforCostCenterAccounting→
Plan/ActualComparisons→CostCenters: Actual/Plan/Variance
Cost center: PC##
Period: Currentperiodincurrentfiscalyear
Choose Execute.
Costcenter Activity- ActualAc- PlannedAc- Operating
Type tivity tivity
Rate
(% variance+100)
PC## MAH## 1200h 1000h 120%
CHIP## MAH## 320h 350h 91%
CHIP##** MAH##** 320h 200h** 160%**
**Costcenterhasplannedactivitiesof200hinperiods6-9,and350h
in the remaining periods.
3. Executetarget=actualactivityallocationforthecurrentperiod.
RunyourcostcentergroupH_TECH##inatestruninversion0.
WhatoperatingratedidcostcenterENER##haveinthecurrentperiod?
Operating rate of ENER##: ________%
Continued on next page
158
©2006SAPAG.Allrightsreserved. 2006/Q2
| Cost center | Activity Type | Actual Activity | Planned Activity | Operat ing Rate |
|---|---|---|---|---|
| (% variance+100) | ||||
| PC## | MAH## | h | h | % |
| CHIP## | MAH## | h | h | % |
| Costcenter | Activity- Type | ActualAc- tivity | PlannedAc- tivity | Operating Rate |
|---|---|---|---|---|
| (% variance+100) | ||||
| PC## | MAH## | 1200h | 1000h | 120% |
| CHIP## | MAH## | 320h | 350h | 91% |
| CHIP##** | MAH##** | 320h | 200h** | 160%** |
第 171 页 / 共 257 页
AC412 Lesson: Periodic Activity Allocation
Post the results.
a) Toexecutetarget=actualactivityallocation,select.
CCA: Period-End Closing → Single Functions → Allocations →
Target=Actual Activity Allocation
Costcentergroup: H_TECH##
Businessprocesses: None
Version: 0
Period: Currentperiodincurrentfiscalyear
Select Test run.
Choose Execute.
Operating rate of ENER##:
(Periods 6-9: 128 %)
Post the results.
4. UsetheActual/PlanVarianceReporttodeterminewhichactualcostsfrom
cost center ENER## wereallocated to the receiver PC##. Go to the line
itemsofcostelement639200andchoosethelayout“ActivityAllocation”.
Continued on next page
159
2006/Q2 © 2006 SAP AG. All rights reserved.
第 172 页 / 共 257 页
Unit3: ActualCostAllocation AC412
Sender/ Receiver/ Quantity Value
ActivityType ActivityType
ENER##/ENH## /
a) Resultsof thetarget=actualactivityallocation
CCA: Information System > Reportsfor Cost CenterAccounting >
Plan/ActualComparisons→CostCenters: Actual/Plan/Variance
Cost center: ENER##
Period: Currentperiodincurrentfiscalyear
Version: 0
Choose Execute.
Selectthelineitemforcostelement639200(allocatedactualcosts)
Double-click the entry.
Choose Actual Line Items.
In the line item, choose:
Layout: Secondarycostsactivityallocations
Sender/Activity Receiver/Activity Quantity Value
Type Type
ENER##/ENH## PC##/MAH## -120,000 -19,920,-
kWh
Plan price
0,166*
120,000kWh
160
©2006SAPAG.Allrightsreserved. 2006/Q2
| Sender/ ActivityType | Receiver/ ActivityType | Quantity | Value |
|---|---|---|---|
| ENER##/ENH## | / |
| Sender/Activity Type | Receiver/Activity Type | Quantity | Value |
|---|---|---|---|
| ENER##/ENH## | PC##/MAH## | -120,000 kWh | -19,920,- |
| Plan price 0,166* 120,000kWh |
第 173 页 / 共 257 页
AC412 Lesson: Periodic Activity Allocation
Lesson Summary
You should now be able to:
• Describeandusetechniquesforperiodicactivityallocation
• Describeandusetarget=actualaccrualcostcalculations
• Describeand use indirect activity allocation
• Describe and use template allocation
• Describeandusetarget=actual activityallocation
161
2006/Q2 © 2006 SAP AG. All rights reserved.
第 174 页 / 共 257 页
UnitSummary AC412
Unit Summary
You should now be able to:
• Explaintheconceptofactualcostandactivityallocation
• Execute,cancel,andreposttransaction-basedactivityallocations
• Describeandimplementtheconceptof“EnteringSenderActivities”
• Describeandusetechniquesforperiodicactivityallocation
• Describeandusetarget=actualaccrualcostcalculations
• Describeand use indirect activity allocation
• Describe and use template allocation
• Describeandusetarget=actualactivityallocation
162
©2006SAPAG.Allrightsreserved. 2006/Q2
第 175 页 / 共 257 页
AC412 Test Your Knowledge
Test Your Knowledge
1. Whenactualcostsareentered, aretransferred
from thepreviouscomponenttocostaccounting.
Fillintheblankstocompletethesentence.
2. To execute activity allocation, create an activity type with
activity type category 1.
Fillintheblankstocompletethesentence.
3. Activity type category 4 is frequently used
toallocatecoststoProfitabilityAnalysis(CO-PA).
Fillintheblankstocompletethesentence.
4. Accrual cost calculation
Choosethecorrectanswer(s).
□ A Isthedistributionandpostingofaccrualcosts
□ B CanbepostedintheFinancialAccountingcomponent(FI)using
recurring entries
5. Youcanonlyusethetarget=actualmethodtoaccrueactivity-dependentcosts.
Determinewhetherthisstatementistrueorfalse.
□ True
□ False
6. Internalorderscannotbethesenderofindirectactivityallocation.
Determinewhetherthisstatementistrueorfalse.
□ True
□ False
7. Theactualactivitytypecategory5mustbeusedforthisactualallocation.
Determinewhetherthisstatementistrueorfalse.
□ True
□ False
163
2006/Q2 © 2006 SAP AG. All rights reserved.
第 176 页 / 共 257 页
TestYourKnowledge AC412
Answers
1. When actual costs are entered, primary costs are transferred from the
previous component to cost accounting.
Answer: primary costs
2. To execute direct activity allocation, create an activity type with activity
type category 1.
Answer: direct
3. Activitytypecategory4isfrequentlyusedbyadministrationandsalescost
centerstoallocatecoststoProfitabilityAnalysis(CO-PA).
Answer: byadministrationandsalescost centers
4. Accrual cost calculation
Answer: A, B
The distribution and posting of these accrued costs is called accrual
calculation.
You can post accrualsin theFinancial Accounting(FI) component using
recurring entries, or determine them in Cost Accounting using the costs
posted there.
5. Youcanonlyusethetarget=actualmethodtoaccrueactivity-dependentcosts.
Answer: False
The target=actual method is used for the accrual calculation of
activity-dependent costs.
6. Internalorderscannotbethesenderofindirectactivityallocation.
Answer: False
Costcentersfunctionassendersinindirectactivityallocation.
164
©2006SAPAG.Allrightsreserved. 2006/Q2
第 177 页 / 共 257 页
AC412 Test Your Knowledge
7. Theactualactivitytypecategory5mustbeusedforthisactualallocation.
Answer: True
Theactualactivitytypecategory 5must beusedfor thisactualallocation
(target=actual allocation).
165
2006/Q2 © 2006 SAP AG. All rights reserved.
第 178 页 / 共 257 页
第 179 页 / 共 257 页
第 180 页 / 共 257 页
Unit3: ActualCostAllocation AC412
166
©2006SAPAG.Allrightsreserved. 2006/Q2
第 181 页 / 共 257 页
Unit 4
Period-end closing
Unit Overview
Thislessonshowsthedifferentpossibilitiesformonitoringthecostsofareasof
responsibilityandappropriateperiod-endclosingscenarios.
Unit Objectives
After completing thisunit, you will beableto:
• Analyzeandevaluatestandardreportssuchasplan/actualcomparisons
• Explainthelimitationsofplan/actualcomparisons
• Explainthe goals of and options available in enhanced R/3 analysisand
allocation tools
• Explaintheconceptofcontinuouscalculationoftargetcosts
• Interprettarget/actual comparisonsof cost centers
• Usetargetcostanalysisasaninstrumentforcostandactivitycontrollingin
cases of operating fluctuations
• Explainactual costsplittingandhowtoexecuteit
• Distinguishbetweenthevariancecategoriesoftheinputsideandtheoutput
side
• Explain the causes of variances
• Implement variance analysis effectively
• Describethesignificanceofactualpricecalculationanditsprocedures
• Configureandexecuteactual pricecalculation
• UsethecostcomponentsplitinOverheadCostControlling
• DescriberevaluationatactualpricesinProductCostControlling
• ExplainthebusinessreasoningbehindmarginalcostallocationsinCO-OM
• Describetheconceptofandprocedureforpredistributionoffixedcosts
• Configure and use the predistribution of fixed costs in overhead cost
controlling
• Explainwhatneedstobeconsideredforspecialcasesofpredistributionof
fixed costs
167
2006/Q2 © 2006 SAP AG. All rights reserved.
第 182 页 / 共 257 页
Unit4: Period-endclosing AC412
Unit Contents
Lesson: Plan/Actual Comparison.............................................169
Lesson: Target Cost Analysis .................................................174
Exercise 7: Target Cost Analysis.........................................179
Lesson: Variance Analysis.....................................................191
Exercise 8: Variance Analysis ............................................203
Lesson: Actual Price Revaluation ............................................207
Exercise 9: Actual Price Revaluation....................................213
Lesson: Marginal Costs........................................................224
168
©2006SAPAG.Allrightsreserved. 2006/Q2
第 183 页 / 共 257 页
AC412 Lesson: Plan/Actual Comparison
Lesson: Plan/Actual Comparison
Lesson Overview
In this lesson, you learn how to analyze standard reports and explain their
limitations.
Lesson Objectives
After completingthislesson, youwillbeable to:
• Analyzeandevaluatestandardreportssuchasplan/actualcomparisons
• Explainthelimitationsofplan/actualcomparisons
• Explainthe goals of and options available in enhanced R/3 analysisand
allocation tools
Business Example
The plan and actual costs have been entered and allocated. Now you want to
utilizethedifferentcostcontrolandanalysismethodsavailableintheR/3System.
Cost Center Balance
Figure 44: Cost Center Balance
169
2006/Q2 © 2006 SAP AG. All rights reserved.
第 184 页 / 共 257 页
Unit4: Period-endclosing AC412
As soon as all periodic allocations are executed (accrual allocations, periodic
repostings, distributions, assessments, indirect activity allocations, and
target=actual activity allocations), you can executeclosing analyses for your
areasofresponsibility. TheControllingfunctionsavailableintheR/3System
depend onthefunctions you have used duringtheperiod andcost accounting
system that you implement.
Theinformationsystemplaysacrucialrolehere. Therefore,wewillnowtakea
lookatthesimpleanalyticalfunctionsthatareavailable,sothatyoucanmaster
the more advanced functions covered later in this unit. In the “Under/Over
Absorption Actual Costs” column in the plan/actual comparison, you can
analyze the balance of the cost center:
• Thisspecifiesthedebitsonthecostcenter andhowmuchof thesedebits
thecostcenterhaspassedon. Ifthecostcenterhasassessedallitscosts,
the balance is zero.
• For cost centers that allocate activity-related costs using plan prices, the
balanceisusuallytransferredtoProfitabilityAnalysisusingassessment.
Foractivitytypes/costcentersandconstantperiodprices(inthiscase,200.00
EUR/quantityunit),theallocatedcostsareinlinewiththetargetcreditsas
opposedtotheactualactivity–seeaboveillustration.
• Anegativebalance–asshownabove–showsthattheactualcostsincurred
werelessthantheactivitycostsdebitedtothereceiver(-5,000EUR).
Plan/Actual Comparison
Figure 45: Plan/Actual Comparison: Debit Side
170
©2006SAPAG.Allrightsreserved. 2006/Q2
第 185 页 / 共 257 页
AC412 Lesson: Plan/Actual Comparison
Asimplewayofjudgingthecosteffectivenessofacostcenterinstandardcosting
istocarryoutaplan/actualcomparisononthedebitside. Theactualcostsare
compareddirectlywiththeplancostsinthiscase.
Intheabovereport,theactualcostsexceedtheplancostsby3,000EUR.Thatis,
highercostswereactuallyincurredthanwereplanned.
However,thisreportdoesnottakeintoaccounttheoutputofthecostcenter,sowe
cannotreliablyjudgeitscosteffectivenessfromthisdata.
Figure 46: Plan/Actual Comparison: Credit Side
Theplan/actualvarianceonthecredit sidetellsuswhatcostswereallocated
comparedwiththeplannedallocationforthecostcenter.
Inthisexample, thevarianceonthecreditsideisnegative. Thismeansthatthe
receiversoftheactivities(or costs) of thecostcenter areburdenedwithalot
higher debits than planned.
Theillustrationshowsasimplecaseforonecostcenterwithonlyoneactivitytype
thatisallocatedwithaniterativeplanpriceof200EUR.
171
2006/Q2 © 2006 SAP AG. All rights reserved.
第 186 页 / 共 257 页
Unit4: Period-endclosing AC412
Figure 47: Period-end closing: Extended Scenarios
In the R/3 System, you can use various methods for advanced analysis of
responsibilityareas. Theappropriatemethoddependsontheorganization'sgoals
and its cost controlling approach.
Fourperiod-endclosingscenariosarethereforeillustratedbelow. Eachpresents
different information and hasdifferent impacts. Thescenarios are designed to
clearlyillustratetheimportance,goals,tools,requiredsteps(Customizing)and
the ideal procedure in each case.
Incertaincases,thesescenarioscanbecombinedwitheachother. Forexample,
you can combine marginal cost allocation with variance analysis, but not with
revaluation at actual prices. More detailed information is contained in the
following scenarios.
172
©2006SAPAG.Allrightsreserved. 2006/Q2
第 187 页 / 共 257 页
AC412 Lesson: Plan/Actual Comparison
Lesson Summary
You should now be able to:
• Analyzeandevaluatestandardreportssuchasplan/actualcomparisons
• Explainthelimitationsofplan/actualcomparisons
• Explainthe goals of and options available in enhanced R/3 analysisand
allocation tools
173
2006/Q2 © 2006 SAP AG. All rights reserved.
第 188 页 / 共 257 页
Unit4: Period-endclosing AC412
Lesson: Target Cost Analysis
Lesson Overview
In this lesson, you learn how to analyze cost centers with regard to the actual
operating level.
Lesson Objectives
After completingthislesson, you will beable to:
• Explaintheconceptofcontinuouscalculationoftargetcosts
• Interprettarget/actual comparisonsof costcenters
• Usetargetcostanalysisasaninstrumentforcostandactivitycontrollingin
cases of operating fluctuations
Business Example
Astheoperatinglevelsinyourcompanymayfluctuate,youaremainlyinterested
inatargetcostanalysisthatexamineshowtheactualcostsvarywiththeoperating
level.
Target Costs
Figure 48: Target Cost Analysis: Objective
Inorderthatyoucananalyzetheactualcostsonamoredetailedlevel,youmust
take account of the number of activities actually used as compared to those
plannedinthecostcenter. Costcenteranalysisisbasedonthetargetcosts.
174
©2006SAPAG.Allrightsreserved. 2006/Q2
第 189 页 / 共 257 页
AC412 Lesson: Target Cost Analysis
The target costs are determined based on the cost center's plan costs and the
activities provided(operating rate). Targetcostsarethose expectedfor certain
activities.
The operating rateindicatestheactual capacity utilization of an activity bya
cost center, and is given as the ratio (in percent) of the actual activity to the
plan activity.
Figure 49: Target costs: Concepts and Calculations
TheR/3Systemcancontinuouslycalculatethetargetcostsdirectly. Thismakesit
possibletoobtainanactual/targetcomparisonbeforetheendoftheperiod. Target
costsdeviate from theplan costsonlywhenactivity-dependent planning has
takenplace. Increasesintargetcostsandactualactivitiesofanactivitytypeare
correlated for the cost center.
Targetcoststhatappearinthestandardreport“Target/ActualComparison”
are calculated as follows:
Debit side:
• Activity-independent plan costs:
– Plan costs = (Fixed) target costs
• Activity-independent plan costs:
– Fixed plan costs = Fixed target costs
– Variableplancosts*operatingrate=Variabletargetcosts
(Secondarycostsarecalculatedusingfixedorvariablequantities)
175
2006/Q2 © 2006 SAP AG. All rights reserved.
第 190 页 / 共 257 页
Unit4: Period-endclosing AC412
Credit side:
• Targetcredit=Allocatedquantities*iterativeplanprices(fullcostbasis)
Figure 50: Target Costs: Areas of Responsibility
Targetcostscanbeusedinreportingtorepresentvariousareasofresponsibility,
suchascostcentersandcostcentergroups. The“variation”functionallowsyouto
go from one area of responsibilityto another.
Youcananalyzetheactualandtargetcostsforeacharea. Youcanalsoviewthe
appropriateactivitytypesforeacharea,alongwiththecurrentoperatingrates.
Theaboveexampleshowshowtargetcostscanprovidemoredetailedinformation
thantheplan costs, for different operating rates.
Theactualcostsmaybehigherthanthetargetcosts,duetothefollowingreasons:
• The actual costs are too high
• The actual activity quantity is too low
176
©2006SAPAG.Allrightsreserved. 2006/Q2
第 191 页 / 共 257 页
AC412 Lesson: Target Cost Analysis
Target=Actual Comparison and Target Cost Analysis
Figure 51: Target-Actual Comparison
Thetarget/actualvariancesfromthetargetcostanalysisareusedtocheckthe
economicvariancesofthedebit side. Here, theincurredcostcentercostsare
comparedwiththosethatshouldhavebeenincurred.
Theabovereportshowsthatthecostcenterincurredlesscoststhanitshouldhave
at the same level of operation, even though more actual costs are shown than
plancosts. Thecostcenterhadafavorable(negative)target/actualvariancefor
the debit side (-1,000 EUR). This stems from a higher level of activities than
planned. Thetarget/actualcomparisonreport showstheoperatingrateforeach
individual activity type of the cost center.
Furthermore,the“over/underabsorption”valuedetailswhatcostswereallocated
too high, or toolow(compared to thetarget costs). Thesearevariances of the
estimatedcosts(targetcosts)thataredebitedtoohighortoolowtothereceiver. In
theexampleabove,thereceiverisallocatedwithactivitycoststhataretoohigh
(4,000EUR),whichthenworksoutfavorablyforthesendercostcenter(negative
variance -4,000 EUR).
The illustration showsthat thebalance (under/over absorptionof actual costs)
is the sum of the target/actual variances for the debit side plus the under/over
absorption of the target costs.
177
2006/Q2 © 2006 SAP AG. All rights reserved.
第 192 页 / 共 257 页
Unit4: Period-endclosing AC412
Figure 52: Target Cost Analysis: Procedure
Ideal sequence for target cost analysis:
• Theperiod-endclosingscenarioswithtargetcostcalculationdiffersfrom
standardanalyzesinthattheactualactivities,andnotjusttheactualcosts
areexaminedtoevaluatethecostcenter'sperformance.
• You can obtain meaningful target costs that increase with the actual
activity output (and thus favorably affect the cost center) only with
activity-dependent planning. The actual costs for activity-independent
planningwouldalwaysequaltheplancosts. Tofullyinterprettheresults,
youshouldfirst executeplan reconciliation to calculatetheexact prices
to be allocated.
• Otherwise, this analysis is easy to use and offers current target cost
calculations, which is an advantage.
• The balance of the cost centers is normally transferred to profitability
analysis, asisthecasewithplan/actual analyses.
178
©2006SAPAG.Allrightsreserved. 2006/Q2
第 193 页 / 共 257 页
AC412 Lesson: Target Cost Analysis
Exercise 7: Target Cost Analysis
Exercise Objectives
After completingthisexercise, youwillbeableto:
• Analyzestandardreportssuchasplan/actualcomparisons
• Describe how target costs are updated
Business Example
Your choice of analysis tool depends on your management goals. You can
chooseatoolonceyouhavelearnedaboutadvancedplanningandthemethods
for transaction-based and periodic actual costs and activity allocations. In
the exercises below you will examine which analysis tools will provide the
informationandresultsyourequireforthecostcenterRepairs“Rep#”.
Task 1:
Preparation:
1. Inyourusersettings,deletegroupH_TECH##fromthecostcentergroup,
and enter cost center REP## instead.
Task 2:
Checking the plan costs
1. NoactualcostshavebeenpostedtoyourcostcenterREP##forthecurrent
period. Viewtheplannedvaluesbygoingtocostelementplanning(version
0, current period, cost centerREP##, activitytype*[=all], cost elements
400000–699999,freeentry). Whichthreecostelementshavebeenplanned
uptonow? Whatvalueswereplannedforthesecostelements? Forwhich
costelementdidyousetthe“Recordquantity”indicator?
CostCenter: REP##forthecurrentperiod:
Activity Cost Plan Variable Quan- Variable Units Q
tity
Type Type Costs
Fixed
Fixed
Continued on next page
179
2006/Q2 © 2006 SAP AG. All rights reserved.
| CostCenter: REP##forthecurrentperiod: | |||||
|---|---|---|---|---|---|
| Activity Cost Plan Type Type Costs Fixed | Variable | Quan- tity Fixed | Variable | Units Q | |
第 194 页 / 共 257 页
Unit4: Period-endclosing AC412
(Ifthefieldforactivitytypeisblank(or#),wasactivity-independent/fixed
planning carried out?)
Compareyourplanwiththesolution,andchangethevaluesifneeded.
2. Analyzetheplannedoutputof yourcostcenter REP##inplanning of the
activity output.
Whatactivityquantities(activitytype*)wereplannedinthecurrentperiod?
What price did you calculate earlier for this quantity (the price was
automaticallytransferredintoplanningduringpricecalculation)?
What activity quantity was scheduled?
Comparethiswiththevalueinthesolutionsandmakechangesifnecessary.
CostcenterREP##inthecurrentperiod:
Activity Planned Fixed VariablePrice ScheduledActivity
Price
Type Activity
REPH##
3. AnalyzecostcenterREP##usingthetarget/actualcomparisonreportinthe
information system.
Have any actual costs been posted?
Haveanyactivitiesbeenoutputduringtheperiod?
Interpretthetargetcostsusingtheknownvalues.
Interprettheplancostsusingtheknownvalues(gotothenextpageinthe
report).
CostCenter: REP## Interpretation:
Actualcosts:
Actualactivities:
Targetcosts: Sincetheoperatingrate=0: Allplanfixed
costs
(Comparisoncostsifthereiszerooutput)
Plancosts: Allfixedandvariableplancosts
(seenextpageofreportonright-handside)
Continued on next page
180
©2006SAPAG.Allrightsreserved. 2006/Q2
| CostcenterREP##inthecurrentperiod: | ||
|---|---|---|
| Activity Planned Fixed Price Type Activity | VariablePrice | ScheduledActivity |
| CostCenter: REP## | Interpretation: | |
|---|---|---|
| Actualcosts: | ||
| Actualactivities: | ||
| Targetcosts: | Sincetheoperatingrate=0: Allplanfixed costs (Comparisoncostsifthereiszerooutput) | |
| Plancosts: | Allfixedandvariableplancosts (seenextpageofreportonright-handside) |
第 195 页 / 共 257 页
AC412 Lesson: Target Cost Analysis
Task 3:
1. From the sender cost centerREP##, allocate140hoursof activitytype
REPH## to cost center PC## using direct activity allocation (since the
activitytypeisofactivitytypecategory1). Allocatethehoursinthescreen
variant “cost center” in list entry.
2. AnalyzethetargetcostsagainforthecostcenterREP##.
Howhigh are thetarget costson the debit side (previously 10,000.00),
since the operating rate is 140%?
How did the system calculate this?
Cost center REP##, current period
Targetcosts:
Calculation:
3. NowposttheactualcostsofcostcenterREP##incomponentFI.Usethe
currentdateandchoosethescreenvariantwithcostcenterandquantity.
Choose the control indicator V0 (no control). Remember to enter the
quantity110honthedetailsscreenofcostcenter415100.
Tosimplifyentry,youcanuseaccountassignmenttemplateAC412band
justchangethecostcenterstoyournumber##.
G/L Debit/Credit Amount Tax Cost Quan- Unit
Account tity
Ind Center
icator
404000 D 900 V0 REP##
415100 D 12,100 V0 REP## 110 H
430000 D 9,000 REP##
470000 D 1,000 V0 REP##
113100 H 23,000
Compareallyour amountsandthenchoosePost.
Continued on next page
181
2006/Q2 © 2006 SAP AG. All rights reserved.
| Cost center REP##, current period | |
|---|---|
| Targetcosts: | |
| Calculation: |
| G/L Account | Debit/Credit Ind icator | Amount | Tax | Cost Center | Quan- tity | Unit |
|---|---|---|---|---|---|---|
| 404000 | D | 900 | V0 | REP## | ||
| 415100 | D | 12,100 | V0 | REP## | 110 | H |
| 430000 | D | 9,000 | REP## | |||
| 470000 | D | 1,000 | V0 | REP## | ||
| 113100 | H | 23,000 |
第 196 页 / 共 257 页
Unit4: Period-endclosing AC412
4. You have recorded your costs for the entire period. Now you want to
analyze the cost effectiveness of the cost center using the
target/actual comparison report. Analyze the balance of cost
center REP##, the plan/actual variance and the target/actual
variance for the input side. Then answer the following questions:
Cost center REP##, current periodplan/actual variance:
%Assessment: Favorable/unfavorable (2nd page in report):
Fillintheblankstocompletethesentence.
5. Target/actualvariance: %Assessment: Favorable/unfavorable:
Fillintheblankstocompletethesentence.
6. Underabsorption/Overabsorption: (Howmuchmore
or less was allocated than was actually debited to the cost center?)
Fillintheblankstocompletethesentence.
182
©2006SAPAG.Allrightsreserved. 2006/Q2
第 197 页 / 共 257 页
AC412 Lesson: Target Cost Analysis
Solution 7: Target Cost Analysis
Task 1:
Preparation:
1. Inyourusersettings,deletegroupH_TECH##fromthecostcentergroup,
and enter cost center REP## instead.
a) Preparation: Toselectusersettings, choose:
CCA: Information System→User Settings
Basicdata: RemovethecostcentergroupH_TECH##andreplaceit
with the cost center REP##.
Task 2:
Checking the plan costs
1. NoactualcostshavebeenpostedtoyourcostcenterREP##forthecurrent
period. Viewtheplannedvaluesbygoingtocostelementplanning(version
0, current period, cost centerREP##, activitytype*[=all], cost elements
400000–699999,freeentry). Whichthreecostelementshavebeenplanned
uptonow? Whatvalueswereplannedforthesecostelements? Forwhich
costelementdidyousetthe“Recordquantity”indicator?
CostCenter: REP##forthecurrentperiod:
Activity Cost Plan Variable Quan- Variable Units Q
tity
Type Type Costs
Fixed
Fixed
(Ifthefieldforactivitytypeisblank(or#),wasactivity-independent/fixed
planning carried out?)
Continued on next page
183
2006/Q2 © 2006 SAP AG. All rights reserved.
| CostCenter: REP##forthecurrentperiod: | |||||
|---|---|---|---|---|---|
| Activity Cost Plan Type Type Costs Fixed | Variable | Quan- tity Fixed | Variable | Units Q | |
第 198 页 / 共 257 页
Unit4: Period-endclosing AC412
Compareyourplanwiththesolution,andchangethevaluesifneeded.
a) CCA:Planning→CostandActivityInputs→Change
Layout: 1-101
Version: 0
Timeperiod: Currentperiodincurrentfiscalyear
Cost center: REP##
Activitytype: *
Costelement: from 400000 to 699999
Free entry
Overview
CostCenter: REP##forthecurrentperiod:
Activity- Cost- Plan- Vari- Quan- Vari- Units Q
Type Type Costs able tity able
Fixed
Fixed
430000 9.000,-
470000 1.000,-
REPH## 415100 — 10.000,- – 100 h X
If the field for the activity type is empty, then the planning data is
activity-independent(onlyfixed). Checkyourplanagainstthesolution
and make changes if necessary.
ThetotalplancostisEUR20,000. Wages(430000)andoffice/building
costs(470000)arefixed. Theexternalactivities(415100)arevariable.
External activities are given a variable quantity whose indicator Q
togetherwithunithcausesthesystemtoissueawarningduringactual
postingstoenteraquantityforaccountassignment. Thereforeatotalof
10,000infixedcostsand10,000invariablecostsisplanned.
2. Analyzetheplannedoutputof yourcostcenter REP##inplanning of the
activity output.
Whatactivityquantities(activitytype*)wereplannedinthecurrentperiod?
What price did you calculate earlier for this quantity (the price was
automaticallytransferredintoplanningduringpricecalculation)?
What activity quantity was scheduled?
Comparethiswiththevalueinthesolutionsandmakechangesifnecessary.
Continued on next page
184
©2006SAPAG.Allrightsreserved. 2006/Q2
| CostCenter: REP##forthecurrentperiod: | ||||
|---|---|---|---|---|
| Activity- Cost- Plan- Type Type Costs Fixed | Vari- able | Quan- Vari- Units tity able Fixed | Q | |
| 430000 9.000,- | ||||
| 470000 1.000,- | ||||
| REPH## 415100 — 10.000,- – 100 h X |